Detroit Edison Co. v. Armada Township

357 N.W.2d 843, 137 Mich. App. 161
CourtMichigan Court of Appeals
DecidedSeptember 5, 1984
DocketDocket No. 76315
StatusPublished
Cited by3 cases

This text of 357 N.W.2d 843 (Detroit Edison Co. v. Armada Township) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Detroit Edison Co. v. Armada Township, 357 N.W.2d 843, 137 Mich. App. 161 (Mich. Ct. App. 1984).

Opinion

Allen, P.J.

In this appeal involving the acquisition of land for the purpose of constructing a 22-mile-long high energy transmission line, we are asked to decide a question of first impression: Does §2 of the Uniform Condemnation Procedures Act (UCPA), MCL 213.52; MSA 8.265(2), require that a public utility, before acquiring property for a proposed transmission line, obtain a certificate of public necessity from each township or governmental unit through which the transmission line would run? On January 25, 1984, the trial court answered this question in the affirmative and issued an order of accelerated judgment in favor of defendants. Plaintiff appeals as of right. We reverse.

The facts are basically undisputed. In 1977, Edison developed a plan to build a 22-mile-long power transmission line (known as the "SaratogaJewell” line) from its Saratoga generating station in St. Clair County, through portions of Armada and Richmond Townships, to its Jewell station in Macomb County. Edison claims that this new line is necessitated by the impending completion of two new generating plants on Belle River which are expected to begin operation in 1984 or 1985. In late 1980, Edison filed a special land use application with Armada Township, which requested approval for construction of a 765 kilovolt power [165]*165line. On October 11, 1982, Edison filed a revised request for a 345 kilovolt line. At the time, Article X, § 1014 of the Armada Township zoning ordinance was in effect. Article X, § 1000 set forth general standards for "special approval land use requirements” to be submitted in plan form to the township planning commission. If the plans so submitted:

"meet the required standards of this Ordinance, Article, and applicable section and indicate no adverse effect, which in the opinion of the Township Board, would cause injury to the residents, users or adjoining property, or the Township as a whole, the Township Board shall approve the use. The Township Board after a recommendation from the Planning Commission shall have sole power to approve or disapprove all special approval uses”.

Section 1014 of Article X, as then worded, provided in pertinent part as follows:

"Section 1014. Public utilities, gas and oil pipelines AND STORAGE FACILITIES

"Public utilities, electric and gas lines, gas storage fields, oil and gas pipe lines, transformer stations and other utility or services which transverse the Township of Armada. Such uses and site plans must meet the requirements of this ordinance and the following conditions:

"A. Utility lines and pipe lines shall follow section or quarter-section lines or mile roads wherever possible. Major overhead utility lines shall be permitted to parallel road rights-of-way only when there is no feasible alternate route or when such route would benefit the environment and/or the residents of the township or where there is no other reasonable route.”

Pursuant to the ordinance, Edison’s revised petition was referred to the township planning com[166]*166mission. On June 13, 1983, while the application was still pending before the planning commission, Edison filed a condemnation action in circuit court under UCPA to "take” certain land in Armada Township for the construction of the Saratoga-Jewell transmission line. The township was the owner of parcel 10 of the land taken in the action and individual defendants were owners of parcels 9, 16, 18, 22, 23 and 24 therein. On July 6, 1983, the township filed a motion for accelerated judgment on grounds that the action was premature and should be dismissed because Edison filed its complaint for condemnation without showing necessity as required by § 1014 of the township zoning ordinance. The landowners of the various parcels listed above, as well as Richmond Township as amicus curiae, joined in Armada Township’s motion.

While the motion was still pending before the circuit court, Armada Township adopted amendments to § 1014. As so amended September 21, 1983, the revised version required a public utility to prove a clear and apparent need for any proposed power transmission line.

"Section 1014. Public utilities, gas and oil pipelines AND STORAGE FACILITIES.

"Public utilities, electric and gas lines, gas storage fields, oil and gas pipelines, transformer stations and other utility or services which transverse the Township of Armada. Such uses and site plans must meet the requirements of this Ordinance and the following conditions:

"A. That a clear and apparent public need is proven for the proposed utility transmission line, including necessity based on future area consumer demands as predicted on documented projections.”

On January 25, 1984, Judge Deneweth in a [167]*167written opinion granted the motion for accelerated judgment. In so doing, the court did not speak to the question of the subsequent rewording of § 1014. Instead, the court held that § 2 of UCPA, MCL 213.52; MSA 8.265(2), required a public utility to obtain a certificate of public necessity from the governmental unit through which the utility’s power line would run as a condition precedent to condemnation.

"The Court holds Detroit Edison must obtain a certificate of public necessity pursuant to the Armada Township Ordinance as a condition precedent to bringing this action pursuant to MCL 213.52. That section makes it clear that the private agency shall not institute judicial proceedings to acquire property until it has secured the 'required certificate’. The required certificate is a 'Certificate of Public Necessity’ from 'other public agency’. Armada Township is a 'public agency’ within the definition contained in MCL 213.51(i). The intent of the Legislature in passing the Uniform Condemnation Procedures Act is to make uniform the procedures for the condemnation of property for public purposes in the State of Michigan. However, the Legislature did not wish to remove all requirements of prior approval by local government entities. As a result, the Legislature maintained the condition precedent language in MCL 213.52(3).”

Though the parties frame the issues differently,1 both quantitatively and qualitatively, a fair synthesis thereof reveals three issues: (1) Does § 2(3) of UCPA require Edison to secure a certificate of public necessity from the township before commencing a condemnation action; (2) Does § 1014 of Armada’s zoning ordinance require approval by [168]*168the township before a private utility may acquire property; (3) Assuming the answer to question (2) is "yes”, did the trial court err in applying Armada’s newly enacted version of § 1014?

I

Does § 2(3) of UCPA require Edison to secure a certifícate of public necessity from the township before commencing its condemnation action?

This Court is again faced with the inherent conflict between the electrical power needs of an entire area versus the rights of individual townships to protect their residents’ well-being. See Detroit Edison Co v City of Wixom, 382 Mich 673, 678; 172 NW2d 382 (1969). The lower court ruled that MCL 213.52(3) required Edison to secure a certificate of public necessity from Armada Township before instituting condemnation proceedings. MCL 213.52(3); MSA 8.265(2X3) reads:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Consumers Energy Company v. Brian Storm
Michigan Supreme Court, 2022
Lyons v. United States
794 F. Supp. 238 (E.D. Michigan, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
357 N.W.2d 843, 137 Mich. App. 161, Counsel Stack Legal Research, https://law.counselstack.com/opinion/detroit-edison-co-v-armada-township-michctapp-1984.