Deslatte v. Tidex Incorporated

CourtCourt of Appeals for the Fifth Circuit
DecidedApril 25, 1996
Docket94-40810
StatusUnpublished

This text of Deslatte v. Tidex Incorporated (Deslatte v. Tidex Incorporated) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Deslatte v. Tidex Incorporated, (5th Cir. 1996).

Opinion

IN THE UNITED STATES COURT OF APPEALS

FOR THE FIFTH CIRCUIT

_____________________

No. 94-40810 _____________________

MARK J. DESLATTE,

Plaintiff-Appellee,

versus

TIDEX, INC.,

Defendant-Appellant.

_________________________________________________________________

Appeal from the United States District Court for the Western District of Louisiana (93-CV-546) _________________________________________________________________ March 18, 1996

ON PETITION FOR REHEARING

Before GARWOOD, JOLLY, and BARKSDALE, Circuit Judges.

E. GRADY JOLLY, Circuit Judge:*

On petition for rehearing, Tidex takes the panel to task for

deciding the case on a basis different from the rationale and the

specific findings of the district court. Notwithstanding the

petitioner's protestations, however, and to the extent that his

* Pursuant to Local Rule 47.5, the court has determined that this opinion should not be published and is not precedent except under the limited circumstances set forth in Local Rule 47.5.4. point has support, appellate courts may comprehensively canvas the

record and are free to affirm a district court on any basis that

the record supports. Ferguson v. Hill, 846 F.2d 20, 21 (5th Cir.

1988); Brock v. Mr. W Fireworks, Inc., 814 F.2d 1042, 1044 (5th

Cir), cert. denied, 484 U.S. 924, 108 S.Ct. 286 (1987). In

comparing the district court's formal findings with other

information in the record, we can also make assumptions regarding

what the district court properly could have concluded in reaching

its decision. Ferguson, 846 F.2d at 21; Thomas v. Express Boat

Co., Inc., 759 F.2d 444, 448 (5th Cir. 1985).

Tidex further argues in its petition for rehearing that we

engaged in factfinding, which, of course, an appellate court is not

permitted to do. Although we did not engage in factfinding, the

petitioner has pointed out that in certain instances we failed to

state with accuracy the precise record facts. We regret each

error. Nevertheless, each error ultimately is inconsequential to

our finding that, on this record, the district court's findings of

liability and damages are supportable and must be affirmed. In

order to correct any mistakes in our reading of the record as

reflected in our earlier opinion, the panel withdraws the opinion

that was filed in this appeal on June 23, 1995, and substitutes the

following. In all other respects, the petition for rehearing is

denied.

-2- I

Tidex, Inc. ("Tidex") appeals the district court's entry of

judgment against it on Mark Deslatte's ("Deslatte") claims of

negligence under the Jones Act, 46 U.S.C. § 688, and

unseaworthiness under general maritime law, the district court's

apportionment of damages, and the district court's denial of its

motion for a new trial. We carefully have reviewed the record and

the briefs in this case and conclude that the judgment of the

district court must be affirmed in all respects, save its award for

"found" damages.

II

Because an explanation of the facts will facilitate a better

understanding of this case, we present them in detail.

Deslatte was injured during a mooring operation on

December 15, 1990, while he was working for Tidex on its supply

vessel, the M/V O'NEIL TIDE. Deslatte, age twenty-six at the time,

was serving as the chief engineer on the vessel and had been

working for Tidex almost four years when the accident occurred.

The accident occurred when the O'NEIL TIDE was delivering

supplies to a drilling rig in the Gulf of Mexico. The supply

vessel’s captain, Ernest LeBouef, had never been to this drilling

rig. Because the currents were strong that day, Captain LeBouef

decided to tie the O'NEIL TIDE's bow to a mooring buoy, which was

-3- approximately one-fourth mile from the drilling platform, and back

the stern of the supply vessel to the rig. Once on location, the

drilling rig was to lower mooring lines to be secured to the

vessel's stern bitts.

Before commencing the operation, the captain met with Deslatte

and part of the crew to discuss the method of securing the vessel

to the buoy. Captain LeBouef ordered Deslatte to man the bow line

and three other crew members to handle the stern lines, while the

captain would attempt to execute the backdown maneuver using the

stern controls of the vessel. Positioned at the stern controls,

the captain would have no means of seeing Deslatte or of

communicating with him during the procedure. The one remaining

crew member was permitted to sleep through the procedure.

Captain LeBouef decided to use a bridle setup to secure the

O'NEIL TIDE to the anchor buoy because it provided more stability

than the alternative single line setup. Under the bridle setup,

one end of the line is tied to the portside bitt on the bow. The

other end is then placed through a shackle attached to the anchor

buoy line and then tied to the starboard side bitt on the bow.

With only 300 feet of bow line available, the use of this method

effectively reduced the available bow line by one-half. Captain

LeBouef chose this procedure even though he was uncertain of the

length of the buoy line.

-4- Deslatte's job was to monitor the bow line at the starboard

side bitt as the vessel backed toward the rig. When more line was

needed, Deslatte was to take a wrap off the bitt. If the line

began to surge, Deslatte was to put the wrap back on the bitt. If

the line began to surge uncontrollably, the captain instructed

Deslatte to drop the rope and try to get away.

As the operation proceeded, Deslatte paid out the bow line on

two different occasions, without incident. The operation proceeded

uneventfully until the vessel moved into position to receive the

mooring lines from the rig. When the vessel reached the rig,

Deslatte decided to let out the line a third time, without looking

to see whether enough rope remained on deck. As he was doing this,

the line surged suddenly and uncontrollably through his hands.

Deslatte dropped the line and attempted to step back, but as the

line surged, the end of it whipped around the bitt and struck his

right leg just below the knee. Deslatte sustained a fractured leg

and severe damage to his right knee. Deslatte admitted that had he

checked, he would have seen that the end of the line was at his

feet, and he would not have let out more line. Despite three

surgical procedures, including reconstructive surgery, the injury

to his right knee remains disabling.

III

-5- Deslatte brought a seaman's action for damages against his

employer, Tidex, under the Jones Act, 46 U.S.C. § 688, and general

maritime law. Following a two-day bench trial, during which the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Deslatte v. Tidex Incorporated, Counsel Stack Legal Research, https://law.counselstack.com/opinion/deslatte-v-tidex-incorporated-ca5-1996.