Developers Surety & Indemnity Co. v. Populous, Inc.

903 F. Supp. 2d 822, 2012 WL 4858607, 2012 U.S. Dist. LEXIS 146664
CourtDistrict Court, W.D. Missouri
DecidedOctober 11, 2012
DocketCase No. 11-0645-CV-W-NKL
StatusPublished

This text of 903 F. Supp. 2d 822 (Developers Surety & Indemnity Co. v. Populous, Inc.) is published on Counsel Stack Legal Research, covering District Court, W.D. Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Developers Surety & Indemnity Co. v. Populous, Inc., 903 F. Supp. 2d 822, 2012 WL 4858607, 2012 U.S. Dist. LEXIS 146664 (W.D. Mo. 2012).

Opinion

ORDER

NANETTE K. LAUGHREY, District Judge.

Pending before the Court is a Motion to Dismiss [Doc. # 154] and Motion for Summary Judgment [Doc. # 156] filed by Defendants Kansas City Chiefs Football Club [“the Chiefs”] and Jackson County Sports Complex Authority [“the Sports Authority”] [collectively “the Chiefs”], as well as a Motion for Summary Judgment [Doc. # 155] filed by Defendant Jackson County, Missouri; and Motions for Summary Judgment filed by Populous Inc. [Doc. # 164]; The Konrath Group [Doc. # 162]; and Ghostfire Design, Inc. [Doc. # 166].

I. Background

Developers is a surety who brought a lawsuit against several defendants involved in renovations to Arrowhead Stadium, including the construction of the Chiefs Hall of Honor and Children’s Learning Center at Arrowhead Stadium. The Kansas City Chiefs entered into a written contract with Defendant Ghostfire Design to serve as contractor for the project. Ghostfire’s contract with the Chiefs obligated it to submit periodic invoices including:

[An] updated schedule and progress report setting forth in detail the actual progress to date (in terms of percent complete) and the scheduled or planned progress, a listing of the value of materi[824]*824al on hand included in the Invoice, and other data specified in the Contract Document. ...

[Doc. # 1 at 6]. Ghostfire would then be entitled to be paid according to the payment schedule, but only “so long as [Ghostfire] has progressed with the [work] as required.” [Id. at 8].

Ghostfire then entered into a written subcontract with L & L Group, in which L & L agreed to provide fabrication and services for all exhibit casework. The contract between L & L and Ghostfire incorporated by reference Ghostfire’s contract with the Chiefs and further states that “[a]ll payment applications and progress of the work will be directed, approved, and processed by Design Consultant [Ghost-fire] .... ” [Doc. # 1-3]. Section 16.0 of the L & L Agreement with Ghostfire provides that L & L was to be paid a total of $639,100.00, for the scope of work it was to perform. [Doc. # 1-3 at 6, sec. 16.0] [Doc. # 161 at 10]. The Agreement states that payment should be made “in one deposit payment, and four progress payments upon receipt of invoices for services performed and expenses incurred.” [Doc. # 1, ¶ 36].

The Chiefs also entered into a written contract with Defendant Populous, who agreed to serve as architect for the project. Populous’ contract with the Chiefs stated that it would provide “Application for Payment certification services” to the Chiefs. This work involved reviewing and inspecting the work of contractors on the project, including Ghostfire and L & L, and then certifying that:

[T]he Contractors’ applications for payment are accurate and correct, that they accurately represent the quantity of Work in place or reasonably stored at the site, that the Work complies with the requirements of the Contract Documents, and that the application accurately reflects previous payments and retainage amounts.

[Doc. # 107 at 6],

Defendant Konrath contracted with the Chiefs to serve as program manager for the project. Their contract with the Chiefs involved oversight of the architect and other design professionals’ work.1

L & L submitted 5 pay applications in July 2009, September 2009, November 2009, February 2010, and March 2010. The first four of these pay applications were paid by the Chiefs, but the last one submitted on March 31, 2010, was not. Pay Applications 1, 3, and 4 were certified by Populous before being paid by the Chiefs, while the second pay application was not provided to Populous before payment.

On May 3, 2010, L & L closed its business operations and had no further funds to finish the project to its completion. Ghostfire declared L & L in default and made demand on Plaintiff, Developers Surety to correct the breach. In 2009, [825]*825Developers had issued a performance bond to the Chiefs under which Developers guaranteed the performance of L & L on the project. Under the bond, Developers had the obligation upon notice of “contractor’s failure to perform,” to

promptly and at Surety’s expense take one of the following actions: (a) Arrange for Contractor, with the written consent of the Owner, to perform, complete or cure the default or breach of the Contract; (b) Undertake to perform and complete the Contract itself through qualified Contractors approved by Owner; or (c) Waive its right to perform, complete or cure the default or breach of the Contract and pay to the Owner the total amount due Owner from Contractor under the terms of the Contract not to exceed the amount of this Bond as set forth in Paragraph 11.

[Doc. # 161, ¶ 96].

After the default, Developers retained the services of Guardian Group, Inc., to investigate the claim made against the performance bond by the Chiefs and provide recommendations to Developers on a course of action. Developers chose to waive it’s right to perform under the bond and instead to pay a penal sum. The penal sum listed in the contract was $639,100.90, with a reservation of rights. But Developers initially paid the sum of $618,325.56, citing $20,674.44 that Developers claims it incurred to move, store and ship materials from L & L’s facility in Indiana to the completion contractor, EAI. [Doc. # 161 at ¶ 158].

Defendants claim that the Court penal sum comprises the original amount of $639,100.00, plus the amounts of two agreed change orders altering the L & L scope of one in the amount of $14,700.00, and one in the amount of $8,250.00. Thus, Defendants claim that the correct total penal bond sum was $662,050.00. Under Paragraph 8 of the Performance Bond, Developers waived “notice of any change, including changes of times, to the Contract or to related subcontracts, purchase orders and other obligations, provided that the Surety will be notified in writing by Owner of any change that would cause the aggregate amount of all changes to exceed twenty percent (20%) of the original Contract Sum. [Doc. # 161, ¶ 97]. Developers disputes Defendants’ assertions that L & L executed these change orders and initially did not pay this increased amount. In 2012, as this litigation was ongoing, however, Developers paid Chiefs the additional sum of $22,950.00, while claiming a full reservation of rights.

According to Developers, the Chiefs significantly overpaid L & L when compared to the amount of work L & L had completed on the project. Further, Populous, Ghostfire and Konrath failed to properly supervise payments to L & L as required by their contracts with the Chiefs and the standards of their professions.

Developers’ damages analysis appears to be based on the costs it would have incurred to complete the project had the overpayments not been made. It is undisputed that more probably than not, Developers would have elected to pay the penal sum of the performance bond to the Chiefs as long as the cost to Developers to complete L & L’s scope of work exceeded 75% of that sum, due to the risk of the ultimate completion cost being more than L & L’s contract and other factors. As of the date of L & L’s default, the amount left in the Chiefs’ contract balance that Plaintiff could use to complete L & L’s scope of work was approximately $124,000.00.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
903 F. Supp. 2d 822, 2012 WL 4858607, 2012 U.S. Dist. LEXIS 146664, Counsel Stack Legal Research, https://law.counselstack.com/opinion/developers-surety-indemnity-co-v-populous-inc-mowd-2012.