Desert Sunlight 250, LLC v. United States

CourtUnited States Court of Federal Claims
DecidedNovember 2, 2021
Docket17-1826
StatusPublished

This text of Desert Sunlight 250, LLC v. United States (Desert Sunlight 250, LLC v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Desert Sunlight 250, LLC v. United States, (uscfc 2021).

Opinion

CORRECTED

In the United States Court of Federal Claims No. 17-1826 T Filed: October 8, 2021 Re-issued: November 2, 20211

) DESERT SUNLIGHT 250, LLC and DESERT ) SUNLIGHT 300, LLC, ) ) Plaintiffs, ) ) v. ) ) THE UNITED STATES, ) ) Defendant. ) )

Steven J. Rosenbaum, Covington & Burling LLP, Washington, D.C., for Plaintiff. Dennis B. Auerbach, Sean M. Akins, Alexis N. Dyschkant, and Seth A. Mohney, of counsel.

Matthew D. Lucey, United States Department of Justice, Tax Division, Court of Federal Claims Section, Washington, D.C., with whom were Richard E. Zuckerman, Principal Deputy Assistant Attorney General, David I. Pincus, Chief, Court of Federal Claims Section, G. Robson Stewart, Assistant Chief, Court of Federal Claims Section, and Jason S. Selmont and Katherine Powers, Trial Attorneys, of counsel, for Defendant.

OPINION AND ORDER

MEYERS, Judge.

To encourage investment, Section 1603 of the American Recovery and Reinvestment Act of 2009 (“Section 1603”) provided cash grants to reimburse the cost of placing in service certain renewable energy properties. Here, Plaintiffs acquired and applied for Section 1603 grants for the Desert Sunlight solar energy project in California (the “Project”), which the Government largely approved and awarded the Plaintiffs $550 million in grants. But the Government did not approve $59 million of Plaintiffs’ application, and Plaintiffs sued to recover this $59 million. The Parties have cross moved for summary judgment and the Government has filed a motion in limine to strike certain statements in Plaintiffs’ declarations.

1 The Court issued this opinion under seal and directed the Parties to confer and propose any redactions pursuant to the protective order. Because the Parties advise that no redactions are necessary, the Court re-issues this opinion in full. The Government moves for summary judgment arguing that the Plaintiffs have not produced the required allocation of the consideration they paid for Desert Sunlight among all the assets Plaintiffs acquired. While the Plaintiffs did not submit their allocation on an IRS Form 8594, whether they provided sufficient information to support their claim is a factual issue that is not amenable to resolution on summary judgment. Therefore, the Court denies the Government’s motion insofar as it seeks judgment ending this case.

In the alternative, the Government seeks summary judgment on several legal questions about how assets should be categorized. Plaintiffs also seek summary judgment on these questions and several more. For the reasons explained below, these motions are granted-in-part and denied-in-part.

Finally, the Government has moved to strike certain statements in Plaintiffs’ witness declarations because they are either legal conclusions, hearsay, or the declarant has not laid the foundation for the challenged statements. Because none of the challenged statements are necessary for the resolution of the summary judgment motions, the Court does not consider them and denies the Government’s motion in limine as moot without prejudice to raise these objections at trial.

I. Background

A. The Desert Sunlight Facility, the LGIA, and the PPAs

The Desert Sunlight Facility (the “Facility”) is a massive solar energy power plant located in California’s Mohave Desert. Brannen Decl. ¶ 10 (ECF No. 86-3 at App’x 5).2 Sitting on a site roughly 20% of the area of Manhattan, the Facility occupies an area approximately 3.2 miles by 2.6 miles. Id. ¶ 11. Prior to the Facility, nobody had undertaken building a solar energy facility of similar size. Id. ¶ 20. As a solar photovoltaic (“PV”) electricity plant, the Facility converts sunlight into electricity. Id. ¶ 12. It does so using solar panels, or “modules,” to convert sunlight into direct current (“DC”) electricity. Id. ¶ 32. The Facility then uses inverters to convert the DC electricity into alternating current (“AC”) electricity for delivery to the utility transmission system. Id. (at App’x 21). As designed, the Facility’s DC generating capacity was projected to be 724 megawatts of DC (“MWdc”). As built, the Facility has a slightly greater 740.7 MWdc capacity. Id. ¶ 16. Its total AC generating capacity is approximately 550 megawatts of alternating current (“MWac”). Id. The Facility is comprised of two segments, a 250 MWac-capacity plant and a 300 MWac-capacity plant. Id. ¶ 17. Plaintiffs Desert Sunlight 250, LLC and Desert Sunlight 300, LLC own the 250 MWac plant and the 300 MWac plant, respectively. ECF No. 1 ¶¶ 10-11. The Facility entered service in 2014. Brannen Decl. ¶ 10.

