Dixie MacHine, Weld. Mtl. Wks. v. Boulet Transp.

38 So. 2d 546, 1949 La. App. LEXIS 401
CourtLouisiana Court of Appeal
DecidedJanuary 24, 1949
DocketNo. 19020.
StatusPublished
Cited by15 cases

This text of 38 So. 2d 546 (Dixie MacHine, Weld. Mtl. Wks. v. Boulet Transp.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dixie MacHine, Weld. Mtl. Wks. v. Boulet Transp., 38 So. 2d 546, 1949 La. App. LEXIS 401 (La. Ct. App. 1949).

Opinion

Dixie Machine, Welding Metal Works, Inc., brought this suit against Milton P. Boulet, doing business as Boulet Transportation Company, alleging that, as the result of an oral agreement made with an authorized representative of Boulet, it made certain repairs to the boom of a hoisting crane belonging to Boulet; that a fair price for the work, $195.67, had been charged, and that Boulet had failed and refused to pay for the said work. Boulet denied that there had been any agreement for the repair of the said boom and alleged that the said repairs had been made necessary because of negligence of employees of plaintiff corporation which had rented the hoisting crane from Boulet and had damaged it through carelessness or lack of skill. Boulet averred that the repairs had been made voluntarily by the plaintiff corporation and that he was in no way responsible for the cost thereof. He also averred that if there was any liability in him, the price charged was excessive.

Boulet then, assuming the position of plaintiff in reconvention, averred that he had rented the said hoisting crane to plaintiff corporation and had secured an operator at the request of the said corporation; that the charges for the rental of the crane and for the reimbursement of the wages and expenses incurred in connection with the operator had been agreed upon and that as a result there was due to him by plaintiff corporation the sum of $396.80, and he prayed for judgment in reconvention for that amount against plaintiff corporation, Dixie Machine, Welding Metal Works, Inc. The amount claimed in the reconventional demand was subsequently reduced voluntarily to $356.40.

When the matter came to trial in the First City Court, counsel for plaintiff objected to any evidence in support of the reconventional demand on the ground that such evidence was irrelevant and incompetent for the reason that the reconventional demand was based on a claim not necessarily connected with nor incidental to the main demand. This objection to evidence was based on the provisions of Article 375 of our Code of Practice, which reads as follows: "In order to entitle the defendant to institute a demand, in reconvention, it is required that such demand, though different from the main action, be, nevertheless, necessarily connected with and incidental to the same * * *."

After an extended trial, there was judgment dismissing the main demand and in favor of defendant, plaintiff in reconvention, for $356.40. Plaintiff has appealed.

The record shows that Milton P. Boulet, engaged in business as Boulet Transportation Company, is the owner of a ten-ton *Page 548 crane having a sixty-foot boom, and mounted on the platform of a very large motor truck, and that this crane is used by Boulet in heavy construction work and is rented out by him to other persons doing similar work and who may need such a machine. Dixie Machine, Welding Metal Works, Inc., among other businesses in this locality, is engaged in heavy construction work.

The Dixie Company obtained a contract for the erection of a smokestack at the plant of Johns-Manville Company located on the west side of the Mississippi River.

Early in June, 1947, a representative of the Dixie Company telephoned Boulet's office and asked if it would be possible to rent the ten-ton crane of Boulet for use in the job at the Johns-Manville plant. The answer of Boulet was that that crane was not available at that particular time, but that it would be in a few weeks and that he would be glad to rent it to the Dixie Company, although, since, the crane had not yet completed the work on which it was engaged, there was no certainty as to just when it could be released to the Dixie Company. Boulet advised the Dixie Company that the charges would be $10.00 per hour and that there must be a minimum guarantee of forty hours' work. The Dixie Company agreed to wait until that crane would be available. There is considerable dispute as to whether or not, at that time, Boulet was advised as to the details of the job in which the crane was to be used.

