Diversified Building Systems LLC v. Penn Construction Group Inc

District Court, W.D. Oklahoma·Decided January 23, 2024·No. 5:22-cv-00801·Unknown

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF OKLAHOMA

THE UNITED STATES FOR THE USE ) AND BENEFIT OF DIVERSIFIED ) BUILDING SYSTEMS LLC, a Florida ) limited liability company, ) ) Plaintiff, ) ) v. ) Case No. CIV-22-801-D ) PENN CONSTRUCTION GROUP, ) INCORPORATED, a Texas for-profit ) corporation; KORTE CONSTRUCTION ) COMPANY, a Missouri for-profit ) corporation; and TRAVELERS CASUALTY ) AND SURETY COMPANY OF AMERICA, ) a Connecticut insurance corporation, ) ) Defendants. )

ORDER

Before the Court is the Motion for Partial Summary Judgment [Doc. No. 51] filed by Plaintiff, the United States for the Use and Benefit of Diversified Building Systems, LLC. Defendant, Penn Construction Group, Inc. (Penn), filed a response [Doc. No. 57], to which Plaintiff replied [Doc. No. 59]. 1 The matter is fully briefed and at issue. BACKGROUND This litigation stems from a construction project to build a fuel maintenance hangar and depot maintenance hangar at Tinker Air Force Base. Korte Construction Company was

1 Initially, Plaintiff also moved for summary judgment on its Miller Act claim against Defendants Korte and Travelers [Doc. No. 51]. Thereafter, Plaintiff reached a settlement as to all claims against Korte and Travelers [Doc. No. 74]. Accordingly, the only issue remaining is Plaintiff’s motion for partial summary judgment for its claims against Penn. awarded the prime contract, and Korte hired Penn as a first-tier subcontractor. Penn then entered into a verbal agreement with Plaintiff to provide skilled labor services for the

project. The verbal agreement between Plaintiff and Penn was negotiated by Plaintiff’s President, Tom Vermeesch, and Penn’s Build Director, Michael Luessi. As alleged by Plaintiff, the verbal agreement for the Tinker project was identical to a previous verbal agreement between Penn and Plaintiff for a federal construction project at the Mayport naval facilities in Florida. Plaintiff asserts that the following terms were the only terms

governing the subcontract for the Tinker project: Plaintiff would pay its skilled workforce at pre-existing hourly rates, plus overtime and standard benefits, based on the workers’ timesheets; Penn would be charged a flat $65 per hour worked; and Penn would pay Plaintiff upon receiving invoices. The scope of the subcontract between Plaintiff and Penn is disputed. Plaintiff alleges

that the original scope of the Tinker project was for Plaintiff’s crews to install IMP panels at the fuel hangar. However, Plaintiff asserts that Penn then expanded the scope of Plaintiff’s services and directed Plaintiff’s workers to: repair, rebuild, and reinstall significant parts of the fuel hangar; take over the remaining framing and roofing needed for the depot hangar; and then install IMP panels at both hangars. According to Plaintiff,

all work performed by Plaintiff’s crews was supervised by Penn’s Construction Manager, Don Harrold, and Penn’s Superintendent, David Cox. Penn alleges that Mr. Luessi and Mr. Vermeesch met in person on May 25, 2021, and agreed to additional terms. According to Penn, Plaintiff agreed “on payment of $65.00 per manhour with a 4.5-man crew achieving production at the standard installation rates of 25 to 30 metal wall panels per day and 3,000 roof squares per day, and that payment would

be reduced if the agreed-to production levels were not met.” [Doc. No. 57, at 10]. Penn further alleges that Plaintiff also agreed to provide supervision for its own crews. Plaintiff alleges that Penn ultimately stopped paying Plaintiff’s invoices by mid- November of 2021. After Penn asked Korte for assistance in getting payment, Penn paid a portion of the outstanding invoices for Plaintiff’s work on the depot hangar, but refused to pay for Plaintiff’s services related to the panel installation at the fuel hangar. Penn’s refusal

to pay Plaintiff’s invoices caused Plaintiff to pull its crews from the Tinker project in February of 2022. Plaintiff contends that Mr. Luessi (Penn’s Build Director) had not been forthcoming to Korte about the “true expanded scope of work performed by [Plaintiff’s] skilled crews and had been instead claiming that [Plaintiff’s] crews had only done the IMP panel installation at the fuel hangar….” [Doc. No. 51, at 3].

