DiCarlo ex rel. DiCarlo 38 SS Realty Trust v. Ellsworth

15 Mass. L. Rptr. 295
CourtMassachusetts Superior Court
DecidedSeptember 20, 2002
DocketNo. 005170J
StatusPublished

This text of 15 Mass. L. Rptr. 295 (DiCarlo ex rel. DiCarlo 38 SS Realty Trust v. Ellsworth) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
DiCarlo ex rel. DiCarlo 38 SS Realty Trust v. Ellsworth, 15 Mass. L. Rptr. 295 (Mass. Ct. App. 2002).

Opinion

Giles, J.

Introduction

Pursuant to Section 17 of Chapter 40A of the General Laws, the plaintiff, Barbara DiCarlo (“plaintiff’), commenced this action against the defendants, the Hopkinton Zoning Board of Appeals (“ZBA”) and the Town of Hopkinton (“Town”) (collectively, “defendants”), challenging the ZBA’s denial of a building permit for Lots 205, 206, and 2071 and seeking that the statutory zoning freeze be applied to that land. This matter is before the court on the plaintiffs and the defendants’ cross motions for summary judgment with respect to these two issues. For the reasons set forth below, the defendants’ motion for summary judgment is ALLOWED; and the plaintiffs motion for summary judgment is DENIED.

Background

The undisputed facts as revealed by the summary judgment record, viewed in the light most favorable to the non-moving party,2 are as follows.

On May 21, 1993, the Town’s Planning Board endorsed the subdivision plan entitled “Forestside Estates III Definitive Plan of Land in Hopkinton, Massachusetts,” which is recorded with the Middlesex South District Registry of Deeds as Plan 320 of 1993 in Book 23222, Page 215 (“Subdivision Plan”). As part of the approval process, three public hearings had been held in March 1993. At these hearings, the Planning Board requested that, prior to the subdivision of the land to the north and south of Elizabeth Road into lots using the road as frontage, the plaintiff3 provide perimeter survey information of those lots on plans submitted. The Subdivision Plan created parcels 51, 52, and 53, as well as the parcel shown as “N/F DiCarlo” on the north side of Elizabeth Road. The cover sheet of the Subdivision Plan showed the location of those parcels in relation to additional land owned by other parties.

At the time the Planning Board endorsed the Subdivision Plan, Hopkinton’s Zoning By-laws authorized lots of 40,000 square feet if served by Town water. On May 3, 1994, the Town voted to amend the Zoning By-laws by increasing the minimum lot size to 60,000 square feet, whether or not the land was served by municipal water.

On April 25, 1994, the plaintiff submitted to the Planning Board the plan entitled “Plan of Land in Hopkinton Massachusetts,” dated April 14, 1994, which showed Lots 200 through 209 on Elizabeth Road (“8 IP Plan”). Pursuant to G.L.c. 41, §81P, the Planning Board endorsed the 8 IP Plan as “approval not required.” The 8 IP Plan was recorded with the Middlesex South District Registry of Deeds on May 4, 1994, as Plan No. 399 of 1994 in Book 24510, Page 263. The lots on the 81P Plan each contained more than 40,000 square feet, but less than 60,000 square feet.4

On June 5, 2000, the plaintiff filed an application for a building permit for the construction of a single-family residence on one of the lots on the 81P Plan; the lot contained 42,710 square feet. The Building Department issued the permit on June 12, 2000. On June 29, 2000, the Planning Board appealed the Building Inspector’s order of decision to the ZBA, alleging that the plaintiffs land was not entitled to the eight-year zoning freeze authorized by the statute. The ZBA held public hearings in July and August 2000 and issued its decision on October 23, 2000, revoking the building permit for the lots at issue.

Count II5 of the plaintiffs complaint seeks an order that the zoning freeze provided by G.L.c. 40A, §6, be applied to Lots 205, 206, and 207, thereby protecting the land from the increased area requirements the Town adopted in May 1994.

[296]*296Discussion

Summary judgment is granted where there are no genuine issues of material fact and where the moving party is entitled to judgment as a matter of law. Mass.R.Civ.P. 56(c); Cassesso v. Commissioner of Correction, 390 Mass. 419, 422 (1983); Community Nat’l Bank v. Dawes, 369 Mass. 550, 553 (1976). The moving party bears the burden of affirmatively demonstrating the absence of a triable issue, and that the summary judgment record entitles the moving party to judgment as a matter of law. Pederson v. Time, Inc., 404 Mass. 14, 16-17 (1989). The moving party may satisfy this burden either by submitting affirmative evidence negating an essential element of the opposing party’s case or by demonstrating that the opposing party has no reasonable expectation of proving an essential element of its case at trial. Flesner v. Technical Communications Corp., 410 Mass. 805, 809 (1991); Kourouvacilis v. General Motors Corp., 410 Mass. 706, 716 (1991). The opposing party cannot rest on his or her pleadings and mere assertions of disputed facts to defeat the motion for summary judgment. LaLonde v. Eissner, 405 Mass. 207, 209 (1989).

