Dickson Construction, Inc. v. Fidelity & Deposit Co. of Maryland

960 S.W.2d 845, 1997 WL 716056
CourtCourt of Appeals of Texas
DecidedFebruary 4, 1998
Docket06-97-00031-CV
StatusPublished
Cited by53 cases

This text of 960 S.W.2d 845 (Dickson Construction, Inc. v. Fidelity & Deposit Co. of Maryland) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dickson Construction, Inc. v. Fidelity & Deposit Co. of Maryland, 960 S.W.2d 845, 1997 WL 716056 (Tex. Ct. App. 1998).

Opinions

OPINION

GRANT, Justice.

Dickson Construction, Inc. appeals an adverse summary judgment ruling in favor of Fidelity and Deposit Company of Maryland (F & D), Hibbs-Hallmark & Company (Hibbs-Hallmark), and Billy Hibbs, president of Hibbs-Hallmark. Dickson brought suit against the three defendants in the court below for business disparagement, tortious interference, and in the alternative, fraud, civil conspiracy, and breach of fiduciary duty. Additionally, Dickson sued F & D alternatively for violations of Article 21.21 of the Insurance Code and breach of the duty of good faith and fair dealing. Summary judgment was granted on the basis of the affirmative defense of the statute of limitations.

On appeal, Dickson complains that the trial court erred in finding that Dickson’s claims were barred by the statute of limitations (1) because limitations was extended by the discovery rule and because the acts amounted to a continuous tort, and (2) because the trial court was premature in ruling on the motion for summary judgment because discovery was incomplete.

In October, 1986, Dickson contacted Hibbs-Hallmark about securing bonding for a $2 million bid with the U.S. Army Corps of Engineers. F & D agreed to provide the requested bonding based upon that information. Later that same month, Dickson told F & D and Hibbs-Hallmark that it had entered into the bonded, excavation contract for the sum of $3,098,000. F & D issued the bond through Hibbs-Hallmark, an independent insurance agency. Dickson paid the initial premium charge of $29,000, an amount based on the contract’s initial sum. Dickson commenced work on April 22, 1987, but because of adverse weather conditions, the completion date was extended 250 days with the approval of the Corps of Engineers. Despite this approved delay, Dickson completed its obligations ahead of the modified time allowed. Because the material to be excavated was less than anticipated, the contract was modified to reduce the original contract, creating an underrun. However, at the Corps of Engineer’s request, Dickson performed additional work for which it became entitled to additional payment. After these modifications were made, the final contract increased to $3,608,546.40. The Corps of Engineers accepted the completed work on August 17, 1990, and paid Dickson the modified contract sum.

In December 1990, the Corps of Engineers processed two modifications increasing the amount of the contract as a result of additional work it required of Dickson. At the Corps of Engineer’s request, Dickson tried to obtain F & D’s execution of a consent of surety form through Hibbs-Hallmark to recognize the contract increase. F & D and Hibbs-Hallmark demanded that before the form would be executed, Dickson would first have to pay $8,164 additional bond premium. F & D and Hibbs-Hallmark asserted a claim [848]*848against Dickson for an overrun premium and a 21% additional premium surcharge for the extra time it took for Dickson to complete the contract. Dickson disputed this claim. Although the Corps of Engineers confirmed to F & D the total contract price, F & D did not reduce the overrun premium.

In March 1992, the Corps of Engineers agreed to increase the contract another $737,000 due to additional work it required of Dickson. Again, a request was made to F & D to execute the consent of surety form, and again, it was refused.

In January 1993, F & D and Hibbs-Hall-mark made an additional demand upon Dickson to pay an additional premium of $14,340 due to the latest contract modifications. The only alleged defamatory, false statement made by F & D or Hibbs-Hallmark regarding Dickson was a comment made by F & D employee John Barnes to Jim Bass, a third party, in January 1993, wherein Barnes stated that Dickson did not pay his bills.

