Devlin v. Milwaukie Covenant Church

525 P.2d 998, 269 Or. 596, 1974 Ore. LEXIS 418
Oregon Supreme Court·Decided September 6, 1974·Published·Cited by 2 cases

Opinion

O’CONNELL, C.J.

Plaintiff brought this action to foreclose a mechanic’s lien. Defendants answered by way of general denial and also counterclaimed for damages on the ground of an alleged breach of contract. The trial court held in favor of plaintiff, and defendants appeal.

In early 1970, defendant Milwaukie Covenant Church decided to construct a new church building. The congregation retained Donald Lindgren, an architect who had specialized in church design, to plan the structure. After the plans and specifications were completed, Lindgren recommended that defendant employ [598] plaintiff to act as general contractor. The chnrch was interested in cutting costs by having congregation members do some of the labor, an arrangement which plaintiff was willing to accept. Plaintiff inspected the site and examined the plans and specifications, after which he got in touch with several potential subcontractors, prepared a cost estimate and un March 16, 1971, sent the following “Contractor’s Proposal” to the church:

“Sirs:
“I am pleased to report that we can construct your Church Building, plans by Donald Lindgren Architect, for the amount of One Hundred Forty Four Thousand Dollars ($144,000). This amount does not include Electrical, Carpet, or Appliances.
“The above price may be reduced by Volunteer labor as much as is available and also by changes in specifications and securing additional Subcontract bids.
“Thank you,
/sgd/ Edward L. Devlin
Edward L. Devlin”

Thereafter, on July 14, 1971, the parties entered into a contract prepared by plaintiff using Standard Form Contract A 111, published by the American Institute of Architects (AIA). The contract is entitled “Standard Form of Agreement Between Owner and Contractor where the basis of payment is the Cost of the Work Plus a Fee.” Article 7 of this contract provides that plaintiff’s fee was to be $14,400. Article 6, entitled “COST OF THE WOKE AND GUARANTEED MAXIMUM COST,” provides:

“6.2 The maximum cost to the Owner, including the Cost of the Work and the Contractor’s Fee, is guaranteed not to exceed the sum of One hundred forty-four thousand and no/100 dollars [599] ($144,000.00); such Guaranteed Maximum Cost shall be increased or decreased for Changes in the Work as provided in Article 8.
“All savings made by the use of Volunteer Church Workers, trade discounts, changes in material specification, and lower bids by subcontractors will be deducted from contract maximum amount.
“The above amount does not include any electrical work.”

Construction work began shortly after the execution of the contract. Almost immediately, for reasons which need not be discussed here, the actual cost of construction exceeded the estimates which plaintiff had used in preparing his Contractor’s Proposal. The first application for payment, submitted in August to Lindgren for approval pursuant to Article 9 of the “GENEBAL CONDITIONS OP THE CONTBACT FOB CONSTBUCTION”, was for an amount greater than was then available to the church. Lindgren approved payment of this amount and the church disbursed all available funds, making up the difference as the rest of its funding was received. The September application for payment was also approved by Lindgren and paid by the church. In October, November and December, however, Lindgren refused to approve payment of the full amounts applied for by plaintiff. Two bases appear to have led Lindgren to this action. Costs continued to outpace estimates and he began to doubt that plaintiff could “finish the job for the balance that he said he could do it for.” Additionally, Lindgren sought documentation of certain expenses because actual progress did not appear to correspond [600] to alleged expenditures and plaintiff did not produce such documentation promptly.

During this period, a separate dispute arose concerning plaintiff’s procurement of a contractor’s bond. Plaintiff claimed that the church had orally waived the contract requirement that he supply such a bond. The church disagreed. Finally, Lindgren and the church, in December, asked plaintiff to supply proof that he could complete the project within the contract guaranteed maximum cost. Plaintiff submitted a statement indicating that work would be completed for $140,000, but the church and architect rejected this figure as unrealistic and continued to withhold approximately $13,000. On January 7, 1972, plaintiff sent the church a letter stating that unless, within seven days, he received all sums for which he had applied he would stop work. No payments were made and plaintiff left the project on January 13. The church then hired a new supervisor and completed construction.

At trial, plaintiff contended that three alleged inconsistencies among the provisions of the three contract documents rendered the agreement unenforceable and sought recovery on a quantum meruit theory. Conversely, defendants argued that the agreement was an enforceable contract under which plaintiff agreed to construct the church building for a sum not to exceed $144,000 and sought damages for the [601] amount by which actual costs exceeded that figure. The trial judge neither accepted nor rejected either position. Rather, he construed the transaction as a cost-plus-fee arrangement with no fixed maximum. He then determined the amount actually expended by plaintiff prior to his leaving the project, held the church responsible to pay this amount, and awarded plaintiff 10% of this sum as his fee.

We cannot accept the trial court’s construction of the contract. Article 6, as noted above, clearly provided that “the maximum cost to the Owner, including the Cost of the Work and the Contractor’s Fee, is guaranteed not to exceed the sum of One hundred forty-four thousand and no/100 dollars * * *; such Guaranteed Maximum Cost shall be increased or decreased for Changes in the Work as provided in Article 8.” Consequently, if an enforceable contract existed at all, it protected the church against any costs in excess of this amount.

We are also of the opinion that the alleged inconsistencies relied on by plaintiff are neither real nor significant enough to render the contract unenforceable. Plaintiff points first to the form of bid required by the various contract documents and notes that whereas the architect’s specifications provided for a firm bid, the Owner-Contractor Agreement was labeled a “cost-plus-fee” contract. Second, he argues [602] that whereas the specifications provided for periodic payments based on the percentage of work completed, the Owner-Contractor Agreement based payments on actual expenditures. Finally, he points out that whereas the specifications placed the burden of the cost of the contractor’s bond un the contractor, the Owner-Contractor Agreement placed it on the owner.

Free access — add to your briefcase to read the full text and ask questions with AI

Devlin v. Milwaukie Covenant Church, 525 P.2d 998, 269 Or. 596, 1974 Ore. LEXIS 418 (Or. 1974).

525 P.2d 998 (Devlin v. Milwaukie Covenant Church) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Pacific Erectors, Inc. v. Westinghouse Electric Corp.
655 P.2d 613 (Court of Appeals of Oregon, 1982)
Devlin v. Milwaukee Covenant Church
557 P.2d 647 (Oregon Supreme Court, 1976)