Devir v. Mayor of Malden

178 N.E. 617, 277 Mass. 502, 79 A.L.R. 222, 1931 Mass. LEXIS 1131
CourtMassachusetts Supreme Judicial Court
DecidedDecember 4, 1931
StatusPublished
Cited by6 cases

This text of 178 N.E. 617 (Devir v. Mayor of Malden) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Devir v. Mayor of Malden, 178 N.E. 617, 277 Mass. 502, 79 A.L.R. 222, 1931 Mass. LEXIS 1131 (Mass. 1931).

Opinion

Pierce, J.

This is an appeal from a final decree dismissing the plaintiffs’ bill of complaint. The bill was [504]*504brought by more than ten taxable inhabitants under G. L. c. 40, § 53. The case was presented to the court upon a stipulation and agreement between parties which stated, or referred to, certain facts, and defined the issues presented therein for the determination of the court.

On June 24, 1931, the street and water commissioners of the city of Malden duly published an advertisement in a newspaper published in Malden, in terms and figures as follows: "City of Malden. Proposals for Furnishing and Laying Top-Surfacing in Street and Water Commission, June 23, 1931. Sealed proposals for furnishing and laying Top Surfacing on Pleasant St., Exchange St., Lebanon St. and Eastern Ave. in Malden, Mass., will be received at the office of the Street and Water Commission until Thursday, July 2, 1931, at 8:00 o’clock, p.m., when they will be publicly opened and read. Bids will be received on either or both Warrenite-Bitulithic and 3" Sheet Asphalt. All bids submitted for performing the work must be on the basis of a five-year guarantee. Specifications and plans may be seen and all necessary information obtained at the office of the City Engineer between 8:00 a.m. and 12 m. daily. The Commission reserves the right to reject any or all proposals or to accept any proposal, should it deem it for the interest of the City of Malden so to do. A certified check for $500.00 payable to the City of Malden, must accompany each proposal. A bond satisfactory to the Street and Water Commission will be required of the contractor for the faithful performance of the work and guaranteeing the same for the term of five years. Proposals should be marked 'Proposals for Furnishing and Laying Top Surfacing’ and be addressed to the Street and Water Commission, Malden, Mass. Per order of the board, John J. Connell, Clerk.” The specifications are set out in the record but are not recited here. The plans to which reference is made in the advertisement and in the stipulation and agreement show the approximate areas upon which the work was proposed to be done upon the four streets, and the total area of surfacing required for all the streets, that is to say, Eastern Avenue, 13,710 square yards; Leb[505]*505anon Street, 8,420 square yards; Pleasant Street, 9,700 square yards; Exchange Street, 4,300 square yards; making a total of 36,130 square yards.

Pursuant to directions to bidders contained in the advertisement it was stated to prospective bidders “that the work on Eastern Avenue may not be awarded”; and it was further stated by the city engineer “that all bids must be submitted on a per yard basis and that the City reserved the right to award the contract for any one or more streets to any bidder.” Bids were received from four bidders, and the proposals of two of them were accepted and contracts made between the city and the successful bidders. “No Contracts for wearing surface was let for Eastern Avenue.” At the trial in the Superior Court it was found “There is nothing in the present case to convince the court that the city officials were actuated by unworthy motives.”

In the "Stipulation and Agreement” it is agreed that the issue presented for the determination of the court is, “Are the relevant requirements of sections 14 and 15 of Chapter 53 of the revised ordinances of 1928 of the City of Malden satisfied by the use of an advertisement duly published, certain plans, specifications, statements and proposals” as set forth in the stipulation and agreement above referred to. The material provisions of the ordinance are as follow: “Section 14. Before making any contract for the furnishing of labor or materials, involving the expenditure of more than five hundred dollars, the committee or board having charge of the same shall prepare, or cause to be prepared plans and specifications, advertise for public bids in the form of sealed proposals for furnishing said labor and materials in one or more of the local papers at least one week before the awarding of said contract, and that citizens and taxpayers of the city of Malden be given the preference in awarding said contracts, all other considerations being equal”; “Section 15. In cases where competitive bids are requested by a committee or municipal board for a contract with the city, no proposals shall be received by the said committee or board unless the same are sealed. All proposals shall be publicly opened and read at the hour and place designated; Provided, [506]*506•always, that the said committee or board may reject any or all proposals, or waive defects, when, in their judgment, the interests of the city justify such a course. In the event of the rejection of all bids as. hereinbefore provided no contract involving the expenditure of more than five hundred dollars shall be awarded unless competitive bids are again requested.” '

The plaintiffs do not question “that the provisions of said sections were complied with in every respect except as the above recited facts may disclose affirmatively a non-compliance with some provisions of said sections and the law applicable thereto.” They contend, as set forth in paragraph “7A” of their bill of complaint, that the prospective bidders when applying for plans and specifications at the office of the city engineer were informed by the said city engineer “‘That al bids must be submitted on a per yard basis and that the City reserved the right to award the whole or any part of the total amount of the wearing surface advertised to any bidder or bidders’; so that bidders could not know with practical definiteness and certainty the quantity and quality of the work required or the materials to be furnished in order to intelligently submit a bid.” In support of this contention the plaintiffs rely upon Sweezey v. Mayor of Malden, 273 Mass. 536, where it was held to be improper to permit the bidder, to furnish his own specifications as to the composition and manner of laying of the wearing surface. The reason for the decision is found in that part of the opinion which reads, at page 542: “To permit each bidder to furnish his own specifications for the construction of the wearing surface might, and probably would, allow a substantial variance in the manner of construction and its cost. Such a method of bidding would not result in bids being submitted on any common basis. Where, as here, each bidder is invited to bid upon his own specifications, it is plain that there can be no real competition between such bidders. Such an advertisement not only destroys competition, but gives city officials an opportunity to exercise favoritism in awarding contracts. A compliance with the ordinances makes it mandatory that prospective bidders shall stand upon an equal footing and [507]*507that no one shall be permitted to submit his bid upon a basis different from that of any other bidder. To allow a bidder to furnish his own specifications for any material part of the contract in question would destroy genuine and fair competition and be subversive of the public interests. The purpose of the ordinances is to prevent fraud and favoritism and to protect the financial interests of the city.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J.F. White Contracting Co. v. Massachusetts Port Authority
748 N.E.2d 1020 (Massachusetts Appeals Court, 2001)
Datatrol Inc. v. State Purchasing Agent
400 N.E.2d 1218 (Massachusetts Supreme Judicial Court, 1980)
Automatic Merchandising Corp. v. Nusbaum
210 N.W.2d 745 (Wisconsin Supreme Court, 1973)
Gifford v. Commissioner of Public Health
105 N.E.2d 476 (Massachusetts Supreme Judicial Court, 1952)
Sutton v. City of St. Paul
48 N.W.2d 436 (Supreme Court of Minnesota, 1951)
Archambault v. Mayor of Lowell
180 N.E. 157 (Massachusetts Supreme Judicial Court, 1932)

Cite This Page — Counsel Stack

Bluebook (online)
178 N.E. 617, 277 Mass. 502, 79 A.L.R. 222, 1931 Mass. LEXIS 1131, Counsel Stack Legal Research, https://law.counselstack.com/opinion/devir-v-mayor-of-malden-mass-1931.