Diponio Contracting Inc v. City of Howell

CourtMichigan Court of Appeals
DecidedApril 14, 2015
Docket319295
StatusUnpublished

This text of Diponio Contracting Inc v. City of Howell (Diponio Contracting Inc v. City of Howell) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Diponio Contracting Inc v. City of Howell, (Mich. Ct. App. 2015).

Opinion

STATE OF MICHIGAN

COURT OF APPEALS

DIPONIO CONTRACTING, INC., UNPUBLISHED April 14, 2015 Plaintiff/Counter-Defendant- Appellee,

v No. 319295 Livingston Circuit Court CITY OF HOWELL, LC No. 11-026309-CK

Defendant/Counter-Plaintiff- Appellant.

Before: OWENS, P.J., and JANSEN and MURRAY, JJ.

PER CURIAM.

This contract dispute arises from a road reconstruction project. Defendant appeals as of right from the trial court’s amended judgment for plaintiff DiPonio Contracting, Inc. (hereinafter DCI). Defendant contends that the trial court erred when it awarded it a setoff limited to 10 days of liquidated damages, totaling $15,500, on its counterclaim against plaintiff. We affirm.

I. BACKGROUND

In January 2010, DCI bid on and was awarded a construction project for defendant known as the Multi Year Road Improvement Program, Phase II. The project involved the installation of new roads, sanitary sewer, water lines, and storm sewers. Engineering firm Hubbell, Roth & Clark (HRC) served as the project manager. The contract provided that construction was to begin “no earlier than May 3, 2010.” The project was originally designed and bid as a road replacement project with a small quantity of sanitary/storm sewer work. However, after the contract was awarded, DCI received a set of revised plans, at least one significant change order, and several contract modifications between the starting date in May, and the ultimate final completion date in July 2011. DCI was also asked by defendant, at least twice, to stop work and make some emergency repairs that were unrelated to the road project.

Ultimately, the roads were completely topped and available for safe use by the motoring public, with all traffic control devices installed, on November 21, 2010. DCI continued to work on the project until December 2, performing clean-up at the site as well as “raking topsoil for greenbelt restoration.” Some signs were also installed. HRC considered December 9 the seasonal shut down date for the project.

-1- On May 4, 2011, DCI received a three-page letter from HRC containing numerous punch list items. DCI informed HRC that it was treating the letter as the “final” punch list for the project and that it would “entertain no additional punch lists whatsoever.” DCI returned to the project on May 16, 2011 to complete the additional punch list items; DCI completed its work on May 20. DCI believed the project was completed on May 26 when its subcontractor completed the road striping.

However, a June 16, 2011 construction pay estimate report reflected liquidated damages, calculated as “32 calendar days, from May 16, 2011 to June 16, 2011, at $1,550 per day for a total of $49,600. These liquidated damages will continue to be charged until the project is completed.” HRC contended that DCI did not complete the contract until State Barricades placed street name signs on July 1, 2011. However, the June 20, 2011 contract modification indicated that it was requested “to add the following items to the contract.” The “new items” were street signs, and the reason provided was, “The plans called for replacement, but a new pay item was negotiated to install new post, mounting brackets, and street ‘name’ signs.” DCI believed that, because defendant changed the brackets that were to be used to hang the signs in June 2011, defendant prevented DCI from completing the project, which precluded defendant from being entitled to liquidated damages.

Ultimately, the project as completed cost less than the project as awarded including change order 1. There were no outstanding construction issues or quality issues. Nevertheless, defendant refused to pay DCI the remaining $121,872.52 due under the contract.1

On October 11, 2011, DCI filed a complaint against defendant, alleging breach of contract and unjust enrichment. Defendant filed a counter-complaint against DCI, alleging that, under the contract, it was entitled to liquidated damages of $88,350 for DCI’s failure to complete the project on time. After a seven-day bench trial,2 the trial court explained that it “generally adopt[ed] plaintiff’s finding of facts,” the result of which was an award for DCI for the full amount of its contract claim, $121,872.51, set off by an award to defendant of 10 days of liquidated damages at a rate of $1,550 a day, or $15,500, equating to a net judgment of $106,372.51, plus statutory interest. An amended judgment was subsequently entered that included an award to DCI of $24,381.20, plus statutory interest, for post-case evaluation taxable costs and attorney fees pursuant to MCR 2.403(O).

