Digesare Mech., Inc. v. U.W. Marx, Inc.

2019 NY Slip Op 7668
CourtAppellate Division of the Supreme Court of the State of New York
DecidedOctober 24, 2019
Docket527775
StatusPublished

This text of 2019 NY Slip Op 7668 (Digesare Mech., Inc. v. U.W. Marx, Inc.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Digesare Mech., Inc. v. U.W. Marx, Inc., 2019 NY Slip Op 7668 (N.Y. Ct. App. 2019).

Opinion

Digesare Mech., Inc. v U.W. Marx, Inc. (2019 NY Slip Op 07668)
Digesare Mech., Inc. v U.W. Marx, Inc.
2019 NY Slip Op 07668
Decided on October 24, 2019
Appellate Division, Third Department
Published by New York State Law Reporting Bureau pursuant to Judiciary Law § 431.
This opinion is uncorrected and subject to revision before publication in the Official Reports.


Decided and Entered: October 24, 2019

527775

[*1]Digesare Mechanical, Inc., Appellant,

v

U.W. Marx, Inc., et al., Respondents.


Calendar Date: September 5, 2019
Before: Garry, P.J., Lynch, Mulvey and Devine, JJ.

Couch Dale Marshall PC, Latham (Mark W. Couch of counsel), for appellant.

Mastropietro Law Group, PLLC, Saratoga Springs (Nathan C. Woodward of counsel), for respondents.



Garry, P.J.

Appeal from an order of the Supreme Court (Fisher, J.), entered August 28, 2018 in Ulster County, which, among other things, granted defendants' cross motion for summary judgment dismissing the complaint against defendant U.W. Marx, Inc.

Defendant U.W. Marx, Inc. (hereinafter Marx) was the contractor to the Dormitory Authority of the State of New York (hereinafter DASNY) on a public improvement project for the construction of a residence hall. In 2013, Marx hired plaintiff as a subcontractor pursuant to a written agreement (hereinafter the subcontractor agreement). Defendant Liberty Mutual Insurance Company, the surety for the project, issued a labor and material payment bond pursuant to State Finance Law § 137. In April 2017, following the completion of the project, plaintiff commenced this breach of contract action alleging that Marx had not fully paid plaintiff for its work on the project (first three causes of action). Plaintiff further claimed payment from Liberty Mutual pursuant to the bond agreement (fourth cause of action). Marx joined issue alleging, among other things, that the unpaid funds were properly withheld as damages for delays and faulty workmanship. Liberty Mutual likewise joined issue and denied liability.

Plaintiff moved for summary judgment on its first, second and fourth causes of action, and defendants cross-moved for summary judgment dismissing the complaint against Marx. Supreme Court denied plaintiff's motion, finding that a triable issue of fact existed as to whether Marx had breached the contract, and granted defendants' cross motion for summary judgment dismissing the complaint against Marx on the ground that plaintiff's claims against Marx were time-barred by a six-month limitation period set forth in the subcontractor agreement. The court further searched the record and determined that plaintiff's claim against Liberty Mutual (fourth cause of action) was time-barred pursuant to the bond agreement and granted summary judgment to Liberty Mutual dismissing the complaint against it. Plaintiff appeals.

The parties to a contract are free to agree in writing to shorten the six-year limitations period for breach of contract so long as "the intent to do so is expressed in clear terms and the time period is reasonable" (Whitney Lane Holdings, LLC v Don Realty, LLC, 159 AD3d 1163, 1165 [2018]; see CPLR 201, 213; John J. Kassner & Co. v City of New York, 46 NY2d 544, 550-551 [1979]). Here, the subcontractor agreement provided that "[a]ny claim by [plaintiff] against [Marx] must be filed . . . within six (6) months after [plaintiff's] last day of work on the [p]roject site." Marx established in defendants' cross motion for summary judgment that plaintiff's last day of work on the project was October 13, 2015, and that plaintiff commenced this action more than six months later, in April 2017. In finding the action to be time-barred, Supreme Court rejected plaintiff's contention that the shortened limitation period was unreasonable, noting that courts have previously found comparable six-month limitation periods to be enforceable (see e.g. Dart Mech. Corp. v City of New York, 121 AD3d 452, 452 [2014]; Top Quality Wood Work Corp. v City of New York, 191 AD2d 264, 264 [1993]). However, whether a shortened contractual limitation period is "fair and reasonable [depends upon] . . . the circumstances of each particular case. . . . The circumstances, not the time, must be the determining factor" (Executive Plaza, LLC v Peerless Ins. Co., 22 NY3d 511, 519 [2014] [internal quotation marks and citation omitted]). Under the circumstances presented here, we find that the six-month limitation period was unreasonable, and therefore reverse the dismissal of the complaint against Marx.

