Dewayne Blaha d/b/a Blaha Roofing, LLC v. Larry Strange

CourtCourt of Appeals of Iowa
DecidedFebruary 25, 2026
Docket24-1865
StatusPublished

This text of Dewayne Blaha d/b/a Blaha Roofing, LLC v. Larry Strange (Dewayne Blaha d/b/a Blaha Roofing, LLC v. Larry Strange) is published on Counsel Stack Legal Research, covering Court of Appeals of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dewayne Blaha d/b/a Blaha Roofing, LLC v. Larry Strange, (iowactapp 2026).

Opinion

IN THE COURT OF APPEALS OF IOWA _______________

No. 24-1865 Filed February 25, 2026 _______________

Dewayne Blaha d/b/a Blaha Roofing, LLC, Plaintiff–Appellant, v. Larry Strange, Defendant–Appellee. _______________

Appeal from the Iowa District Court for Mills County, The Honorable Amy Zacharias, Judge. _______________

AFFIRMED AS MODIFIED _______________

J. Joseph Narmi, Council Bluffs, attorney for appellant.

Wyatt D. Suhr of Peters Law Firm, P.C., Council Bluffs, attorney for appellee. _______________

Considered without oral argument by Ahlers, P.J., and Chicchelly and Sandy, JJ. Opinion by Ahlers, P.J.

1 AHLERS, Presiding Judge.

Larry Strange hired Dewayne Blaha’s construction business, Blaha Roofing, LLC, to install a new roof, siding, and gutters on Strange’s house and an outbuilding. Dissatisfied with the work after Blaha completed the project, Strange did not pay the outstanding balance on the contract. Blaha sued to recover the balance. Strange filed a counterclaim seeking damages for the cost needed to remedy the claimed defects in the work. Following a bench trial, the district court denied Blaha’s claim and entered judgment in Strange’s favor on his counterclaim for $50,066.93.

Blaha appeals. He contends (1) the district court’s ruling denying his breach-of-contract claim is not supported by the evidence and (2) the damages awarded to Strange results in unjust enrichment.

We find the district court’s ruling is supported by substantial evidence, but we find that its damage calculation failed to properly account for the outstanding balance owed on the underlying contract. We affirm as modified.

I. Factual and Procedural Background

Strange and Blaha contracted for Strange to pay Blaha $36,427.02 to replace the roof, siding, and gutters on Strange’s house and a nearby shed to repair storm damage. Strange paid $15,000.00 to Blaha for materials, and Blaha began work on the project with the use of a subcontractor.

During the siding replacement phase of the job, another storm hit. The subcontractor and his crew had removed the siding near one of the windows on the home and were not able to replace it before the storm rolled through. Rain from the storm leaked through this window and caused damage to Strange’s floor.

2 After the project was completed, Strange paid $6,000.00 directly to the subcontractor because he was worried Blaha would not pay the subcontractor. Strange testified that he was dissatisfied with the quality of the work, and he notified Blaha of the problems so they could be fixed. Blaha claims he was not informed of the issues until after the job was complete and Strange declined a final walkthrough after the job was complete. Strange testified that he never declined a walkthrough or access to the property to remedy the defective work. Strange’s issues with the job were not corrected, so he did not pay the remaining $15,427.02 due under the contract. Blaha sued to recover the unpaid balance, and Strange counterclaimed for an amount equal to the cost to fix the damage caused by Blaha’s work and to complete the project in a workmanlike manner.

During the bench trial, the court heard testimony from both parties and two contractors Strange called. The court noted some credibility issues with one of the contractors but ruled in Strange’s favor in part because the pictures and video evidence corroborated the testimony of Strange and his witnesses. The court found Blaha’s claim that Strange denied Blaha the opportunity to do a final walkthrough and fix the problems lacked credibility. The court denied Blaha’s claim for the unpaid contract balance and entered judgment in favor of Strange on his counterclaim in the amount of $50,066.93—the cost of electrical repairs, flooring repairs, and replacement siding needed to repair the defective work and complete the project.

