Dlr Group, Inc. v. Oskaloosa Community School District M&M Enterprises And Story Construction Co.

CourtCourt of Appeals of Iowa
DecidedFebruary 10, 2016
Docket15-0356
StatusPublished

This text of Dlr Group, Inc. v. Oskaloosa Community School District M&M Enterprises And Story Construction Co. (Dlr Group, Inc. v. Oskaloosa Community School District M&M Enterprises And Story Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dlr Group, Inc. v. Oskaloosa Community School District M&M Enterprises And Story Construction Co., (iowactapp 2016).

Opinion

IN THE COURT OF APPEALS OF IOWA

No. 15-0356 Filed February 10, 2016

DLR GROUP, INC., Petitioner-Appellant,

vs.

OSKALOOSA COMMUNITY SCHOOL DISTRICT; M&M ENTERPRISES; and STORY CONSTRUCTION CO., Respondents-Appellees. ________________________________________________________________

Appeal from the Iowa District Court for Polk County, Richard G. Blane II,

Judge.

DLR Group, Inc. appeals the district court’s denial of its motion to vacate

the arbitration award and the court’s approval of the arbitration award.

AFFIRMED.

Keith A. Harvat and Daniel J. Epstein of Houghton, Vandenack, Williams,

Whitted, Weaver, Parsonage, L.L.C., Omaha, Nebraska, for appellant.

Edward W. Remsburg and Jason M. Craig of Ahlers & Cooney, P.C., for

appellee Oskaloosa Community School District.

Mark A. Schultheis of Nyemaster Goode P.C., Des Moines, for appellee

Story Construction.

F. Richard Lyford of Dickinson, Mackaman, Tyler & Hagen, P.C., Des

Moines, for appellee M&M Enterprises.

Heard by Tabor, P.J., and Bower and McDonald, JJ. Blane, S.J., takes no

part. 2

BOWER, Judge.

DLR Group, Inc. (DLR) appeals the district court’s denial of its motion to

vacate the arbitration award and the court’s approval of Oskaloosa Community

School District’s (District) motion to confirm the arbitration award. We affirm.

I. BACKGROUND FACTS AND PROCEEDINGS

We incorporate the district court’s summary of the factual background:

This case involves construction at the Oskaloosa High School. The District entered into separate contracts with DLR, Story [Construction Company], and M&M [Enterprises]. The design for the project was prepared by DLR in 2001 and 2002. The District hired Story to perform construction management services on the project. The District hired M&M to perform general construction services, including pouring the concrete floors at the high school. M&M constructed the floors for the school in three layers. The first layer was a vapor barrier, the second was three to four inches of rock fill, and the third layer was concrete. The concrete slab-on-grade floors in the high school were poured by M&M from March 2003 through May 2003. The floor slabs were poured by M&M in such a way that humps and unlevel floors resulted. Repairs to fix the levelness issues generally occurred in November of 2003. M&M and Skold Construction used leveling compounds to level the floor. All of the leveling work and leveling products used by M&M and Skold were approved by DLR. After the repair work in 2003, vinyl composite tiles were placed on the floor slabs by another contractor, Poindexter. As early as 2004, the vinyl composite tiles started to bubble. As a result of this condition, the vinyl floor tiles had to be removed, the leveling compounds had to be removed to expose the original concrete floor slabs, a moisture resistant floor sealer with leveling materials installed, and then the vinyl floor tiles had to be reinstalled.

The parties agreed their dispute concerning the flooring defects should be

submitted to arbitration. The District claimed DLR breached sections 1.1.1,

1.2.3.8, 2.4.4.1, 2.6.2.1, and 2.6.2.2 of the contract. Before the arbitration

hearing, on July 2, 2013, DLR filed a motion for summary judgment, arguing the 3

District’s claims were barred by the statute of limitations. DLR asserted, although

the District’s requests were pled as a breach of contract, their claims were

actually for professional negligence and barred by the five-year statute of

limitations pursuant to Iowa Code section 614.1(4) (2013). After reviewing the

resistances filed by M&M and the District, the arbitrator found the District’s claims

were properly submitted as contract claims and denied DLR’s motion.