The subcontractor agreement provided for plaintiff to receive monthly progress payments while work on the project was ongoing, less a specified percentage withheld as retainage, to be paid within seven days after Marx received payment from DASNY. Plaintiff was entitled to final payment of the entire unpaid balance following completion of the project and upon Marx's receipt of payment from DASNY. Plaintiff established that it submitted a total of 20 invoices to Marx for its work on the project; Marx paid plaintiff for the first 15 of these invoices, but neither paid the amounts claimed in the final five invoices nor gave plaintiff written notice of disapproval of any of the invoices as required by the subcontractor agreement.[FN1] In addition, plaintiff submitted pleadings from a separate litigation commenced by Marx against DASNY and the project architect. In that action, Marx had asserted that its work had been delayed by design defects and other errors and omissions on the part of DASNY and the project architect, and that DASNY had failed to make full payment to Marx for its work. DASNY counterclaimed against Marx for delay damages. Plaintiff submitted evidence revealing that this litigation was settled in February 2018, and that Marx received a settlement payment from DASNY thereafter. Plaintiff asserts that this settlement amount constituted DASNY's final payment to Marx within the meaning of the subcontractor agreement. Therefore, plaintiff argues that Marx's contractual obligation to make final payment to plaintiff was not triggered, and plaintiff's cause of action for breach of contract did not accrue until the settlement was paid in 2018 — long after the six-month contractual limitation period expired in 2016.

Although there is nothing inherently unreasonable about the contractual six-month limitation period, "an otherwise reasonable limitation period may be rendered unreasonable by an inappropriate accrual date" (Executive Plaza, LLC v Peerless Ins. Co., 22 NY3d at 519). The enforceability of a contractual accrual date depends upon "whether the plaintiff had a reasonable opportunity to commence its action within the period of limitation" (id. [internal quotation marks and citation omitted]). Here, plaintiff had no such opportunity, because the timing of its payment was subject to a condition — Marx's receipt of payment from DASNY — that plaintiff could not control and that did not occur before the limitation period expired (see D & S Restoration, Inc. v Wenger Constr. Co., Inc., 160 AD3d 924, 926 [2018]). Had plaintiff attempted to commence an action within the six-month period, the action would have been subject to dismissal as premature, as plaintiff's claim had not yet accrued.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

A.C. Legnetto Construction, Inc. v. Hartford Fire Insurance
702 N.E.2d 830 (New York Court of Appeals, 1998)
Beal Savings Bank v. Sommer
865 N.E.2d 1210 (New York Court of Appeals, 2007)
John J. Kassner & Co. v. City of New York
389 N.E.2d 99 (New York Court of Appeals, 1979)
Schuler-Haas Electric Co. v. Aetna Casualty & Surety Co.
357 N.E.2d 1003 (New York Court of Appeals, 1976)
Dart Mechanical Corp. v. City of New York
121 A.D.3d 452 (Appellate Division of the Supreme Court of New York, 2014)
Hyman v. Schwartz
127 A.D.3d 1281 (Appellate Division of the Supreme Court of New York, 2015)
In Re the Estate of Shambo
138 A.D.3d 1215 (Appellate Division of the Supreme Court of New York, 2016)
Executive Plaza, LLC v. Peerless Insurance
5 N.E.3d 989 (New York Court of Appeals, 2014)
Zuckerman v. City of New York
404 N.E.2d 718 (New York Court of Appeals, 1980)
West-Fair Electric Contractors v. Aetna Casualty & Surety Co.
661 N.E.2d 967 (New York Court of Appeals, 1995)
Kingsley Arms, Inc. v. Sano Rubin Construction Co.
16 A.D.3d 813 (Appellate Division of the Supreme Court of New York, 2005)
George S. May International Co. v. Thirsty Moose, Inc.
19 A.D.3d 721 (Appellate Division of the Supreme Court of New York, 2005)
American Building Contractors Associates, Inc. v. Mica & Wood Creations, LLC
23 A.D.3d 322 (Appellate Division of the Supreme Court of New York, 2005)
Allied Environmental Group, Inc. v. Samson Construction Co.
36 A.D.3d 521 (Appellate Division of the Supreme Court of New York, 2007)
Top Quality Wood Work Corp. v. City of New York
191 A.D.2d 264 (Appellate Division of the Supreme Court of New York, 1993)
Swing Staging, Inc. v. Hartford Fire Insurance
269 A.D.2d 193 (Appellate Division of the Supreme Court of New York, 2000)
Jovee Contracting Corp. v. AIA Environmental Corp.
283 A.D.2d 398 (Appellate Division of the Supreme Court of New York, 2001)
Convenient Medical Care, P.C. v. Medical Business Associates, Inc.
291 A.D.2d 617 (Appellate Division of the Supreme Court of New York, 2002)
Baluk v. New York Central Mutual Fire Insurance
126 A.D.3d 1426 (Appellate Division of the Supreme Court of New York, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
2019 NY Slip Op 7668, Counsel Stack Legal Research, https://law.counselstack.com/opinion/digesare-mech-inc-v-uw-marx-inc-nyappdiv-2019.