II. Standard of Review

We review breach-of-contract claims for correction of errors at law. Iowa Mortg. Ctr., L.L.C. v. Baccam, 841 N.W.2d 107, 110 (Iowa 2013). The district court’s factual findings are binding if they are supported by substantial evidence, but its conclusions of law and application of legal

3 principles are not binding on us. Id. Substantial evidence exists when a “reasonable mind would accept it as adequate to reach a conclusion.” EnviroGas, L.P. v. Cedar Rapids/Linn Cnty. Solid Waste Agency, 641 N.W.2d 776, 781 (Iowa 2002) (quoting Land O’Lakes, Inc. v. Hanig, 610 N.W.2d 518, 522 (Iowa 2000)). We also view the evidence in the light most favorable to the district court’s judgment. Id. And we do not reweigh the evidence or assess the credibility of witnesses. Id. at 785.

III. Breach of Contract

Blaha contends the district court’s decision denying his claim that Strange breached the contract is not supported by the evidence. He argues that the evidence, including Strange’s $6,000.00 payment to the subcontractor, only supports a finding that Strange breached the contract by not paying the remaining balance when the work was complete.

To be successful on a breach-of-contract claim, a party must prove: (1) the existence of a contract; (2) the terms and conditions of the contract; (3) that it has performed all the terms and conditions required under the contract; (4) the defendant’s breach of the contract in some particular way; and (5) that plaintiff has suffered damages as a result of the breach.

Iowa Mortg. Ctr., 841 N.W.2d at 110–11 (quoting Molo Oil Co. v. River City Ford Truck Sales, Inc., 578 N.W.2d 222, 224 (Iowa 1998)). Construction contracts contain an implied warranty that the contract work will be done “in a reasonably good and workmanlike manner.” Fry v. Blauvelt, 818 N.W.2d 123, 134 (Iowa 2012) (citation omitted).

The bulk of Blaha’s argument on this issue is devoted to pointing out why he believes the court should have believed his evidence over the competing evidence presented by Strange. But his argument disregards our standard of review. Weighing evidence and assessing credibility of witnesses

4 is the task of the factfinder at trial, not the appellate court. EnviroGas, 641 N.W.2d at 785. Here, the district court was the factfinder, and it took great care in explaining its weighing of the evidence and credibility determinations. In doing so, it noted credibility issues with one of the contractor witnesses called by Strange due to the witness’s criminal history. Despite this, the court found his testimony and the video and photo evidence presented by Strange were sufficient to conclude that Blaha did not complete the job in a workmanlike manner. Given the deference we afford district courts in assessing witness credibility, the court’s careful credibility assessment, and the photo and video evidence, a reasonable person could conclude Blaha failed to complete the project in a workmanlike manner. Thus, there is substantial evidence supporting the court’s determination that Blaha breached the contract and Strange did not.

We are also not persuaded by Blaha’s claim that Strange’s partial payment to the subcontractor constitutes acceptance of the work. The only authority Blaha cites in support of his contention that payment to a subcontractor can be considered acceptance of work is Higdon v. Rana.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Molo Oil Co. v. River City Ford Truck Sales, Inc.
578 N.W.2d 222 (Supreme Court of Iowa, 1998)
Land O'Lakes, Inc. v. Hanig
610 N.W.2d 518 (Supreme Court of Iowa, 2000)
EnviroGas, L.P. v. Cedar Rapids/Linn County Solid Waste Agency
641 N.W.2d 776 (Supreme Court of Iowa, 2002)
Iowa Mortgage Center, L.L.C. v. Lana Baccam and Phouthone Sylavong
841 N.W.2d 107 (Supreme Court of Iowa, 2013)
Abbey Fry v. Andrew Blauvelt D/B/A Bluefield Trust Construction
818 N.W.2d 123 (Supreme Court of Iowa, 2012)
Lewis Electric Co. Vs. Ronald E. Miller And Kathleen F. Miller
791 N.W.2d 691 (Supreme Court of Iowa, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
Dewayne Blaha d/b/a Blaha Roofing, LLC v. Larry Strange, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dewayne-blaha-dba-blaha-roofing-llc-v-larry-strange-iowactapp-2026.