This text of 468 F. Supp. 1050 (Dicon, Inc. v. Clearspan Construction Co.) is published on Counsel Stack Legal Research, covering District Court, E.D. Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dicon, Inc. v. Clearspan Construction Co., 468 F. Supp. 1050, 1979 U.S. Dist. LEXIS 13653 (E.D. Mo. 1979).

Opinion

MEMORANDUM

WANGELIN, District Judge.

The above entitled action arose from the construction of a fifty unit leased housing project in Charleston, Missouri, known as Project MO 12-3. The case was tried to the Court sitting without a jury. The following [1051]*1051discussion constitutes the Court’s findings of fact and conclusions of law.

This Court has jurisdiction pursuant to 28 U.S.C. § 1332, there being complete diversity of citizenship among the parties, and the amount in controversy exceeding the sum of Ten Thousand Dollars ($10,000), excluding interest and costs.

Defendant and third-party plaintiff Marben Corporation (hereinafter Marben) was the developer of the “turnkey” project, see 24 C.F.R. § 1272 et seq. (1975), who was to arrange for its financing and construction and then transfer the completed project over to a not-for-profit corporation, which in turn leases it to a housing authority. The developer’s function is to arrange for financing of the project, approval of the plans from the Department of Housing and Urban Development (HUD) (HUD in turn enters into an annual contribution contract providing a fixed subsidy to the Housing Authority) and cause construction of the project.

Clearspan was asked to submit a bid on the project as general contractor, and Marben forwarded a contract for construction of the project to Clearspan dated July 27, 1972. In a letter dated August 18, 1972, Robert Lafferty, Senior Vice President of Marben, acknowledged that Clearspan’s signature on the construction contract dated July 27 was conditioned upon final approval of the plans and specifications by the HUD area office in St. Louis, Missouri. The letter went on to indicate that the final contract price would also be subject to revision after subcontractor bids were obtained.

Clearspan requested on September 22, 1972 that their May 1, 1973 completion deadline on the project be extended equal to the amount of time which elapsed, between execution of the contract and final approval of the plans by HUD, and on October 16, 1972 requested a June 16, 1973 deadline. In a generally worded letter dated November 15,1972, after the entrance of Dicon, Marben agreed to extend the completion date without specifying a deadline.

As the above negotiations were taking place and before Clearspan could begin construction, David Bonner, their principal superintendent on the project, was killed in an automobile accident. Clearspan Construction Company was purchased by and merged into Redman Industries.

On account of the foregoing circumstances, Clearspan entered into negotiations with Marben to remove itself as the project’s general contractor. Clearspan approached Dicon, who indicated their willingness to assume the role.

Finally, after several discussions, Marben learned that it could not formally substitute general contractors because of the necessity of individual consent from all the project’s bond holders. The parties agreed to carry out the substitution by redrafting the agreement and calling it a subcontract. This Court finds that the substance of the transaction was clearly and convincingly a novation whereby Marben, Clearspan and Dicon mutually agreed to discharge Clearspan from its obligations as general contractor and substitute Dicon in its stead. McHenry v. Claspill, 545 S.W.2d 690, 692 (St.L.Mo.App.1976); Charles Kahn & Company v. Sobery, 355 F.Supp. 156, 162 (E.D.Mo.1972). The conduct of the parties after the agreement is fully consistent with this determination, at least as to events transpiring prior to the genesis of this litigation.

Resolution of this issue is dispositive of various indemnity claims in the case. It will therefore be ordered that Dicon’s claim against Clearspan be dismissed without prejudice, that Marben’s cross-claim against Clearspan be dismissed without prejudice, that Clearspan’s counter-claim against Di-con be dismissed without prejudice, that the cross-claim of Clearspan against Marben be dismissed without prejudice, and that Clear-span’s third-party complaint against Marx & Bensdorf, Inc. be dismissed without prejudice.

All that remains is a determination of Dicon’s claim against Marben, since Marben in its reply brief has stated that it is no longer pursuing its counterclaim. Marben’s counterclaim against Dicon will therefore be dismissed without prejudice.

[1052]*1052Dicon’s contract with Marben, executed November 7, 1972, provided for a $650,000 contract price and a June 1,1973 completion date. Dicon argues entitlement to Clear-span’s proposal to Marben that the completion date be extended equal to the delay in securing final plans from HUD. This proposal for extension of time is important in that the contract between Dicon and Marben provided for the assessment of liquidated damages in the amount of $200 per day for delay in completion of the project. The aforesaid contract also contained a provision incorporating the Marben-Clearspan contract of July 27, 1972. As of November 7, 1972 final plans had not been approved by HUD, and in fact were not forthcoming until May 16, 1973.

The Court has previously noted that in a letter dated November 15, 1972, Marben agreed with Clearspan “to extend the completion date and all other terms of the contract to your contract”. However, if the communications between the parties are taken in logical sequence, the above quoted language applies to the October 16, 1972 letter from Clearspan to Marben requesting a June 16, 1973 completion date, and not the letter from Clearspan to Marben written on September 22, 1972 requesting a grace period concomitant with any delay in receiving plans from HUD. As such, the Court finds the completion date for the Dicon-Marben contract to be June 16, 1973. Plaintiff argues that the delay in obtaining a final set of approved plans prevented their performance and therefore the contract completion date should nonetheless be extended by an amount equal to the delay. This argument finds very little evidentiary support. It is uncontroverted that work on the project continued from and after the date Dicon took over the job. Indeed, requisitions submitted by Dicon to Marben in April and May of 1973 show continuing progress on the project. As to alterations in the plans by HUD which required additional work, or alteration to work previously done, the Court finds that Dicon assumed the risk of any delays occasioned by the absence of final plans from HUD by signing a contract with a fixed completion date with full knowledge that no final plans had yet been received by HUD. Further, it is apparent to the Court that Dicon itself caused or contributed to cause many time problems. Dicon supplied a labor force which was unfamiliar with component panel projects. Dicon failed to adequately supervise the brick work on the project thus necessitating taking the bricks off four buildings, at least one of the buildings was laid out backwards and required corrective work. Dicon’s supervisor created problems by using an old set of plans after being advised to use a revised set.

The completion date of the project must be determined for the purpose of computing Marben’s set off for liquidated damages.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Charles Kahn & Company v. Sobery
355 F. Supp. 156 (E.D. Missouri, 1972)
Southwest Engineering Co. v. Reorganized School District R-9
434 S.W.2d 743 (Missouri Court of Appeals, 1968)
McHenry v. Claspill
545 S.W.2d 690 (Missouri Court of Appeals, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
468 F. Supp. 1050, 1979 U.S. Dist. LEXIS 13653, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dicon-inc-v-clearspan-construction-co-moed-1979.