Developers Surety &, Indemnity Co. v. Bi-Tech Construction, Inc.

979 F. Supp. 2d 1307, 2013 WL 5835412, 2013 U.S. Dist. LEXIS 157855
District Court, S.D. Florida·Decided October 17, 2013·No. Case No. 13-22767-CIV·Published·Cited by 2 cases

Opinion

ORDER ADOPTING REPORT OF MAGISTRATE JUDGE

WILLIAM P. DIMITROULEAS, District Judge.

THIS CAUSE is before the Court upon the Report and Recommendations of Magistrate Judge Lurana S. Snow, dated September 20, 2013, (the “Report”) [DE 40]. The Court notes that no objections to the Report [DE 40] have been filed, and the time for filing such objections has passed. As no timely objections were filed, the Magistrate Judge’s factual findings in the Report [DE 40] are hereby adopted and deemed incorporated into this opinion. LoConte v. Dugger, 847 F.2d 745, 749-50 (11th Cir.1988), cert. denied, 488 U.S. 958, 109 S.Ct. 397, 102 L.Ed.2d 386 (1988); RTC v. Hallmark Builders, Inc., 996 F.2d 1144, 1149 (11th Cir.1993).

Although no timely objections were filed, the Court has conducted a de novo review of the Report [DE 40] and record and is otherwise fully advised in the premises. The Court agrees with the Magistrate Judge’s recommendations in full.

Accordingly, it is ORDERED AND ADJUDGED as follows:

1. The Report [DE 40] is hereby ADOPTED and APPROVED;
2. Any funds remaining in the Bank of America Accounts ending in -0869 [1310] and -2093, and in any other accounts maintained at Bank of America in the name(s) of either of the Indemnitors are frozen and Bank of America shall turn over such funds to Surety in partial or full satisfaction of the Injunction;
3. The Indemnitors’ assets are frozen and are, therefore, prevented from being transferred, sold, dissipated, or otherwise disposed of without further order of Court until Indemnitors bring themselves in compliance with the Injunction;
4. The Injunction is hereby converted to a Partial Judgment in favor of the Surety in the amount of $219,896.82, with specific findings that Indemnitors committed fraud, defalcation and embezzlement, as those terms are defined under 11 U.S.C. § 523(a)(4);
5. The Partial Judgment also recognizes the Indemnitors’ assignment of $36,000 from the Douglas Gardens Community Mental Health Center and of any and all contract proceeds due and owing under the Bonded Contract;
6. Expedited discovery to address the fraudulent conveyances and to permit the Surety to enforce its rights under the Partial Judgment is granted, including but not limited to requiring the Indemnitors’ full and complete production of documentation responsive to a formally issued Request for Production within ten (10) days thereof, and requiring the deposition of Aguado and the corporate representative of Bi-Tech within two (2) weeks from receipt of the requested documentation;
7. The Surety is awarded all attorneys’ fees and costs incurred in connection with its pursuit and enforcement of the Injunction; and
8.The Court finds that the Indemnitors’ intentionally and willfully violated the Injunction

REPORT AND RECOMMENDATION

LURANA S. SNOW, United States Magistrate Judge.

THIS CAUSE is before the Court on Developers Surety and Indemnity Company’s (“Plaintiff’ or “Surety”) Motion for Expedited Entry of Order Enforcing Preliminary Injunction dated August 21, 2013 (“Motion”) (DE 15), which was referred to United States Magistrate Judge Lurana S. Snow for Report and Recommendation. The Court construed the motion as a motion to show cause why the Defendants, Bi-Tech Construction, Inc. (“Bi-Tech”) and Rafael I. Aguado (“Aguado”) (collectively with Bi-Tech “Defendants” or “Indemnitors”) should not be held in contempt or sanctioned.

The Court ordered expedited briefing and scheduled a Show Cause Hearing for Thursday, September 5, 2013 [DE 22], at which time it heard arguments of counsel and accepted documentary evidence stipulated by the parties. Despite the Order to Show Cause, neither a representative of Bi-Tech nor Aguado appeared at the hearing. As a result, the Court continued the Show Cause Hearing on Tuesday, September 10, 2013, and required Defendants to appear and testify as to why they should not be held in contempt and sanctioned.

The Defendants failed to appear at the September 10, 2013 Show Cause Hearing. The Court again heard the arguments of counsel and accepted additional documentary evidence stipulated by the parties. Having carefully considered the Motion [DE 15], the Response [DE 17], the Reply [DE 18], the Plaintiffs Proposed Findings [1311] of Fact and Conclusions of Law [DE 31] as well as the Defendants’ Response [DE 34], and the Plaintiffs Reply thereto [DE 39], the record, and all other evidence presented at the Show Cause Hearings held on September 5, 2013 and September 10, 2013, the Court submits the following Findings of Fact and Recommendations of Law.

I.FINDINGS OF FACT

A. Procedural Background

1. On August 19, 2013, the Court entered its Order Granting Motion for Preliminary Injunction (“Injunction”) [DE 14], 964 F.Supp.2d 1304, 2013 WL 4563657 (S.D.Fla.2013), and ordered the Defendants to post collateral security with the Surety in the amount of $205,000.00. The Court ordered the security to be posted no later than August 20, 2013

2. In their Response to the Motion, the Defendants conceded that they have failed to post the $205,000.00 in collateral as required by the Injunction; however, they claim that they were unable to raise the required funds, and requested an opportunity to present evidence at a show cause hearing.

3. At the Show Cause Hearing held on September 5, 2013, Defendants failed to appear in person and did not offer any evidence to demonstrate they did not possess the financial capability to raise the required funds. Instead, the Defendants authorized their counsel to confess a judgment in favor of the Surety in the collateral amount of $205,000.00, and assign $36,000.00 allegedly owed to Bi-Tech- from a project for Douglass Gardens Community Mental Health Center and $130,000.00 allegedly owed to Bi-Tech on the bonded project. [Ex. 19, ¶¶ 12,13 and 14],

4. In response, Plaintiff presented evidence showing that Defendants intentionally and willfully disregarded the Injunction. Plaintiff argued and presented evidence that Defendants, as Indemnitors, committed fraud and defalcation while acting in their fiduciary capacity as the trustee of contract funds received by Bi-Tech on the bonded project. Plaintiff • contended that the Defendants embezzled the trust funds for their personal use and benefit, fraudulently divested themselves of such funds, and/or otherwise continue to maintain access to the defalcated funds.

5. The Court refrained from making any rulings to allow the Defendants an opportunity to appear in person to respond to the Plaintiffs allegations of fraud, defalcation and embezzlement.

Free access — add to your briefcase to read the full text and ask questions with AI

Developers Surety &, Indemnity Co. v. Bi-Tech Construction, Inc., 979 F. Supp. 2d 1307, 2013 WL 5835412, 2013 U.S. Dist. LEXIS 157855 (S.D. Fla. 2013).

979 F. Supp. 2d 1307 (Developers Surety &, Indemnity Co. v. Bi-Tech Construction, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Great Am. Ins. Co. v. Brandt (In re Brandt)
594 B.R. 829 (S.D. Florida, 2019)
Hanover Insurance v. Hermosa Construction Group, LLC
57 F. Supp. 3d 1389 (N.D. Georgia, 2014)