Because of F & D’s continuous refusal to execute the consent and surety form, because of F & D’s miscalculations in reaching the $14,340 amount when it excluded the under-run and imposed a 22% surcharge on the revised bond premium due to an alleged 22-month delay in performing the contract, and because of Hibbs-Hallmark’s two letters to Dickson threatening legal action dated January 12 and April 29, 1993, Dickson filed a formal complaint with the Texas Department of Insurance (TDI), attacking F & D’s surcharge demands. The TDI notified F &.D of the complaint on June 1,1993, and requested a formal response pursuant to the Texas Insurance Code. On June 15, 1993, F & D responded by letter, acknowledging their mistake in calculating the surcharge amount and canceling the extra time surcharge. However, F & D still insisted on an overrun premium of $3,523. The TDI notified Dickson of this letter on July 29, 1993. Dickson filed suit on March 9,1995.

Dickson asserts that prior to June 15, 1993, Dickson’s bonding capacity was so restricted that it was unable to effectively bid on large, bonded contracts. Further, Dickson asserts that Hibbs-Hallmark did not protect Dickson’s interests, but assisted F & D in furthering the alleged wrongful conduct. Dickson also contends that F & D, Hibbs-Hallmark, and/or Hibbs circulated disparaging credit information about Dickson within the business community.

STANDARD OF REVIEW

A defendant who moves for summary judgment based upon an affirmative defense must plead the affirmative defense and prove each element of that defense as a matter of law, leaving no issues of material fact.1 The reviewing court must examine the evidence in the light most favorable to the nonmovant and indulge every reasonable inference in favor of the nonmovant, resolving all doubts in the nonmovant’s favor.2

The trial court granted the summary judgment in this case solely on the basis of the statute of limitations affirmative defense. However, the Texas Supreme Court has recently held in Cincinnati Life Insurance Co. v. Cates3 that when a trial court grants summary judgment on specific grounds, the court of appeals should consider all summary judgment grounds preserved for appellate review in the interest of judicial economy even if those were not the grounds upon which the trial court granted the summary judgment. For that reason, we consider not only the contentions involving the affirmative defenses of statute of limitations, but on the cause of action in which we found the statute of limitations has not run as a matter of law, we address whether the movant has offered proof destroying one of the elements as a matter of law.

STATUTE OF LIMITATIONS

Most tort actions not dealt with in another statute are governed by the two-year statute [849]*849of Imitations. For example, courts have held that the following causes of action are governed by the two-year statute of limitations: legal malpractice, negligence and gross negligence, and intentional infliction of emotional distress.

Chapter 16 of the Texas Civil Practice and Remedies Code and case law interpreting that chapter provide the requisite statute of limitations periods for most of the various causes of action before us. Under Section 16.003,4 a cause of action alleging a breach of the duty of good faith and fair dealing must be filed within two years of the accrual of the cause of action,5 along with civil conspiracy,6 tortious interference with business relations,7

Free access — add to your briefcase to read the full text and ask questions with AI

Related

U.S. Bank, N.A. v. Smith (In re Smith)
524 B.R. 125 (S.D. Texas, 2015)
Tim Hotchkin v. Glen Bucy
Court of Appeals of Texas, 2014
Houston Poly Bag I, Ltd v. Ken Kujanek
370 S.W.3d 82 (Court of Appeals of Texas, 2012)
Curt Anthony Porter v. State
Court of Appeals of Texas, 2008
Albert Alexander v. State
Court of Appeals of Texas, 2007
Texas Disposal Systems Landfill, Inc. v. Waste Management Holdings, Inc.
219 S.W.3d 563 (Court of Appeals of Texas, 2007)
Henry Gauna v. State
Court of Appeals of Texas, 2006
James Ray Blake v. State
Court of Appeals of Texas, 2006
Krohn v. Marcus Cable Associates, L.P.
201 S.W.3d 876 (Court of Appeals of Texas, 2006)
Alfred Plough, Jr. v. Cecilia Reynolds
Court of Appeals of Texas, 2006
Gary Moyer v. Marsha Ann Moyer
Court of Appeals of Texas, 2005
Malone v. Sewell
168 S.W.3d 243 (Court of Appeals of Texas, 2005)
Shaun Malone v. Barbara Sewell
Court of Appeals of Texas, 2005
Rogers v. Ardella Veigel Inter Vivos Trust No. 2
162 S.W.3d 281 (Court of Appeals of Texas, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
960 S.W.2d 845, 1997 WL 716056, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dickson-construction-inc-v-fidelity-deposit-co-of-maryland-texapp-1998.