Detroit Fidelity & Surety Co. v. Frey

158 N.E. 910, 96 Ind. App. 696, 1927 Ind. App. LEXIS 298
CourtIndiana Court of Appeals
DecidedDecember 8, 1927
DocketNo. 12,859.
StatusPublished
Cited by1 cases

This text of 158 N.E. 910 (Detroit Fidelity & Surety Co. v. Frey) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Detroit Fidelity & Surety Co. v. Frey, 158 N.E. 910, 96 Ind. App. 696, 1927 Ind. App. LEXIS 298 (Ind. Ct. App. 1927).

Opinion

Nichols, J.

Action by appellee Frey against appellant and other appellees. There being special findings of fact and conclusions of law, we deem it unnecessary to consider alleged errors as to the pleadings. It appears by these findings so far as here involved, that appellant, at the time of the execution by it of the bond sued on, December 1, 1923, was, and is a surety company for profit; and ever since has been duly authorized to transact in Indiana its business of a surety company for profit.

During the year 1923, appellees, Conder and Culbertson, were partners engaged in the business of erecting houses and other structures.

On or about August 2, 1923, appellees, Conder & Culbertson, and appellant entered into a written contract whereby Conder & Culbertson agreed to erect a two-story stucco apartment building on appellee Frey’s lot in the City of Indianapolis, Marion County, Indiana. Said contract provided, inter alia, that the contractors should begin the work immediately, complete the building on or about October 1, 1923, that they would be held responsible for and make good any defects arising from or discovered in the work within one year after the completion and acceptance of the building, that they would pay for all labor and materials used in the erection and construction of said building, that no person, persons, corporation or corporations should file or maintain any lien thereon or on the real estate on which the same was located, for labor or material used in the erec *698 tion and construction thereof, and that they would keep the building and real estate free from all liens for labor and materials.

Frey agreed to pay Conder & Culbertson for the performance of the contract a sum not to exceed $22,920, subject to conditions and deductions as provided in the general conditions of the contract, payments to be made one-third of the contract price when the building was ready for plastering, one-third when the building was plastered and ready to finish, and the final one-third when the building was completely finished, providing satisfactory evidence and an affidavit were given that there were not and could not be any liens or claims for any labor or materials furnished in the performance of the contract. Pursuant to said contract Conder & Culbertson commenced the erection of said building in the summer of 1923 and almost completed the same in December, 1923. In the construction of said building Brannum-Keene Lumber Company sold and furnished in 1923 to Conder & Culbertson building material to be used, and which was used in the construction of said building, on which there became due in 1923 to said lumber company $4,887.82, which sum was not paid. On February 2d, 1924, said Lumber Company filed in the Recorder’s office of Marion County its notice of an intention to hold a mechanic’s lien for the said sum on said lot and buildings, and on September 3, 1924, said Lumber Company commenced its suit in the Superior Court of Marion County, Indiana, against Frey and his wife and Conder and Culbertson, partners, to foreclose said lien. All of said defendants appeared in court and resisted the suit, but such proceedings were had therein that on November 5, 1925, judgment was rendered in said last named suit in favor of the Lumber Company against Conder & Culbértson for the total sum $4,858.72, and a foreclosure of said mechanic’s lien was had and *699 ordered, and said real estate was ordered sold to satisfy said judgment and costs. In said suit the claim and demand of the Lumber Company was reduced by $845.69. Frey and his wife filed their motion for a new trial in said cause, which was overruled by the court. On December 12, 1925, Frey, in order to prevent the sale of his said real estate under said judgment and decree of foreclosure, paid said judgment, interest thereon and costs, the total sum paid by him amounting to $4,901.25, which sum has never been repaid to him

On September 6, 1924, appellant was duly notified of the commencement and nature of said suit by Frey’s attorney and from time to time thereafter was duly advised of what was being done and was done in said suit, but it gave no attention whatever to said suit and took no part therein, and did not assist in the defense thereof.

In the late fall or early winter of 1923, Conder & Culbertson, before the completion of said building and before all material and labor used in the construction thereof had been paid for, desired and requested the payment to them of the balance to become due them on the completion of their said contract before the completion thereof, and in order to induce Frey to pay to them such balance they tendered and delivered to him, on December 1st, 1923, the bond sued on in this action, which bond said Conder & Culbertson executed as principal and appellant as surety, for a consideration to be paid to it by Conder & Culbertson. Said Francis J. Frey accepted said bond and, relying theron, paid to Conder & Culbertson, on December 5th, 1923, on their said contract the sum of $7,455.25, being the sum that would have become due Conder & Culbertson on the completion of said building and after the payment by them for all labor and material used in the construction of said building. In addition to the usual conditions of *700 such bonds, this bond was conditioned that: “This bond is executed waiving, and with full knowledge of the provisions of the contract between the owner herein and the principal herein providing that before the balance due is paid to the principal, the principal' shall furnish the owner evidence and an affidavit showing that all bills and claims on account of said construction have been paid and with the knowledge that as yet all bills and claims have not been paid and with the understanding and agreement .that the oivner may, without such evidence or affidavit, at once pay to the principal the balance due under said contract.” (our italics), and with provision “that no suit, action or proceeding by reason of any default whatever shall be brought on this bond after three months from the day on which the final payment under the contract falls due.”

Conder & Culbertson never finished the construction of said building and have never paid for much of the labor and material used in the construction thereof. The findings specify divers failures to complete the building according to plans and specifications, and divers sums of money which Frey was compelled to pay out in order to make the building, in the respective particulars, comply with the plans and specifications. In the defense of said suit of the Lumber Company, Frey employed an attorney to look after the defense thereof and who did look after it and to whom Frey paid $300 as a fee for such services, which fee was a reasonable fee for the services rendered. A reasonable fee for the services of Frey’s attorney in the present suit would be and is $700, which fee is unpaid but which Frey has contracted to pay. No part of any sums herein found to have been paid by Frey has been repaid to him and all of said sums are long past due and unpaid. No part of the sums required to complete said building have been paid to Frey, nor has he been paid for any attorney’s1 *701 fee or fees hereinbefore found to have been paid or contracted for by him.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Indiana University v. Indiana Bonding & Surety Co.
416 N.E.2d 1275 (Indiana Court of Appeals, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
158 N.E. 910, 96 Ind. App. 696, 1927 Ind. App. LEXIS 298, Counsel Stack Legal Research, https://law.counselstack.com/opinion/detroit-fidelity-surety-co-v-frey-indctapp-1927.