Development Services, Inc. v. Sheehan

189 N.W.2d 34, 290 Minn. 382, 45 A.L.R. 3d 1320, 1971 Minn. LEXIS 1140
CourtSupreme Court of Minnesota
DecidedJune 25, 1971
DocketNo. 42324
StatusPublished

This text of 189 N.W.2d 34 (Development Services, Inc. v. Sheehan) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Development Services, Inc. v. Sheehan, 189 N.W.2d 34, 290 Minn. 382, 45 A.L.R. 3d 1320, 1971 Minn. LEXIS 1140 (Mich. 1971).

Opinion

Kelly, Justice.

Plaintiff sued defendants for $13,000 as commission due for the procurement of a loan. The lower court found for defendants and thus this appeal.

On June 23, 1965, defendants signed a loan procurement contract with Neil Larson whereby Larson would be paid lV^-percent commission on the principal amount of the mortgage if he could obtain a $650,000 mortgage amortized over 20 years with [383]*3836-percent interest per annum. An additional commission of one-half percent of the principal was to be paid to Larson if he could obtain interim construction financing. The commission was to “be considered earned, due and payable as of the date the firm commitment is issued.” The firm commitment was “to provide the financing as applied for, or in any other amount and/or at any other terms which the undersigned shall agree in writing to accept.” Larson thereafter assigned all of his interest in the contract to plaintiff.

Larson prepared a written presentation and contacted three financial institutions, including Midwest Federal Savings and Loan Association (then known as Minneapolis Federal Savings and Loan Association, hereafter referred to as Midwest).

On October 25, 1965, Midwest by a letter to defendant James Sheehan made a tentative commitment for the loan sought by defendants, stating therein:

“This is estimated strictly upon the appraisal submitted by you, and a firm commitment will be given upon receipt of detailed plans, specifications, bids and itemized sworn construction statement, as well as proof of ability of the borrowers to qualify for such a mortgage. Approval of our Loan Committee must be made after final appraisal.”

In early January, Midwest issued an oral commitment to furnish interim construction financing and for a loan of $650,000, to be discounted at 2 percent, to carry an interest rate of 6% percent and to be amortized over a 25-year period, with a proviso that “[t]he commitment will become firm upon [Midwest’s] approval of your mortgage application.”

On January 13, 1966, defendants accepted the oral commitment by signing a mortgage loan application embodying the following pertinent provisions:

“* * * gworn construction statement and lien waivers required yes.”
“* * * Notwithstanding an agreement of the Association to [384]*384make this loan, it is understood that the same may be rejected by the Association for falsity in any statement in this application * *

The mortgage application for $650,000 was approved by Midwest’s board of directors on January 27, 1966. Notice of the loan approval was communicated to defendants, who subsequently signed the mortgage note and mortgage deed on March 2, 1966.

On January 3, 1966, defendants and Kaye Construction, Inc., entered into a contract for the construction of a nursing home for a flexible price of $638,228, “unless that price would create an undue hardship for the owner or the contractor in which case the price could be reopened.”

Kaye Westerlund, president of Kaye Construction, and defendant John J. Mondati cosigned a sworn construction statement for Midwest on May 26, 1966, stating the cost of construction to be $868,050. In the declaration contained in the sworn construction statement, the signers declared under oath that the statement included “the amounts due and to become due” to each contractor and subcontractor and “that no arrangements of any kind whatsoever have been entered into with any person involving any trade, or the payment of monies, credits, refunds, or services which are not fully explained or in attached statement.” There was no attached statement. A consulting engineer testified that “ordinary construction practice would dictate that the figures in the construction statement would be identical to the figures in the construction contract.”

In late June or early July of 1966, when Westerlund contacted Midwest to obtain the first mortgage money, the commitment for the loan was withdrawn by Midwest and the reason given by Harold Greenwood, president of Midwest, was “discrepancies or irregularities in the sworn construction statement.” Robert M. Urahn, chief appraiser for Midwest, gave testimony to the same effect. Upon learning that the commitment had been revoked, defendants’ attorney contacted Greenwood to inquire if defendants would be allowed to submit “another sworn construe[385]*385tion statement.” Greenwood replied that Midwest “would review it again” if defendants would “submit another sworn construction statement to Mr. Urahn.” Larson was not informed of the withdrawal of the commitment and apparently was given no opportunity to renegotiate with Midwest.

Defendants through an attorney reapplied for the loan on July 5, 1966. Except for an increased interest rate from 6% percent to 7% percent, the terms and provisions of the second application were substantially identical to those of the first application although the term of the loan was increased to 30 years. The application was approved on July 7, 1966. The revised construction statement of $656,728 was furnished July 11,1966, and the mortgage note and mortgage deed were executed the same day. The initial disbursement of the loan was made on July 26, 1966.

The testimony of Westerlund disclosed that the May 26, 1966, construction statement, which was the first one submitted to Midwest, was false. He testified: “I was told to make a construction statement that would indicate a cost greater than the actual cost.” The second construction statement submitted to Midwest of $656,728 included the architect’s fee of $18,000, which was not a part of the first construction statement. The second construction statement, without the architect’s fee, approximated the contract price of $638,278.

Plaintiff invoiced defendants for the brokerage commission in the amount of $13,000 ($650,000 x 1 y% percent, plus $650,000 x one-half percent), but defendants refused to pay any portion of the commission. Plaintiff sued and the trial court found for defendants.

The issue is whether a brokerage commission is payable on a firm commitment that would have been consummated except for defendants’ furnishing of false information to the mortgagee contrary to a condition of the commitment.

This court has stated in Olson v. Penkert, 252 Minn. 334, 343, 90 N. W. (2d) 193, 200:

“We think the rule well established that, if the efforts of the [386]*386broker are rendered a failure by the fault of the employer, the broker does not lose his commission. This rule is based upon the familiar principle that no one can avail himself of the nonperformance of a condition precedent who has himself occasioned its nonperformance. Usually a broker is entitled to a fair and reasonable opportunity to perform his obligation. * * *
‡ ‡ ‡ $
“* * * [A] broker is entitled to his compensation upon the completion of the negotiations which he undertook, irrespective of whether or not the contract negotiated is actually consummated * *

And in Schramsky v. Hollmichel, 233 Minn. 481, 484, 47 N. W. (2d) 177, 179:

“It is well settled that a broker is entitled to his commission when he has performed all that he undertook to perform, and this necessarily depends upon the agreement of the parties.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rees-Thomson-Scroggins, Inc. v. Nelson
150 N.W.2d 568 (Supreme Court of Minnesota, 1967)
Olson v. Penkert
90 N.W.2d 193 (Supreme Court of Minnesota, 1958)
Schramsky v. Hollmichel
47 N.W.2d 177 (Supreme Court of Minnesota, 1951)

Cite This Page — Counsel Stack

Bluebook (online)
189 N.W.2d 34, 290 Minn. 382, 45 A.L.R. 3d 1320, 1971 Minn. LEXIS 1140, Counsel Stack Legal Research, https://law.counselstack.com/opinion/development-services-inc-v-sheehan-minn-1971.