Dickerson Const. Co., Inc. v. Process Eng.

341 So. 2d 646
CourtMississippi Supreme Court
DecidedJanuary 12, 1977
Docket49023
StatusPublished
Cited by8 cases

This text of 341 So. 2d 646 (Dickerson Const. Co., Inc. v. Process Eng.) is published on Counsel Stack Legal Research, covering Mississippi Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dickerson Const. Co., Inc. v. Process Eng., 341 So. 2d 646 (Mich. 1977).

Opinion

341 So.2d 646 (1977)

DICKERSON CONSTRUCTION COMPANY, INC., et al.
v.
PROCESS ENGINEERING COMPANY, INC.

No. 49023.

Supreme Court of Mississippi.

January 12, 1977.

Watkins & Eager, P.N. Harkins, III, Velia Ann Mayer, Young, Scanlon & Sessums, James Leon Young, Jackson, for appellant.

John R. Poole, Percy Stanfield, Jr., Brown & Stanfield, Jackson, for appellee.

Before GILLESPIE, SUGG and BROOM, JJ.

GILLESPIE, Chief Justice, for the Court.

This appeal involves, among other things, the extent of a firm of Architects-Engineers' duty to administer or supervise the construction of a building and the sufficiency of proof as to the alleged failure of the contractor to execute the contract.

Process Engineering Company, Inc. (hereinafter Owner), sued Dickerson Construction Company, Inc. (hereinafter Contractor), and William H. Cooke, Jr., Nelson Lee Douglass and Robert Earl Farr, d/b/a Cooke-Douglass-Farr, Ltd. (hereinafter Architects-Engineers). Owner charged Architects-Engineers with failure to properly design the building in question and failure to properly supervise construction, and charged Contractor with failure to follow the plans and specifications of the Architects-Engineers. Owner charged that these omissions were the proximate cause of the damages to the building and that the defendants were jointly liable to Owner.

*647 After a jury trial and verdict, the Circuit Court of Hinds County entered judgment for the Owner against the Architects-Engineers and Contractor for $105,000.

In the latter part of 1967, Architects-Engineers undertook to design, prepare plans and specifications for, and administer the construction of a commercial building to house Owner's metal treatment and plating operations. Pursuant to a written contract, plans and specifications were prepared by Architects-Engineers, who also prepared all contracts and handled the advertisement for bids. On October 16, 1967, Contractor and Owner entered into a contract to construct the building for the sum of $100,845. The plans and specifications were made a part of the construction contract.

Prior to the date of contract between Owner and Architects-Engineers, and upon the advice of the latter, Owner employed Ware-Lind Engineers, Inc. (hereinafter Soil Engineers), to test the soil and make recommendations with reference to the type of foundation and drainage on the lot where the building was to be constructed. The Soil Engineers made a written report to Architects-Engineers, stating that beginning about five to seven feet below the surface was a layer of expansive soil known as Yazoo clay. It was recommended that surface grading be kept to a certain minimum so as not to remove the non-expansive top soil more than necessary, and to provide piers to at least twenty feet below the existing grade. The Soil Engineers also recommended, that in order to insulate the exterior grade beams from swelling pressures of the expansive clay, voids be formed under the grade beams (the reinforced concrete beams resting on the piling or piers which in turn support the walls and roof) and that the void be formed by using cardboard boxes filled with vermiculite. The proof showed that the cardboard boxes filled with vermiculite would hold the weight of the concrete when poured to form the grade beams and the cardboard boxes would disintegrate, leaving a void filled with vermiculite. The vermiculite would prevent soil from sloughing in from the side into the void and at the same time would yield to pressure from below created by the expansive Yazoo clay. The Soil Engineers also recommended that the soil under the floor slab be of a select clay or non-expansive sandy clay compacted uniformly. It was further recommended that "drainage around the building, particularly in the rear, east side, should provide rapid surface run-off of storm water away from the foundation."

