DiBella v. Widlitz

541 A.2d 91, 207 Conn. 194, 1988 Conn. LEXIS 98
CourtSupreme Court of Connecticut
DecidedApril 26, 1988
Docket13326
StatusPublished
Cited by41 cases

This text of 541 A.2d 91 (DiBella v. Widlitz) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
DiBella v. Widlitz, 541 A.2d 91, 207 Conn. 194, 1988 Conn. LEXIS 98 (Colo. 1988).

Opinion

Peters, C. J.

The dispositive issue in this case is whether the trial court abused its discretion when it denied specific performance of a contract to a buyer of real estate who failed to establish that he was ready, willing and able to perform at the date set for the closing. The plaintiff, William A. DiBella, brought an action seeking specific performance and damages because of the refusal of the defendants, Gary Widlitz and Patricia M. Widlitz, to convey certain real property located in Westbrook. After a hearing, the trial court rendered a judgment for the defendants. Both parties have appealed. Because we find no error on the plaintiffs appeal, we need not consider the appeal of the defendants.

The trial court found the following facts. In a contract dated September 5,1983, the defendants agreed to sell the plaintiff certain beachfront property in West-brook for $190,000 toward which the buyer made a down payment of $7000. Because of a pending zoning appeal, the date of closing was by mutual agreement postponed to be held within thirty days after the appeal had terminated in favor of the defendants. On April 18, 1985, the defendants notified the plaintiff that the zon[196]*196ing matter had been favorably resolved and asked for a closing. Despite the defendants’ repeated requests for a prompt closing date, the plaintiff, a Connecticut state senator, insisted on delay until the termination of his legislative commitments on June 4,1985. When the defendants sought additional security because of this delay, the plaintiff not only refused to post an additional deposit but informed them that he had filed the contract of sale on the land records.

At a meeting at the site on June 14, 1985, the parties agreed that a closing would be held on July 22, 1985. At that meeting, problems relating to an access road and a foundation were resolved, and the plaintiff received assurances from the defendants that he would receive a written easement for water from an adjoining landowner. The plaintiff’s attorney thereupon wrote the defendants that the closing date was to be July 23, 1985. When the plaintiff did not appear for the closing as scheduled, the defendants contacted the plaintiff and personally informed him that July 26,1985, at 5 p.m. was a final closing date and time. The plaintiff did not demur orally, but sent a letter of protest, on July 25, 1985, by regular mail. As of July 23 and July 26,1985, the plaintiff was not in fact ready, willing and able to proceed with the closing. Because of the plaintiff’s failure to appear for the scheduled closing on July 26,1985, the defendants, on July 27,1985, gave him notice that the contract of sale had been terminated.

On July 29, 1985, the plaintiff went to the office of the defendants’ attorney with two checks sufficient to cover the unpaid balance of the purchase price. He announced his willingness to waive any claimed problems relating to the purchase, and was ready to close [197]*197the deal. Due to their previous termination of the contract, the defendants refused to proceed further.1

On the basis of these facts, the court concluded that the plaintiff could not prevail. It held that “the plaintiff was not ready, willing and able to fulfill his part of the contract until after the contract had been rescinded. Although he had funds available on the 29th, they became available subsequent to July 26th, the final day set by the defendant[s].” The court determined that the equitable remedy of specific performance was unwarranted because of the dilatory conduct of the plaintiff or his representatives, which had justified the defendants’ good faith insistence on a termination date for the contract of sale. The court also held that the plaintiff had adduced insufficient evidence to justify awarding him damages.

The plaintiff’s appeal raises four claims of error. The plaintiff alleges that the trial court erred: (1) in finding that, on July 24 or 25, 1985, the defendants had given sufficient notice of a final date for the closing of the sales contract; (2) in concluding that the plaintiff was obligated to prove his ability to perform when the defendants had not, at that time, provided him with adequate water rights; (3) in excluding the testimony of the plaintiff’s proffered expert witness; and (4) in failing to award damages to the plaintiff. We find no error.2

[198]*198I

The plaintiff launches two different attacks on the trial court’s finding that he was not entitled to specific performance because, on July 26, 1985, he was not ready, willing and able to perform. First, the plaintiff challenges the court’s essentially factual finding that July 26 was the final date for closing and that the plaintiff had sufficient notice of that date. Second, he challenges the court’s legal conclusion that he was obligated to prove his ability to perform when the defendants allegedly had not yet fulfilled all the conditions stated in the contract of sale.

