Dick Enterprises, Inc. v. Commonwealth, Department of Transportation

746 A.2d 1164, 2000 Pa. Commw. LEXIS 27
CourtCommonwealth Court of Pennsylvania
DecidedJanuary 21, 2000
StatusPublished
Cited by4 cases

This text of 746 A.2d 1164 (Dick Enterprises, Inc. v. Commonwealth, Department of Transportation) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dick Enterprises, Inc. v. Commonwealth, Department of Transportation, 746 A.2d 1164, 2000 Pa. Commw. LEXIS 27 (Pa. Ct. App. 2000).

Opinion

DOYLE, President Judge.

The Petitioner, Dick Enterprises (Dick), appeals first from an order of the Board of Claims which awarded it $104,578.80 out of a claim for approximately 3.3 million dollars it alleged it was owed by the Department of Transportation (DOT), and secondly from an order of the Board of Claims which denied its post-trial motions. In addition, the Respondent, Department of Transportation, has cross-appealed from that part of the Board’s order which granted Dick Enterprises (Dick) partial relief and likewise appeals the Board’s denial of its post-trial motions.

The 46-million dollar contract at the center of the controversy was entered into by Dick and DOT on March 13, 1989, following a formal bidding process, and involved the bridge and highway construction in Allegheny County associated with the reconstruction of the West End Bridge and its adjacent highway, State Route 65.1 The exact amount of the contract was $45,-971,064.45. The particular aspect of the contract which is in dispute is the rate of pay for certain excavation work which the contract required. The contract contained four relevant types of excavation: (1) Class 1 excavation, which involved excavation for the removal of unsuitable material below subgrade having a bottom width of eight feet or more, which was paid at the rate of $7.70 per cubic yard; (2) Foreign Borrow Excavation, which was paid at the rate of $9.00 per cubic yard and involved excavating and backfilling of undercut areas; (3) Select Borrow Excavation, which was paid at the rate of $18.00 per cubic yard and involved supplying backfill and backfilling for extra-depth undercut; and (4) Class 1A excavation, which involved excavation for the removal of unsuitable material below subgrade having a bottom width of eight feet or less and which was paid at the rate of $50.00 per cubic yard.2 All Class 1A excavation included the cost of backfill and backfilling; Class 1 excavation, on the other hand, did not include backfilling. Therefore, all Class 1 excavation also required either foreign or select borrow backfilling to be performed.

As part of the contract, Dick was required to design and ultimately build Mechanically Stabilized Earth (MSE) walls which traversed much of the project site on the North Side of the Ohio River. These walls were designed to elevate certain portions of the new roadway to correlate with the construction work on the West End Bridge and its ramps. A special provision of the contract concerning MSEs provided as follows:

Excavation for walls is incidental to the retaining wall items, except that undercut as shown on the roadway cross sections is paid as Class 1A Special Excavation.

(Reproduced Record (R.R.) at 749.) (Emphasis added.) The contract, however, contained no pay provision for “Class 1A Special Excavation,” although, as noted above, it did contain a pay item for Class 1A excavation. In addition, the contract contained roadway cross-sections and overviews of the project area which contained shaded areas, all of which indicated in the [1166]*1166relevant areas of the Class 1 designated excavation, that either Foreign Borrow or Select Borrow Excavation was required and would be paid for that area. The legend for the cross-sections identified Select Borrow areas by double-cross hatch marks, and Foreign Borrow with single cross-hatch marks. However, two sheets of the roadway cross-sections, Sheets 16 and 17, which identified the type of work required and paid for two abutments, contained a notation “CL 1A,” i.e., Class 1A excavation, in areas which contained neither single nor double hatch mark shading. These areas, also, contained no limitation indicating where such excavation would begin or end and no portion of the legends for the cross-section drawings indicated any area where Class 1A excavation was required.

Dick began performance of the contract on April 10, 1989, and by August of 1990 it had completed all of the undercut and extra-depth undercut work. As the project proceeded, DOT made periodic progress payments to Dick every two weeks. Specifically, DOT paid Dick for the undercut and extra-depth undercut at the Class 1 rate of $7.70 per cubic yard and the backfill for undercut areas was paid at the foreign borrow rate of $9.00 per cubic yard. Dick did not object to this payment at that time.

During the construction project, Dick and DOT held periodic meetings to discuss the progress of the project and to discuss potential problems with the project. On July 21,1990, immediately before Dick was about to begin construction of the MSE walls, Dick’s project manager, Mr. Blum, requested payment of all excavation under MSE Wall “P” because, he asserted, although the cross-sections of that area indicated that the excavation was to be performed and paid for at the Class 1-foreign borrow rate, the plan sheet showing the calculation for that same area indicated that 12,000 cubic yards were to be done at the Class 1A rate. DOT’s representative promised to review the matter, but eventually denied Dick’s request.

At an August 28, 1990 meeting, Dick’s representative again advised DOT that it wanted the Class 1A excavation rate for all undercut excavation. Specifically, Dick advised DOT that it was utilizing a one-foot measurement from outside of each MSE wall for a depth to the bottom of the undercut or extra depth undercut. DOT’s representative asked Dick to submit its request in a formal letter for review, which Dick did on October 18, 1990. On October 25,1990, DOT responded by again denying Dick’s request. On October 30, 1990, Dick requested that DOT convene its construction review committee to address the issue of the proper rate of pay, which DOT did on February 4, 1991. On March 12, 1991, DOT issued a letter informing Dick that the construction review committee had denied its request for payment of the disputed excavation as Class 1A.

On April 11, 1991, Dick filed a claim against the Commonwealth before the Board of Claims. In its complaint, Dick alleged that DOT had breached the contract because it failed to pay Dick the Class 1A Excavation rate and asserted that it was entitled to payment for 46,680 cubic yards at the Class 1A Excavation rate of $50 per cubic yard. Based on this breach, Dick sought payment of $1,286,-015.38.3 DOT filed an answer denying the allegations and asserting that the disputed work was not Class 1A excavation work.4

[1167]*1167Following a 10-day trial, the Board issued a decision and order awarding Dick $104,578.80. In reaching this decision, the Board concluded that a latent ambiguity existed in the classification of and, therefore, for the payment for excavation under the MSE walls. Specifically, the Board noted that the special provision of the contract governing MSE walls provided that such excavation was to paid at the “Class 1A Special Excavation” rate. Conversely, several cross-sections which were part of the contract indicated that similar areas required only Class 1 excavation with foreign and select borrow backfilling of those areas. Therefore, the Board found that these provisions conflicted with one another which created an ambiguity as to the type of excavation called for in those areas and the rate of pay for such areas.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Whalen, R. v. Public School Empl Ret Board, Aplt.
Supreme Court of Pennsylvania, 2021
M. Rivera v. Lt. Starzynski
Commonwealth Court of Pennsylvania, 2021
R.J. Whalen v. PSERB
Commonwealth Court of Pennsylvania, 2020
Pfeiffer, A. v. Zawaski, R.
Superior Court of Pennsylvania, 2019

Cite This Page — Counsel Stack

Bluebook (online)
746 A.2d 1164, 2000 Pa. Commw. LEXIS 27, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dick-enterprises-inc-v-commonwealth-department-of-transportation-pacommwct-2000.