D.J. Simmons, Inc. v. Broaddus

116 F. App'x 964
CourtCourt of Appeals for the Tenth Circuit
DecidedDecember 1, 2004
Docket03-2010, 03-2024, 03-2041
StatusUnpublished
Cited by1 cases

This text of 116 F. App'x 964 (D.J. Simmons, Inc. v. Broaddus) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
D.J. Simmons, Inc. v. Broaddus, 116 F. App'x 964 (10th Cir. 2004).

Opinion

ORDER AND JUDGMENT *

McKAY, Circuit Judge.

After examining the briefs and appellate record, this panel has determined unani *966 mously that oral argument would not materially assist the determination of these appeals. See Fed. R.App. P. 34(a)(2); 10th Cir. R. 34.1(G). The cases are therefore ordered submitted without oral argument.

After a bench trial, the district court determined that defendants B/R Energy Partners, Inc., Phoenix Energy Consulting Services, Inc., and F. Brian Broaddus [hereinafter “B/R Energy”] are jointly and severally liable to plaintiff D.J. Simmons, Inc., an oil and gas producer, for past-due payments for natural gas liquids B/R Energy purchased from Simmons under contracts executed in 1995, 1996, and 1998. In a subsequent order, the district court denied Simmons’ request for prejudgment interest due under the contracts but awarded postjudgment interest on the total judgment at a rate provided in the parties’ contracts. In a third order, the court modified the postjudgment interest rate and reconsidered its denial of prejudgment interest. On reconsideration, the court awarded interest on payments due under the 1995 contract, but again denied prejudgment interest on payments due under the other two contracts.

In appeal No. 03-2010, B/R Energy appeals from the award of contract damages in the district court’s November 8, 2002, order. In appeal No. 03-2024, Simmons appeals from the court’s January 7, 2003, denial of prejudgment interest on the 1996 and 1998 contracts. In appeal No. 03-2041, B/R Energy cross-appeals from the award of prejudgment interest on the 1995 contract. The three appeals have been consolidated, and our jurisdiction arises under 28 U.S.C. § 1291.

With respect to the award of contract damages, we conclude that the district court did not err in its utilization of price terms or in disallowing a marketing fee to B/R Energy. We further conclude that the district court should have enforced the parties’ agreement for prejudgment interest on past-due amounts on all three contracts. Therefore, we affirm in part and reverse in part.

I. Standard of review

We review questions of law de novo. We review findings of fact under a clearly erroneous standard. Las Vegas Ice & Cold Storage Co. v. Far W. Bank, 893 F.2d 1182, 1185 (10th Cir.1990). “A finding of fact is ‘clearly erroneous’ if it is without factual support in the record or if the appellate court, after reviewing all the evidence, is left with a definite and firm conviction that a mistake has been made.” Manning v. United States, 146 F.3d 808, 812 (10th Cir.1998) (quotation omitted). The interpretation of a contract is a legal question. See K & V Scientific Co. v. Bayerische Motoren Werke Aktiengesellschaft, 314 F.3d 494, 497 (10th Cir.2002). In resolving the legal issues in this contract action that was removed to federal court, we apply the substantive law of New Mexico. See Sanpete Water Conservancy Dist. v. Carbon Water Conservancy Dist, 226 F.3d 1170, 1178 (10th Cir.2000).

II. Relevant facts

We need not repeat the thorough recitation of facts set forth in the district court’s November 8, 2002, order except as the facts relate to the issues on appeal. B/R Energy purchased all of Simmons’ gas output at the wellheads, where it was metered *967 and then transported to the Chaco processing plant, which is owned by El Paso Field Services 1 (EPFS). Simmons agreed that costs for processing and transportation would be deducted from the price B/R Energy paid for Simmons’ gas. At Chaco, the gas was separated into “residue gas” and various liquid gas components. Simmons was to be paid , based on its yearly contract price for each component, times the number of MMBtus 2 for the various components, minus the processing, transportation, and other fees set forth in the contract. B/R Energy contracted separately with various companies who were purchasing the residue gas from B/R Energy for the transportation and processing of the gas. Those contracts were confidential.

The 1995 purchase contract did not specify what the processing fees were or how they would be determined, but Simmons admitted that the parties agreed that Simmons would pay for the processing fees. Therefore, the district court found that B/R Energy was entitled to off-set its actual processing costs, whether they were in the form of a flat rate per MMBtu or in the form of an amount of liquids retained by the processing plant in lieu of charging a processing fee, against the money it owed to Simmons.

In the 1996 and 1998 contracts, however, Simmons and B/R Energy expressly agreed that Simmons would pay a flat-rate per MMBtu for processing its gas based on the total amount of gas that was metered, no matter what the actual processing cost was to B/R Energy. Accordingly, B/R Energy reduced the gross amount due to Simmons by the flat-fee processing cost. In addition, the contracts specifically provided that Simmons would receive credit for 100% of its liquid gas production.

In 1998 Simmons discovered that the reports it received from B/R Energy indicated that Simmons was not being paid for about 40% of the liquids it was producing. Simmons questioned whether B/R Energy was double charging for processing by paying both the flat-rate processing fee and by B/R Energy not reporting or paying for the amount of liquids that Chaco retained in lieu of charging B/R Energy a processing fee. Documentary evidence obtained in discovery established that Simmons was not paid for 39% of its liquid production even though it had already paid for processing through offset by the flat-rate fee. Thus, the district court found that B/R Energy had double-charged Simmons for processing, thereby breaching its 1996 and 1998 contracts to charge only a flat rate per MMBtu for processing.

The district court also accepted Simmons’ expert’s testimony that B/R Energy had further failed to pay the proper base prices for liquid gas components under all three contracts. The court concluded that B/R Energy owed Simmons $716,806 on the 1996 contract and $489,029 on the 1998 contract, and that B/R Energy had underpaid for liquids in its 1995 contract in the amount of $130,507. The court then reduced the total amount owed by $54,750 because of a mistake Simmons’ expert admitted he had made in his audit.

The district court rejected B/R Energy’s argument that it was entitled to recover *968 marketing fees on all three contracts.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Herrera v. City of Espanola
32 F.4th 980 (Tenth Circuit, 2022)

Cite This Page — Counsel Stack

Bluebook (online)
116 F. App'x 964, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dj-simmons-inc-v-broaddus-ca10-2004.