The plaintiff’s claim with regard to the trial court’s finding of fact need not long detain us. Under familiar principles of appellate review, a trial court’s factual finding will not be reversed or modified unless it is “clearly erroneous in view of the evidence and pleadings in the whole record.” Practice Book § 4061; Gorra Realty, Inc. v. Jetmore, 200 Conn. 151, 159-60, 510 A.2d 440 (1986); Pandolphe’s Auto Parts, Inc. v. Manchester, 181 Conn. 217, 221-22, 435 A.2d 24 (1980). Despite the plaintiff’s argument to the contrary, we conclude that the court could reasonably have found that the plaintiff, through his attorney, had expressly, after extended delays, agreed to a closing on July 23, 1985, which he failed to attend. Thereafter, the plaintiff’s attorney was expressly informed that no further extension of time would be permitted after July 26, 1985. On this factual record, the court could reasonably find that the plaintiff was apprised in a timely manner of the date on which the contract would terminate. In light of the factual circumstances as a whole, it was not clearly erroneous for the court to determine that [199]*199this final extension was a legitimate response to the plaintiffs dilatory tactics.3

The plaintiffs more serious claim is his argument that his own nonperformance was excused on the ground of the defendants’ alleged failure to complete their performance with respect to the water supply for the property he was buying. That argument is unpersuasive because it confuses the consequences of contractual stipulations that operate to condition a seller’s right to demand performance with a buyer’s obligation to establish his own entitlement to the discretionary, equitable relief of specific performance.

In this case, had it been the defendants who had come to court seeking specific performance from the plaintiff, they might have encountered difficulties in persuading a court to grant them this remedy without a showing of a written modification or an express waiver of the contract provisions concerning a water source for the property at issue. As the plaintiff reminds us, we have held, in an action by a seller of services, that “[o]ne cannot recover upon a contract unless he has fully performed his own obligation under it, has tendered performance, or has some legal excuse for not performing.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pryor v. Brignole
Connecticut Appellate Court, 2025
In re Annessa J.
Supreme Court of Connecticut, 2022
Conn. Coal. for Justice in Educ. Funding, Inc. v. Rell
176 A.3d 28 (Supreme Court of Connecticut, 2018)
Medeiros v. Medeiros
167 A.3d 967 (Connecticut Appellate Court, 2017)
Antonucci v. Antonucci
138 A.3d 297 (Connecticut Appellate Court, 2016)
Disciplinary Counsel v. Parnoff
Connecticut Appellate Court, 2015
Dept. of Transportation v. Cheriha, LLC
Connecticut Appellate Court, 2015
Brett Stone Painting & Maintenance, LLC v. New England Bank
72 A.3d 1121 (Connecticut Appellate Court, 2013)
Musolino v. Musolino
997 A.2d 599 (Connecticut Appellate Court, 2010)
Roberson v. Aubin
990 A.2d 1239 (Connecticut Appellate Court, 2010)
Kaczynski v. Kaczynski
981 A.2d 1068 (Supreme Court of Connecticut, 2009)
Martinez v. Commissioner of Correction
936 A.2d 665 (Connecticut Appellate Court, 2007)
David M. Somers & Associates, P.C. v. Busch
927 A.2d 832 (Supreme Court of Connecticut, 2007)
Glaser v. Pullman & Comley, LLC
871 A.2d 392 (Connecticut Appellate Court, 2005)
Donenfeld v. Friedman, No. Cv02 039 51 61 (Oct. 31, 2002)
2002 Conn. Super. Ct. 13733 (Connecticut Superior Court, 2002)
Round v. Matyas, No. 82825 (Aug. 19, 2002)
2002 Conn. Super. Ct. 10557 (Connecticut Superior Court, 2002)
Ro-Tam Sheetmetal v. Nu-Way Heating Air, No. Cv99 0334970s (Oct. 16, 2001)
2001 Conn. Super. Ct. 14721 (Connecticut Superior Court, 2001)
Hartford Restoration Service v. Buccino, No. Cv 99 70043 S (Oct. 10, 2001)
2001 Conn. Super. Ct. 13545 (Connecticut Superior Court, 2001)
Seraya, Inc. v. Wirth, No. Cv 99 70313 S (May 10, 2001)
2001 Conn. Super. Ct. 6618 (Connecticut Superior Court, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
541 A.2d 91, 207 Conn. 194, 1988 Conn. LEXIS 98, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dibella-v-widlitz-conn-1988.