The arbitration hearing was held December 10 through 12, 2013. On the

morning of December 10, DLR notified the parties it had retained a court reporter

to transcribe the proceedings but the court reporter would be late. DLR’s counsel

agreed the parties should begin the proceeding without the reporter.

Consequently, the direct examination of the District’s first witness, David

Dickinson,1 was not reported.

The arbitrator issued his decision on January 28, 2014, finding in favor of

the District. The arbitrator found the three respondents had breached the

contract and were jointly and severally liable for damages in the amount of

$304,500. Concerning DLR, the arbitrator found it had violated “section 1.2.3.6

of its agreement with the District when it recommended both the process and

products to be used in correcting the unlevel floors” and it had not “acted in the

best interest of the District.”

On April 25, 2014, DLR filed a petition at law in the district court to vacate

the arbitration award, claiming the arbitrator had exceeded his powers and

1 Dickinson served as an Oskaloosa School Board member from 2002–2005. He has formal education and training in construction matters and has taught construction-related classes at Iowa State University. Dickinson testified about the concrete floors being poured in 2003 before the building was enclosed. 4

substantial evidence did not support the arbitrator’s ruling. See Iowa Code

§ 679A.12(1)(c), (f). DLR noted substantial evidence did not support the finding

DLR had breached section 1.2.3.6 because the District had never claimed DLR

had violated that section and there was no evidence presented to support this

claim. The District then filed a motion to submit the case to the arbitrator for a

nunc pro tunc order or, in the alternative, for permission to obtain an affidavit

from the arbitrator. The District believed the arbitrator likely made a clerical error

in finding DLR breached 1.2.3.6 of the agreement, instead of section 1.2.3.8., as

the District had never alleged violation of 1.2.3.6 and the language used by the

arbitrator was consistent with the language from section 1.2.3.8.

The district court granted the District’s motion on September 22, and

returned the case back to the arbitrator for “clarifying by him as to whether he

made a drafting or typographical error in referring to section 1.2.3.6 instead of

section 1.2.3.8.” The arbitrator responded to the request by filing an amended

award. The amended award changed the citation on page fourteen from 1.2.3.6

to 1.2.3.8—no other changes were made.

On October 3, 2014, DLR filed a motion to vacate the amended arbitration

award. Following oral arguments, on January 28 the district court denied DLR’s

motion to vacate. On February 19, the District filed a motion to confirm the

amended arbitration award. On February 25, DLR filed a notice of appeal from

the denial of its motion to vacate the arbitration award. On February 26, the

district court entered an order confirming the arbitration award, which was 5

appealed by DLR on March 27. The two appeals were consolidated for our

review.

II. SCOPE AND STANDARD OF REVIEW

A party may appeal a district court order confirming or entering judgment

on an arbitration award pursuant to Iowa Code section 679A.17(1)(c) and (f).

Section 679A.17(2) provides we review the appeal of an arbitration award “in the

manner and to the same extent as from orders or judgments in a civil action.”

Our review is therefore for correction of errors at law. Ales v. Anderson,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ales v. Anderson, Gabelmann, Lower & Whitlow, P.C.
728 N.W.2d 832 (Supreme Court of Iowa, 2007)
State v. Dohlman
725 N.W.2d 428 (Supreme Court of Iowa, 2006)
Baker v. City of Iowa City
750 N.W.2d 93 (Supreme Court of Iowa, 2008)
Humphreys v. Joe Johnston Law Firm, P.C.
491 N.W.2d 513 (Supreme Court of Iowa, 1992)
$99 Down Payment, Inc. v. Garard
592 N.W.2d 691 (Supreme Court of Iowa, 1999)
Reicks v. Farmers Commodities Corp.
474 N.W.2d 809 (Supreme Court of Iowa, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
Dlr Group, Inc. v. Oskaloosa Community School District M&M Enterprises And Story Construction Co., Counsel Stack Legal Research, https://law.counselstack.com/opinion/dlr-group-inc-v-oskaloosa-community-school-district-mm-enterprises-and-iowactapp-2016.