Design Development, Inc. v. Brignole

570 A.2d 221, 20 Conn. App. 685, 1990 Conn. App. LEXIS 46
CourtConnecticut Appellate Court
DecidedFebruary 20, 1990
Docket8052
StatusPublished
Cited by13 cases

This text of 570 A.2d 221 (Design Development, Inc. v. Brignole) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Design Development, Inc. v. Brignole, 570 A.2d 221, 20 Conn. App. 685, 1990 Conn. App. LEXIS 46 (Colo. Ct. App. 1990).

Opinion

Norcott, J.

The defendants, Timothy Brignole and Michael Greci, appeal from the judgment of the trial court awarding damages to the plaintiffs, Design Development, Inc., and John Cazzetta, its president, in a breach of contract action.1 The defendants claim that the trial court erred in awarding damages to the plaintiffs despite its finding that the plaintiffs were in violation of General Statutes §§ 20-290 and 20-297.2 We find error.

[687]*687The trial court found the following undisputed facts. The defendants were a partnership interested in developing an office building on their property. In March, 1985, the defendants hired Cazzetta to prepare drawings, stamped by an engineer, for the construction and renovation of a building of approximately 11,700 square feet on their property. Brignole was aware that Cazzetta was not a licensed architect or engineer.

Cazzetta prepared preliminary plans and delivered them to the defendants on August 26, 1985. Because the plans were not acceptable to zoning authorities without an engineer’s stamp, Cazzetta paid $2500 to acquire the appropriate stamp. The defendants paid the plaintiffs $1000, but refused to pay for the final plans that Cazzetta had prepared. The plaintiffs then brought an action for breach of contract. The defendants raised illegality of the contract as a defense.

The trial court found that Cazzetta violated General Statutes § 20-290 by holding himself out as an architect and designing a building in excess of 5000 square feet. The court awarded damages, however, because it found that the defendant Brignole was in pari delicto with Cazzetta regarding any violation of General Statutes § 20-290. The court based this ruling on the fact that Brignole knew that Cazzetta was not a licensed architect but hired him anyway. The trial court rendered judgment for the plaintiffs for $5000. From this ruling the defendants appeal.

[688]*688The defendants claim that because the trial court found Cazzetta to be in violation of § 20-290, it could not award him damages. They argue that because the rendering of architectural services by Cazzetta was illegal and punishable by a criminal penalty, the agreement for such, services was void and unenforceable, and, hence, no damages could be awarded.

The trial court found that Cazzetta was in violation of General Statutes § 20-290 because he was not licensed, as required by that section, and yet he performed services as and held himself out as an architect.3 Once the trial court found that Cazzetta “practiced as” and “held himself out as” an architect, Cazzetta became subject to a criminal penalty; General Statutes § 20-297; and his contract with the defendant was rendered illegal, void as against public policy and unenforceable. See Douglas v. Smulski, 20 Conn. Sup. 236, 239, 131 A.2d 225 (1957); Lapuk v. Blount, 2 Conn. Cir. Ct. 271, 279, 198 A.2d 233 (1963).

The plaintiffs claim that the defendants cannot assert the alleged illegality of the contract as a defense because they knew that Cazzetta was not a licensed architect. They further assert that should they be denied relief, the defendants will be unjustly enriched and, therefore, that the trial court was correct in ruling that they should be able to recover based upon quantum meruit. We do not agree.

The plaintiffs’ argument and the trial court’s finding that recovery should be permitted on the basis of quantum meruit or unjust enrichment is without merit. “ ‘When the illegality, either in whole or in part, is in [689]*689the thing which the party seeking to recover was to do, then there can be no recovery upon a quantum meruit.’ ” McKnight v. Gizze, 119 Conn. 251, 256, 175 A. 676 (1934); Douglas v. Smulski, supra.

The defendants also argue that the trial court erred in finding that they were in pari delicto and that, even if they were in pari delicto, the trial court erred in awarding damages because the contract would still be rendered unenforceable. We agree.

