DiVeto v. Bell Trucking, Inc.

CourtSuperior Court of Maine
DecidedAugust 24, 2004
DocketPENcv-03-198and04-18
StatusUnpublished

This text of DiVeto v. Bell Trucking, Inc. (DiVeto v. Bell Trucking, Inc.) is published on Counsel Stack Legal Research, covering Superior Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
DiVeto v. Bell Trucking, Inc., (Me. Super. Ct. 2004).

Opinion

STATE OF MAINE SUPERIOR COURT PENOBSCOT, SS CIVIL ACTION

Docket Nos. CV-03-198/CV-04-18

Anthony DiVeto et al., Plaintiffs

Bell Trucking, Inc. et al.,

Defendants THtHtt+t4+44+44 +444 py Order DOMALM EE pers ho Bell Trucking, Inc. et al, SEP is G04 Plaintiffs —

Anthony DiVeto et al., Defendants

Anthony DiVeto and Cynthia DiVeto (collectively, DiVeto) entered into a contract under which Bel] Trucking, Inc. and Alan R. Lyford, Inc. (collectively, Bell), operating as general contractors, built a residential structure for them. When DiVeto failed to pay the amount due to Bell under the contract, Bell filed a mechanic’s lien in the Washington County Registry of Deeds and then sought to enforce that lien in an action filed in the District Court (Machias). Through that action, Bell sought recovery of approximately $18,500. In the court proceeding, Bell moved to enforce the arbitration provision of the construction contract, which provided, “In the event of any disputes under this contract the parties agree to binding arbitration in accordance with standard

AIA procedures.” The court granted Bell’s motion and ordered the parties to proceed to arbitration. Prior to the arbitration hearing, the parties submitted to the arbitrators written statements of their positions, Through counsel, DiVeto argued that Bell’s performance under the construction contract “failed to meet the contractual and implied warranties of workmanlike construction.” DiVeto claimed damages of nearly $75,000.

An arbitration hearing was held. The parties presented documentary and testimonial evidence. In a decision issued on J uly 14, 2003, the arbitrators gave notice of their conclusion that DiVeto had failed to pay $16,000 due under the parties’ contract but that DiVeto had established gross damages of $34,034.57 due to defective construction or other breaches of the construction contract. This entitled DiVeto to a net recovery of $18,034.57 from Bell. Bell wrote to the arbitrators requesting clarification, and the arbitrators responded in writing with further explanation for the basis of their decision. The arbitrators, however, did not modify their ultimate conclusion and award.

In October 2003, Bell filed a motion in the District Court action to vacate the arbitration award. Several weeks later, DiVeto filed a separate action in the Superior Court (Penobscot County) to confirm the arbitration award. The District Court action

was then consolidated with the Superior Court matter.! The parties have agreed to submit

‘the pending matters (Bell’s motion to vacate the arbitration award, and DiVéto’s motion ~~

to confirm that award) on the basis of the written submissions previously filed. The court has reviewed those submissions,

Bell makes two arguments against confirmation of the award. First, Bell contends that the arbitrators exceeded the scope of their authority when they issued a decision that rested on DiVeto’s claims of defective performance. Second, it argues that the award itself is defective because the basis for the decision is unclear. The court concludes that neither contention is sufficient to preclude confirmation of the award.

Under 14 M.R.S.A. § 5938(1)(B), a court may vacate an arbitration award where “[t]he arbitrators exceeded their powers... .” Bell contends that because DiVeto had not

filed a counterclaim in the District Court action, the arbitrators were limited to a

cases were consolidated in the Superior Court in Penobscot County, thus eliminating any venue problems affecting the District Court case.

N consideration of DiVeto’s alleged non-payment and, at least, could not issue an affirmative award to DiVeto. This contention, however, does not account for the comprehensive contractual language creating the parties’ obligation to arbitrate in the first place: “any dispute under the [construction] contract” is subject to mandatory and binding mediation. One need not even resort to the expansive construction given to arbitration provisions, see Bennett y. Prawer, 2001 ME 172, { 8, 786 A.2d 605, 608, to conclude that DiVeto’s claim against Bell was well within the scope of the arbitration provision in this contract.

As part of this argument, Bell also argues that the evidence was insufficient to Support any conclusion reached by the arbitrators that DiVeto’s damages exceeded the amount sought by Bell in the first place. A decision based on any insufficiency of the evidence, however, is not one that exceeds the arbitrators’ powers. In the Matter of Arbitration Between: Eljer Manufacturing, Inc. v. Kowin Dey. Corp., 14 F.3d 1250, 1255-56 (7" Cir. 1994) (an award that exceeds the arbitrators’ powers is one that “exceeds the powers delegated to [the arbitrators] by the parties.” (Emphasis added.)).

That is not the case here. Bell initiated the arbitration process, which, under the contract,

included all disputed matters arising under the parties’ construction contract. -N othing in ~

this record suggests that the arbitrators decided any matter outside of those parameters.

Even beyond this, the documentary evidence presented to the arbitrators, which is at least partially included in Bell’s court filings, belies the suggestion that the arbitrators exceeded the issues developed by the parties. Indeed, DiVeto sought an award of damages far in excess of the amount determined by the arbitrators. Further, because Bell has not provided the court with a transcript or other meaningful record of the arbitration proceeding, it is not possible to glean the substance of the evidence that the parties presented to the arbitrators. Thus, Bell cannot succeed in its present argument, which would rest on an analysis of the hearing record. R.C. Audette & Sons Inc. y. LaRochelle, 373 A.2d 1226, 1228 (Me. 1977).

Bell next urges that the arbitration award should be vacated because the arbitrators did not adequately explain the basis for the decision and that it is therefore “incomplete or unclear.” Bell correctly notes that an arbitration decision is unenforceable

if it is unclear or incomplete. Hearst Corp. v. Swiss Bank Corp., 584 A.2d 655, 658 (Me. 1991). Here, however, the arbitrators’ decision was both clear and complete. With numerical precision, it established the amount that Bell owes DiVeto. Further, it is complete because it addresses the parties’ competing claims. As a clear and complete decision, it is valid and enforceable.

The essence of Bell’s argument, in actuality, is a challenge to the evidentiary basis and to the reasoning underlying the arbitration award. These are not grounds that can support an order vacating an arbitration award. See Stockade Enterprises v. Ahl, 905 P.2d 156, 158 (Mont. 1995) (construing Montana statute materially identical to 14 MLR.S.A. §§ 5938 and 5939). The grounds for such an order are set out in section 5938, and the sufficiency of the evidence is not among them. Thus, Bell’s analysis of the merits of the arbitration decision cannot lead to an order vacating that award.

The limits of any relief to which Bell might be entitled is shown even more clearly in the distinction between sections 5938 and 5939. In the latter, if an arbitration decision is affected by “an evident miscalculation of figures,” then the court itself may modify or correct the award. Bell has argued that the arbitrators’ assessment of DiVeto’s damages does not reflect the evidence of damages as DiVeto claimed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stockade Enterprises v. Ahl
905 P.2d 156 (Montana Supreme Court, 1995)
Bennett v. Prawer
2001 ME 172 (Supreme Judicial Court of Maine, 2001)
Hearst Corp. v. Swiss Bank Corp., New York Branch
584 A.2d 655 (Supreme Judicial Court of Maine, 1991)
R. C. Audette & Sons, Inc. v. LaRochelle
373 A.2d 1226 (Supreme Judicial Court of Maine, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
DiVeto v. Bell Trucking, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/diveto-v-bell-trucking-inc-mesuperct-2004.