Devlin v. Milwaukie Covenant Church

525 P.2d 998, 269 Or. 596, 1974 Ore. LEXIS 418
CourtOregon Supreme Court
DecidedSeptember 6, 1974
StatusPublished
Cited by2 cases

This text of 525 P.2d 998 (Devlin v. Milwaukie Covenant Church) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Devlin v. Milwaukie Covenant Church, 525 P.2d 998, 269 Or. 596, 1974 Ore. LEXIS 418 (Or. 1974).

Opinion

O’CONNELL, C.J.

Plaintiff brought this action to foreclose a mechanic’s lien. Defendants answered by way of general denial and also counterclaimed for damages on the ground of an alleged breach of contract. The trial court held in favor of plaintiff, and defendants appeal.

In early 1970, defendant Milwaukie Covenant Church decided to construct a new church building. The congregation retained Donald Lindgren, an architect who had specialized in church design, to plan the structure. After the plans and specifications were completed, Lindgren recommended that defendant employ [598]*598plaintiff to act as general contractor. The chnrch was interested in cutting costs by having congregation members do some of the labor, an arrangement which plaintiff was willing to accept. Plaintiff inspected the site and examined the plans and specifications, after which he got in touch with several potential subcontractors, prepared a cost estimate and un March 16, 1971, sent the following “Contractor’s Proposal” to the church:

“Sirs:
“I am pleased to report that we can construct your Church Building, plans by Donald Lindgren Architect, for the amount of One Hundred Forty Four Thousand Dollars ($144,000). This amount does not include Electrical, Carpet, or Appliances.
“The above price may be reduced by Volunteer labor as much as is available and also by changes in specifications and securing additional Subcontract bids.
“Thank you,
/sgd/ Edward L. Devlin
Edward L. Devlin”

Thereafter, on July 14, 1971, the parties entered into a contract prepared by plaintiff using Standard Form Contract A 111, published by the American Institute of Architects (AIA). The contract is entitled “Standard Form of Agreement Between Owner and Contractor where the basis of payment is the Cost of the Work Plus a Fee.” Article 7 of this contract provides that plaintiff’s fee was to be $14,400. Article 6, entitled “COST OF THE WOKE AND GUARANTEED MAXIMUM COST,” provides:

“6.2 The maximum cost to the Owner, including the Cost of the Work and the Contractor’s Fee, is guaranteed not to exceed the sum of One hundred forty-four thousand and no/100 dollars [599]*599($144,000.00); such Guaranteed Maximum Cost shall be increased or decreased for Changes in the Work as provided in Article 8.
“All savings made by the use of Volunteer Church Workers, trade discounts, changes in material specification, and lower bids by subcontractors will be deducted from contract maximum amount.
“The above amount does not include any electrical work.”

Construction work began shortly after the execution of the contract. Almost immediately, for reasons which need not be discussed here, the actual cost of construction exceeded the estimates which plaintiff had used in preparing his Contractor’s Proposal. The first application for payment, submitted in August to Lindgren for approval pursuant to Article 9 of the “GENEBAL CONDITIONS OP THE CONTBACT FOB CONSTBUCTION”,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pacific Erectors, Inc. v. Westinghouse Electric Corp.
655 P.2d 613 (Court of Appeals of Oregon, 1982)
Devlin v. Milwaukee Covenant Church
557 P.2d 647 (Oregon Supreme Court, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
525 P.2d 998, 269 Or. 596, 1974 Ore. LEXIS 418, Counsel Stack Legal Research, https://law.counselstack.com/opinion/devlin-v-milwaukie-covenant-church-or-1974.