A few weeks later the representative of the Dixie Company again called Boulet to know if the crane had completed the work on which it was then engaged. A few days later another representative of the Dixie Company called Boulet to discuss the use of the crane and advised that the Dixie Company had secured another job, also across the river, in which it would need the same crane as soon as it could complete the job at the Johns-Manville plant, and as a result it was agreed that the minimum time for which the Dixie Company would be charged in each job would be thirty-two hours.

There is also some dispute as to whether in any of these earlier conversations Boulet was asked to furnish an operator for the crane. When the crane was ultimately released from the job in which it had been engaged by Boulet, it was sent across the river to the point agreed upon and delivered to the Dixie Company. With it Boulet sent an operator, A. F. Zeagler, because prior to the time on which it was delivered he had been requested by the Dixie Company to furnish a competent operator. Zeagler reported to the superintendent or foreman of the Dixie Company, Albert Berniol, who took charge of the work and commenced the erection of the stack. During the early afternoon, while an attempt was being made to lift the stack and it was partially off the ground being raised to an upright position, the boom of the crane buckled or bent in a sidewise direction and was badly damaged. Just what was the cause of this and to whose fault it is to be attributed, we shall later discuss.

Before discussing those questions, however, it is necessary that we determine whether or not the evidence supporting the reconventional demand was properly admitted. Counsel for plaintiff vehemently protest that there was no connection whatever between the charge which they say was based on a contract for repairing the boom and the claim of Boulet based on the allegation that the damage to the crane resulted from negligence chargeable to the Dixie Company. Counsel say that only one issue was raised by the main demand and that this was whether or not there was an agreement for the repair of the crane. They say that if there was such an agreement, then there must be payment under this contract and that whether or not the Dixie Company is responsible in tort for the damage to the crane is a question not in any way connected with nor incidental to the claim made under the contract to repair the crane. We cannot agree with this view.

Defendant denies that there was a contract, but in effect says that if there was a contract for the repair of the boom, it was made necessary by the negligence of plaintiff. In other words, the tenor *Page 549 of the defense is that when it appeared that the boom had been damaged and that it was necessary that it be repaired at once in order that it might be used on that and other jobs, defendant did not object when he was advised that plaintiff could make or was making the necessary repairs, but that his acquiescence in allowing the plaintiff to make the repairs should not be construed as an admission that plaintiff was not responsible for the damage or that the defendant would pay for it. All of these contentions are so closely interwoven that it would unnecessarily extend and complicate litigation to say that defendant must go to trial on the question of whether he must pay to the Dixie Company for the repairs to his boom and then must be relegated to an entirely different and new suit to determine whether he may recover that identical amount from the Dixie Company.

Nor do we think that the cases upon which plaintiff relies, as supporting the contention that the reconventional demand should be considered, are analogous.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lambert v. Austin Bridge Company
189 So. 2d 752 (Louisiana Court of Appeal, 1966)
Truitt v. B & G Crane Service, Inc.
165 So. 2d 874 (Louisiana Court of Appeal, 1964)
McCutchen v. Fruge
132 So. 2d 917 (Louisiana Court of Appeal, 1961)
Frank Maddox v. Aetna Casualty and Surety Company
259 F.2d 51 (Fifth Circuit, 1958)
Fontenot v. National Transfer Company
99 So. 2d 795 (Louisiana Court of Appeal, 1957)
Cox v. Cashio
96 So. 2d 872 (Louisiana Court of Appeal, 1957)
Holland v. Marquette Casualty Co.
95 So. 2d 878 (Louisiana Court of Appeal, 1957)
B & G CRANE SERVICE v. Thomas W. Hooley & Sons
80 So. 2d 369 (Supreme Court of Louisiana, 1955)
Johnson v. Royal Indemnity Co.
206 F.2d 561 (Fifth Circuit, 1953)
Johnson v. Royal Indemnity Co.
104 F. Supp. 821 (W.D. Louisiana, 1952)
Benoit v. Hunt Tool Co.
45 So. 2d 512 (Louisiana Court of Appeal, 1950)

Cite This Page — Counsel Stack

Bluebook (online)
38 So. 2d 546, 1949 La. App. LEXIS 401, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dixie-machine-weld-mtl-wks-v-boulet-transp-lactapp-1949.