II. STANDARD OF REVIEW

We review a trial court’s findings of fact in a bench trial for clear error and its conclusions of law de novo. Chelsea Investment Group, LLC v City of Chelsea, 288 Mich App

1 DCI’s original contract bid was $2,058,608.30. After the unit prices were amended because of the work in change order 1, the contract as awarded was $2,463,242.80. The total undisputed amount due under the contract was $2,444,417.48. DCI received $2,322,544.97. 2 The complaint included DCI’s request for $14,225.07 for additional traffic-control devices. The trial court denied relief on this issue and it has not been cross-appealed.

-2- 239, 250; 792 NW2d 781 (2010). “A finding is clearly erroneous if there is no evidentiary support for it or if this Court is left with a definite and firm conviction that a mistake has been made.” Id. “Special deference is given to the trial court’s findings when they are based on the credibility of the witnesses.” Woodington v Shokoohi, 288 Mich App 352, 355; 792 NW2d 63 (2010). Questions involving the proper interpretation and legal effect of a contract are reviewed de novo. Alpha Capital Mgt, Inc v Rentenbach, 287 Mich App 589, 611; 792 NW2d 344 (2010).

III. EXTENSION REQUESTS

Defendant argues that the trial court’s determination that it wrongfully denied DCI’s requests for extensions of time was clear error and contrary to the contract. Defendant focuses on the contract provision found in section 4.2:

If the Contractor shall be unavoidably delayed in beginning or fulfilling this Contract by reason . . . of extra Work ordered by the City or by an act, neglect, delay or default on the part of the City then the completion date specified may be advanced as the Engineer or Inspector, whose duties and authority are defined in the General Conditions, may adjudge to be just and reasonable. Formal claim for such extension shall be made in writing by the Contractor within seven (7) days after the date upon which such alleged cause of delay shall have occurred.

The parties agree that §§ 108.09 and 108.10 of the MDOT 2003 Standard Specifications for Construction (DX B) apply. Those provisions provide as follows:

108.09 Extension Of Time On Calendar Day or Calendar Date Contracts. When the contract time is specified in calendar days or by calendar date, an extension of the time for opening to traffic and the contract time will be allowed by the Engineer without liquidated damages on each of the following basis:

* * *

C. If there are delays due to unforeseen causes beyond the control and without the fault or negligence of the Contractor, including but not restricted to: . . . acts of Government, acts of State or any political subdivision . . . , then the extension will be the time the delay affects the controlling operation.

E. On a controlling operation, when there is an increase in the quantities set forth in the contract and this is not offset by decreased similar controlling items of work, the extension of time will be based on Formula 108-2.

Ec = Tc x I/Q Formula 108-2

where:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Quality Products and Concepts Co. v. Nagel Precision, Inc.
666 N.W.2d 251 (Michigan Supreme Court, 2003)
Michigan National Bank v. Holland-Dozier-Holland Sound Studios
250 N.W.2d 532 (Michigan Court of Appeals, 1976)
Detroit Police Officers Association v. Detroit
551 N.W.2d 349 (Michigan Supreme Court, 1996)
Schroeder v. Terra Energy, Ltd.
565 N.W.2d 887 (Michigan Court of Appeals, 1997)
Alpha Capital Management, Inc. v. Rentenbach
792 N.W.2d 344 (Michigan Court of Appeals, 2010)
Dancey v. Travelers Property Casualty Co. of America
792 N.W.2d 372 (Michigan Court of Appeals, 2010)
Chelsea Investment Group LLC v. City of Chelsea
792 N.W.2d 781 (Michigan Court of Appeals, 2010)
Woodington v. Shokoohi
792 N.W.2d 63 (Michigan Court of Appeals, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
Diponio Contracting Inc v. City of Howell, Counsel Stack Legal Research, https://law.counselstack.com/opinion/diponio-contracting-inc-v-city-of-howell-michctapp-2015.