Six weeks after Plaintiff removed its crews from the Tinker project, Mr. Luessi sent Mr. Vermeesch a text message purporting to release Plaintiff from the project. Plaintiff alleges that Mr. Luessi also attempted to modify the existing terms of Plaintiff’s verbal agreement with Penn “by stating for the first time that the verbal agreement made in June [of] 2021 was to pay [Plaintiff’s] laborers not only ‘the $65 per hour rate’ but that the rate

would be adjusted ‘using an industry standard install time’….” [Doc. No. 51, at 13]. Plaintiff alleges that its invoices for the Tinker project remain unpaid in the amount of $541,736.99. Plaintiff filed suit against Penn for breach of contract, quantum meruit, and unjust enrichment. With the present motion, Plaintiff seeks summary judgment on its quantum meruit and unjust enrichment claims against Penn. In response, Penn contends that Plaintiff cannot obtain summary judgment on its quasi-contract claims because 1) an

express contract exists between the parties; and 2) the terms of the express contract are in dispute. STANDARD OF DECISION Summary judgment is proper “if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” FED. R. CIV. P. 56(a). A material fact is one that “might affect the outcome of the suit

under the governing law.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). A dispute is genuine if the facts and evidence are such that a reasonable jury could return a verdict for the nonmoving party. Anderson, 477 U.S. at 248. All facts and reasonable inferences must be viewed in the light most favorable to the nonmovant. Id. at 255. The inquiry is whether the facts and evidence identified by the parties present “a sufficient

disagreement to require submission to a jury or whether it is so one-sided that one party must prevail as a matter of law.” Id. at 251-52. DISCUSSION I. Motion to Strike Exhibits to Penn’s Summary Judgment Response For the reasons set forth in the Court’s previous Order [Doc. No. 75] the Court construes Plaintiff’s Motion to Strike [Doc. No. 58] as Plaintiff’s objection to various

exhibits attached to Defendants’ responses to Plaintiff’s motion for partial summary judgment. Specific to Penn, Plaintiff objects to Exhibits D, E, F, I, and H2 to the Declaration of Michael Luessi, attached to Penn’s response as Exhibit No. 1 [Doc. No. 57-1].

Exhibit D is an e-mail from Plaintiff’s President, Mr. Vermeesch, to Penn’s management, Don Harrold, David Cox, and Michael Luessi [Doc. No. 57-2, at 33-34]. Attached to Mr. Vermeesch’s e-mail is an October 20, 2021 letter from Nucor Buildings Group, notifying Mr. Vermeesch that Plaintiff was successful “in completing all requirements for approval and certification to supervise the installation of products” presumably needed for the Tinker project. Id. at 35.

Exhibit E is a series of e-mails between Korte and Penn employees, to include Mr. Luessi, in which they discuss Plaintiff’s certification approval and Korte’s request that Penn provide “something on [Penn’s] letterhead stating [Plaintiff] is [Penn’s] second tier subcontractor….” Id. at 36-40. Attached to Exhibit E is the certification letter from Nucor and a November 3, 2021 letter from Penn referring to Plaintiff as its subcontractor. Id. at

Free access — add to your briefcase to read the full text and ask questions with AI

Diversified Building Systems LLC v. Penn Construction Group Inc, (W.D. Okla. 2024).

Diversified Building Systems LLC v. Penn Construction Group Inc (Diversified Building Systems LLC v. Penn Construction Group Inc) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
McCurdy Group, LLC v. American Biomedical Group, Inc.
9 F. App'x 822 (Tenth Circuit, 2001)
Harvell v. Goodyear Tire and Rubber Co.
2006 OK 24 (Supreme Court of Oklahoma, 2007)
KRUG v. HELMERICH & PAYNE, INC.
2015 OK 74 (Supreme Court of Oklahoma, 2015)
AMERICAN BIOMEDICAL GROUP, INC. v. TECHTROL, INC.
2016 OK 55 (Supreme Court of Oklahoma, 2016)