A. Broad Application of Zoning Freeze Protection

The fifth paragraph of Section 6 of Chapter 40A establishes an eight-year zoning freeze for land shown on a definitive plan that was submitted to a planning board for approval under the subdivision control law.6 The purpose of this zoning freeze is to “protect landowners from ‘the practice in some communities of adopting onerous amendments to the zoning by-law after submission of a preliminary plan which is opposed by segments within the community.’ ” Heritage Park Dev. Corp. v. Town of Southbridge, 424 Mass. 71, 76 (1997). The zoning freeze period is also “designed to protect a developer during the planning stage of a building project.” Falcone v. Zoning Bd., of Appeals of Brockton, 7 Mass.App.Ct. 710, 712 (1979).

Thus, the protection offered by this freeze is “broad” as it seeks to prevent unpredictable changes in zoning by-laws from unfairly burdening development of land. Heritage Park Dev. Corp., 424 Mass. at 76. Indeed, the Supreme Judicial Court has “cited with approval Appeals Court decisions holding that developers can invoke a zoning freeze with inconsistent subdivision filings or with plans filed with no intent other than to invoke the freeze.” Massachusetts Broken Stone Co. v. Town of Weston, 430 Mass. 637, 641-42 (2000). However, the applicability of the zoning freeze is not absolute. See Hanna v. Planning Bd. of Charlton, Civil No. 941531C *2 (Worcester Super. Ct. Sept. 26, 1995) (4 Mass. L. Rptr. 389). Limits must be employed to avoid a “potentially uncontrollable enlargement of the eight-year period.” Id. at *2 n.5.

In the case at bar, the plaintiff is seeking that the zoning freeze be applied to Lots 205, 206, and 207 so that those lots can benefit from the pre-1994 zoning by-laws requiring a minimum square footage of 40,000, rather than the current 60,000 square feet requirement. The land at issue, however, was not described by metes and bounds on the Subdivision Plan that was approved prior to the change in minimum area requirements.

This issue is one of first impression for the court. As discussed below, the land at issue was not “shown on the plan,” as required by the statute. See G.L.c. 40A, §6. The plaintiff had filed a plan under Section 81P of Chapter 41 that contained Lots 205, 206, and 207, thereby affording the plaintiff a three-year zoning freeze under the sixth paragraph of Section 6 of Chapter 40A.7 The plaintiff could have filed a plan “with no intent other than to invoke [this three-year) freeze.” See Broken Stone, 430 Mass. at 642.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pederson v. Time, Inc.
532 N.E.2d 1211 (Massachusetts Supreme Judicial Court, 1989)
LaLonde v. Eissner
539 N.E.2d 538 (Massachusetts Supreme Judicial Court, 1989)
Community National Bank v. Dawes
340 N.E.2d 877 (Massachusetts Supreme Judicial Court, 1976)
Kourouvacilis v. General Motors Corp.
575 N.E.2d 734 (Massachusetts Supreme Judicial Court, 1991)
Flesner v. Technical Communications Corp.
575 N.E.2d 1107 (Massachusetts Supreme Judicial Court, 1991)
Cassesso v. Commissioner of Correction
456 N.E.2d 1123 (Massachusetts Supreme Judicial Court, 1983)
Falcone v. ZONING BOARD OF APPEALS OF BROCKTON
389 N.E.2d 1032 (Massachusetts Appeals Court, 1979)
Long v. Board of Appeals of Falmouth
588 N.E.2d 692 (Massachusetts Appeals Court, 1992)
Massachusetts Commission Against Discrimination v. Liberty Mutual Insurance
356 N.E.2d 236 (Massachusetts Supreme Judicial Court, 1976)
Registrar of Motor Vehicles v. Board of Appeal on Motor Vehicle Liability Policies & Bonds
416 N.E.2d 1373 (Massachusetts Supreme Judicial Court, 1981)
Pielech v. Massasoit Greyhound, Inc.
423 Mass. 534 (Massachusetts Supreme Judicial Court, 1996)
Heritage Park Development Corp. v. Town of Southbridge
674 N.E.2d 233 (Massachusetts Supreme Judicial Court, 1997)
Pierce v. Christmas Tree Shops, Inc.
429 Mass. 91 (Massachusetts Supreme Judicial Court, 1999)
Boulter-Hedley v. Boulter
711 N.E.2d 596 (Massachusetts Supreme Judicial Court, 1999)
Massachusetts Broken Stone Co. v. Town of Weston
430 Mass. 637 (Massachusetts Supreme Judicial Court, 2000)
Acting Superintendent of Bournewood Hospital v. Baker
725 N.E.2d 552 (Massachusetts Supreme Judicial Court, 2000)
K. Hovnanian at Taunton, Inc. v. Planning Board
590 N.E.2d 1172 (Massachusetts Appeals Court, 1992)
Hanna v. Planning Board of Charlton
4 Mass. L. Rptr. 389 (Massachusetts Superior Court, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
15 Mass. L. Rptr. 295, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dicarlo-ex-rel-dicarlo-38-ss-realty-trust-v-ellsworth-masssuperct-2002.