The doctrine of in pari delicto holds that where the parties to an illegal agreement or transaction are equally at fault, the court will leave the parties as it finds them and will not enforce the agreement against one over the other. Ballentine’s Law Dictionary (3d Ed. 1969); see also Vaszauskas v. Vaszauskas, 115 Conn. 418, 423, 161 A. 856 (1932). The doctrine, therefore, is, as the defendants claim, a defensive doctrine. Even if we assume that the court was correct in finding that the parties were in pari delicto in this case, it could not properly enforce this contract against the defendants.4 “In case any action is brought in which it is necessary to prove the illegal contract in order to maintain the action, courts will not enforce it, nor will they enforce any alleged right directly springing from such contract, but if both parties are in pari dilecto, the law will leave them where it finds them.” Vaszauskas v. Vaszauskas, supra.

[690]*690This doctrine has been applied in Connecticut for many years, and the rationale was well articulated by our Supreme Court in 1881. “At first blush it might seem unequal, and therefore unjust, to give the defendant the privilege of setting up his own participation in the illegal contract, resulting in his gain, and deny the privilege to the plaintiff, to his loss. . . . ‘The objection that a contract is immoral or illegal as between plaintiff and defendant sounds at all times very ill in the mouth of the defendant. It is not for his sake however that the objection is ever allowed, but is founded in general principles of policy which the defendant has the advantage of, contrary to the real justice as between him and the plaintiff, by accident . . . ” (Citations omitted.) Funk v. Gallivan, 49 Conn. 124, 128 (1881); see also Beit v. Beit, 135 Conn. 195, 199-200, 63 A.2d 161 (1948).

Having found the plaintiff in violation of General Statutes § 20-290, and having found further that the parties were in pari delicto, the trial court erred in enforcing the contract and awarding damages to the plaintiff.5

There is error, the judgment is set aside and the case is remanded to the trial court with direction to render judgment for the defendants.

In this opinion the other judges concurred.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ass Kickin Ranch, LLC v. North Star Mutual Insurance Co.
2012 S.D. 73 (South Dakota Supreme Court, 2012)
Winer v. Ceslik
786 A.2d 516 (Connecticut Appellate Court, 2001)
Weid v. Westside Realtors Appraisers, No. Cv 98-0262030 S (Dec. 21, 1998)
1998 Conn. Super. Ct. 14837 (Connecticut Superior Court, 1998)
Dwight Getting Heating & Air Conditioning, Inc. v. Jeradco, Ltd.
255 A.D.2d 288 (Appellate Division of the Supreme Court of New York, 1998)
Tunxis Recylcing Opt. v. Automated Cont., No. Cv 98-0486403s (Sep. 11, 1998)
1998 Conn. Super. Ct. 10178 (Connecticut Superior Court, 1998)
Mazza Cons. G. v. M O Const. Co., No. Cv98 0163656 S (Apr. 28, 1998)
1998 Conn. Super. Ct. 5108 (Connecticut Superior Court, 1998)
Winer v. Ceslik, No. Cv90 03 39 26s (Mar. 15, 1995)
1995 Conn. Super. Ct. 2084 (Connecticut Superior Court, 1995)
Ermont Associates, Inc. v. Battenfeld
210 A.D.2d 293 (Appellate Division of the Supreme Court of New York, 1994)
Cimmino v. Town of Trumbull, No. 293612 (Feb. 28, 1994)
1994 Conn. Super. Ct. 2051 (Connecticut Superior Court, 1994)
Youdin v. Riley, No. Cv93 0129970 S (Jan. 11, 1994)
1994 Conn. Super. Ct. 424 (Connecticut Superior Court, 1994)
Rowley Engineering Assoc., P.C. v. Cuomo, No. 50 74 76 (Jan. 2, 1991)
1991 Conn. Super. Ct. 510 (Connecticut Superior Court, 1991)
Garten v. Chachkes, No. Cv87 0091673 S (Aug. 28, 1990)
1990 Conn. Super. Ct. 1224 (Connecticut Superior Court, 1990)
Barrett Builders v. Miller
576 A.2d 455 (Supreme Court of Connecticut, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
570 A.2d 221, 20 Conn. App. 685, 1990 Conn. App. LEXIS 46, Counsel Stack Legal Research, https://law.counselstack.com/opinion/design-development-inc-v-brignole-connappct-1990.