The building was completed and occupied in the spring of 1968, and Owner paid all of the charges made by the Architects-Engineers and the Contractor. About six months after Owner moved into the building, the wall around the front canopy began to crack and a representative of the Architects-Engineers inspected the building at Owner's request and installed a metal brace under the canopy. The front wall continued to crack. The roof began to leak within less than a year, and the building continued to deteriorate. The concrete blocks in various parts of the building were crushed, the wall cracked and buckled, cracks developed in the concrete floor slab, the building leaked, requiring numerous repairs, and the panelling in the office walls buckled. There is no dispute that the building by the spring of 1974 had sustained extensive damages. In February, 1974, holes were dug in and around the building both by the Owner and by the Architects-Engineers to try to determine what caused the building to deteriorate. The water table under and around the building was within two or three feet of the surface, depending upon where the hole was dug. Prior to construction the water table was about ten feet lower.

Although it was undisputed that the building sustained severe damage by the expansive forces of Yazoo clay, it was hotly disputed as to why the Yazoo clay became saturated with water and whether or not the grade beams suffered structural damage.

The basic structural components of the building should be distinguished from the floor slab. The weight of the walls and roof was supported by pilings and grade *648 beams. Grade beams are reinforced concrete poured across the pilings. The slab was free-flowing in the sense that it did not support the outside walls and roof. The plans called for cardboard boxes (Jay voids) to be placed under the grade beams to act as a safety valve. When the Yazoo clay begins to expand, the voids would absorb the expansion.

The Owner's testimony indicates that the voids had not been formed under the grade beams as specified by the plans. The Owner's testimony also indicates that backfill in and around the grade beams consisted of Yazoo clay and not a select backfill. The theory of the Owner is that the damage to the building resulted mainly from the failure of the Contractor to construct drainage ditches or swells on the east side of the building as called for by the plans and as recommended by the Soil Engineers. This failure caused the ponding of water and the saturation of the Yazoo clay. The resulting expansion caused a lateral movement (due to improper backfill) as well as an upward movement (due to the lack of voids) in the grade beams. The Owner's testimony indicated that the grade beams suffered structural stress and cracks. Also due to improper drainage, the floor slab heaved upward causing damage.

The Architects-Engineers urge that there was no movement of the grade beams and that the grade beams did not show any signs of stress. They urge that the damage to the building was caused entirely by the heaving of the floor slab. It is their contention that the Owner negligently allowed chemicals used by Owner to deteriorate the floor slab and erode the epoxy lined waste discharge pipe located under the slab. As a result of this deterioration in the slab and in the pipes, water used by Owner was allowed to saturate the ground under the floor slab. Following this saturation, the Yazoo clay expanded, forcing the floor slab upward and thus causing all the damage to the building. They deny that the damage to the building was caused by the expansion of the Yazoo clay under the grade beams.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hobson v. Waggoner Engineering, Inc.
878 So. 2d 68 (Court of Appeals of Mississippi, 2003)
AmSouth Bank v. Gupta
838 So. 2d 205 (Mississippi Supreme Court, 2002)
George B. Gilmore Co. v. Garrett
582 So. 2d 387 (Mississippi Supreme Court, 1991)
Carmichael v. Agur Realty Co., Inc.
574 So. 2d 603 (Mississippi Supreme Court, 1990)
U.R.S. Co. v. Gulfport-Biloxi Air. Auth.
544 So. 2d 824 (Mississippi Supreme Court, 1989)
Magnolia Const. Co. v. MISS. GULF S. ENG.
518 So. 2d 1194 (Mississippi Supreme Court, 1988)
Mayor of Columbus v. Clark-Dietz & Associates-Engineers, Inc.
550 F. Supp. 610 (N.D. Mississippi, 1982)
Gerodetti v. Broadacres, Inc.
363 So. 2d 265 (Mississippi Supreme Court, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
341 So. 2d 646, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dickerson-const-co-inc-v-process-eng-miss-1977.