2 As detailed more below, Mr. Brannen was NextEra’s Senior Director of Project Engineering and Due Diligence. He served as a lead contract negotiator and oversaw the Plaintiffs’ team that was on-site for the Desert Sunlight Facility’s construction.

2 Before the Facility’s construction, Plaintiffs were owned by First Solar, Inc. (“First Solar”).3 ECF No. 1 ¶ 40. First Solar is a leading manufacturer of “thin film” solar modules, which are widely used in solar PV facilities throughout the world. Brannen Decl. ¶ 15. First Solar is also a leader in developing, financing, engineering, constructing, operating, and selling many of the world’s largest grid-connected solar PV power plants. Id.; see also ECF No. 81-2 at App’x 26. Before construction begins on a solar PV facility, the developer generally “execut[es] an interconnection agreement” and “enter[s] into a power purchase agreement” (“PPA”). ECF No. 81-2 at App’x 31. An interconnection agreement “is a contract in which a utility scale electricity producer obtains the right to interconnect its facility to the electricity grid,” through which it can then transport its electricity to the purchaser. Charles Decl. ¶ 9 (ECF No. 86-6 at App’x 1127).4 “A PPA is a long-term contract in which an electricity producer agrees to sell electricity to a utility or other customer pursuant to an agreed pricing formula[] . . . .” Id. First Solar achieved both milestones as Plaintiffs’ owner while developing the Facility. Id.

In 2010, Plaintiffs entered into a Standard Large Generator Interconnection Agreement (“LGIA”) with the Southern California Edison Company (“SCE”) and the California Independent System Operator Corporation (“CAISO”). ECF No. 81-29 at App’x 2650, 2718-20. Under the LGIA, Plaintiffs secured the right to interconnect the Facility to CAISO’s electricity grid by way of SCE’s transmission system once the Facility became operational. Id. at App’x 2650, 2656-57, 2661-62. Also, Plaintiffs were responsible for building everything necessary to connect the Facility to a substation that SCE was responsible for building. Id. at App’x 2722-23. In other words, the SCE substation served as the handoff point of the Facility’s electricity to the power grid; Plaintiffs were responsible for delivering electricity to the substation and SCE was responsible for transporting it to the grid.

Plaintiffs also executed two PPAs for the output of the Facility. In 2009, Plaintiffs executed a PPA with SCE. ECF No. 81-21; ECF No. 81-20 at App’x 2030. Under this PPA, SCE agreed to purchase the total electrical output from DS 250 for 20 years. ECF No. 81-21 at App’x 2062, 2071. And in 2010, Plaintiffs executed a PPA with Pacific Gas and Electric Company (“PG&E”). ECF No. 81-22 at App’x 2299. Here, PG&E agreed to purchase the total electrical output from DS 300 for 25 years. Id. at App’x 2324.

B. First Solar Sells the Facility to GE and NextEra

In 2011, First Solar began negotiating with NextEra Energy Resources, LLC (“NextEra”) and GE Energy Financial Services (“GE”) to sell First Solar’s interest in Plaintiffs. Brannen Decl. ¶ 13. NextEra builds and operates solar power facilities. Id. ¶¶ 7-8.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Cartwright
411 U.S. 546 (Supreme Court, 1973)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Suitum v. Tahoe Regional Planning Agency
520 U.S. 725 (Supreme Court, 1997)
Whitehouse Hotel Ltd. Partnership v. Commissioner
615 F.3d 321 (Fifth Circuit, 2010)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Schonfeld v. Hilliard
218 F.3d 164 (Second Circuit, 2000)
W.E. Partners II, LLC v. United States
119 Fed. Cl. 684 (Federal Claims, 2015)
Alta Wind I Owner Lessor v. United States
897 F.3d 1365 (Federal Circuit, 2018)
Westrock Virginia Corporation v. United States
941 F.3d 1315 (Federal Circuit, 2019)
Solitron Devices, Inc. v. Commissioner
80 T.C. No. 1 (U.S. Tax Court, 1983)
East Ford v. Commissioner
1994 T.C. Memo. 261 (U.S. Tax Court, 1994)
Pabst Brewing Co. v. Commissioner
1995 T.C. Memo. 239 (U.S. Tax Court, 1995)
Innovair Aviation, Ltd. v. United States
83 Fed. Cl. 498 (Federal Claims, 2008)
Propstra v. United States
680 F.2d 1248 (Ninth Circuit, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
Desert Sunlight 250, LLC v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/desert-sunlight-250-llc-v-united-states-uscfc-2021.