District of Columbia v. Camden Iron Works

15 App. D.C. 198, 1899 U.S. App. LEXIS 3507
CourtCourt of Appeals for the D.C. Circuit
DecidedJanuary 9, 1899
DocketNo. 894
StatusPublished
Cited by1 cases

This text of 15 App. D.C. 198 (District of Columbia v. Camden Iron Works) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
District of Columbia v. Camden Iron Works, 15 App. D.C. 198, 1899 U.S. App. LEXIS 3507 (D.C. Cir. 1899).

Opinion

Mr. Chief Justice Alvey

delivered the opinion of the Court:

This action was brought by the appellee, the Camden Iron Works, a corporation created under the laws of the State of New Jersey, against the District of Columbia, to recover the price of certain iron pipes manufactured for and delivered to the defendant by the plaintiff, under contract under seal. This action is brought in covenant, upon the theory and according to the contention of the plaintiff, that the contract is a specialty contract of the defendant, and one of the principal questions in the case is, whether the agreement sued on is the deed of the defendant, or only a simple contract.

There were several pleas interposed, — all going to and denying the right of the plaintiff to recover, — though some of them in form are appropriate only to an action of assumpsit; but among the pleas is the plea of non est factum. There is no question made, however, as to the inconsistency or inappropriateness of the pleas, and issue was joined on them all, except the plea of the Statute of Limitations, to which a demurrer was entered; and the demurrer was sustained and the plea ruled bad. This plea of the Statute of Limitations [210]*210of-three years was pleaded as a bar, upon, the theory that the proper action upon the contract was assumpsit, and not covenant. But the court did not entertain that view, and accordingly ruled the plea bad on demurrer.

The contract bears date the 29th day of June, 1887, and on its face and by its terms it professes to be made by the District of Columbia, of the first part, and the Camden Iron Works, by Walter Wood, president, of the second part. The contract is conceded to have been for and in behalf of the municipal corporation of the District of Columbia, and for material to be supplied for the water department of the District of Columbia; and the contract throughout professes to be made by and between the District' of Columbia and the Camden Iron Works. The conclusion of the contract is as follows:

“In witness whereof, the undersigned, William B. Webb, Samuel E. Wheatley, and William. Ludlow, Commissioners of the District of Columbia, appointed under the Act of Congress entitled ‘An act providing a permanent form of government for the District of Columbia,’ approved June 11,1878, and the party of the second part to these presents, have hereunto set their hands and seals the day and year first above written.
“William B. Webb [l. s.]
“S. E. Wheatley [l. s.]
“ William Ludlow [l. s.]
Commissioners of the District of Columbia.
[Corporate Seal ' “WALTER Wood,
Ironworks.] “Pres’t Camden Iron Works.
Signed and sealed in the presence of—
“E. H. Dieeenbach.”

This contract was proved and offered in evidence by the plaintiff, but its admissibility was objected to by the defendant, upon the ground that the declaration was in covenant, declaring upon a sealed instrument, whereas the contract [211]*211offered in evidence is not under the corporate seal of the District of Columbia, and therefore not the covenant of the defendant, but a simple contract merely. The objection being overruled, the defendant excepted.

The plaintiff then proved that the municipal corporation of the District of Columbia had a corporate seal, but that the same had not been generally used, until after the contract here sued upon had been executed, and had only been used in executing deeds of conveyance, and instruments of that character. And the plaintiff further proved by competent evidence, that though the contract bears date the 29th of June, it was not in fact executed and delivered by the Commissioners before August 4, 1887. This proof was also objected to by the defendant; and the objection was taken upon the ground that it was not competent to the plaintiff to show by parol evidence that the real or true date of the contract was other or different from that stated on its face; and that the plaintiff was estopped from showing by parol that the contract was not in fact signed by the defendant, and did not go into effect until a date subsequent to that expressed in the instrument. This objection was likewise overruled by the court, and the defendant excepted.

The contract provided -for the manufacture of certain designated sizes of iron pipe by the plaintiff, and its complete delivery to the defendant, “ within 136 days after the date of the execution of the contract; one-half of each size to be delivered on or before September 25, 1887, and the remainder on or before November 10, 1887.” For failure to deliver the pipes within the time thus fixed, the contract provided that there should “ be deducted from the contract price, as in said contract specified, one per cent, of the contract price for all delinquent articles for each and every week day that they remained delinquent.” There was a further provision that for failure to complete the work at the time specified, there should be deducted from the money to become due under the contract “ the sum of ten dollars per diem for the [212]*212same period estimated as liquidated and fixed damages to the District.”

In the contract there was provision made for inspecting the iron pipes and “ to determine whether there was any reason for rejection, prior to delivery.” Payments were to be made after August 1, 1887, for all pipe “ received and accepted in proper order and condition, less 20 per cent, of the amount found due, to be reserved until the satisfactory completion of the contract.”

There appears to have been a suspension in the execution of the contract, owing to misunderstandings as to the qualities of the work, and the inspection thereof; and consequently, but a small proportion of the pipe was delivered prior to November 30, 1887. But after that date, pipe worth $11,404.09, at contract rates, according to estimate made, was delivered to and accepted by the District of Columbia, and used by the corporation. The total value, at contract rates, of all the pipe delivered to and accepted by the District of Columbia, was $16,335.87, on which there was paid in cash $5,291.71, by two checks, which did not indicate that they were meant to be in full settlement of all moneys due under the contract; and the balance, $11,044.16, was more than counterbalanced by the fines and penalties charged up by the defendant for non-delivery of the pipe within the time specified in the contract. It was for this balance of $11,044.16, with interest thereon from the 27th of February, 1888, that this action was brought. There is no pretense that there was any demand made by the defendant for any more or other quantity of pipe than that delivered under the contract and which was refused to be-delivered by the plaintiff. On the contrary, on November 30, 1887, when Captain Symons, the Assistant Engineer Commissioner of the District, requested that no more pipe should be cast, for delivery under the contract, there remained to be cast about 340,000 pounds, on which the profits to the plaintiff, at contract prices, would have been [213]*213about $1,300. After the plaintiff’s letter of November 30, 1887, assenting to the cancelation of the contract, as to all pipe not then manufactured,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Melwin Construction Co. v. Stonewall Construction Co.
113 A.2d 108 (District of Columbia Court of Appeals, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
15 App. D.C. 198, 1899 U.S. App. LEXIS 3507, Counsel Stack Legal Research, https://law.counselstack.com/opinion/district-of-columbia-v-camden-iron-works-cadc-1899.