Derrico Construction Corp. v. Loxahatchee River Environmental Control District (In Re Derrico Construction Corp.)

10 B.R. 553, 1981 Bankr. LEXIS 4655
CourtUnited States Bankruptcy Court, M.D. Florida
DecidedMarch 19, 1981
DocketBankruptcy 78-672 Orl P
StatusPublished
Cited by5 cases

This text of 10 B.R. 553 (Derrico Construction Corp. v. Loxahatchee River Environmental Control District (In Re Derrico Construction Corp.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, M.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Derrico Construction Corp. v. Loxahatchee River Environmental Control District (In Re Derrico Construction Corp.), 10 B.R. 553, 1981 Bankr. LEXIS 4655 (Fla. 1981).

Opinion

FINDINGS OF FACT, CONCLUSIONS OF LAW AND MEMORANDUM OPINION

ALEXANDER L. PASKAY, Chief Judge.

THE MATTER under consideration is an adversary proceeding initiated by Derrico Construction Corp. (Derrico), the Debtor involved in the above-captioned arrangement proceeding. Derrico seeks a determination that certain claims made by the Defendant, Loxahatchee River Environmental Control District (District) are dischargeable; therefore, the District is barred from seeking a recovery from Derrico by virtue of the Order of Confirmation which under § 371 operates as a discharge of all dischargeable debts of a Debtor. The District in opposition of a claim of dischargeability claims first that since the District was not listed as a creditor, did not receive notice of the proceeding in time for a meaningful participation in the proceeding, its claim against Derrico would not be dischargeable by virtue of § 17(a)(3) of the Act. In addition, it is the contention of the District that at the time the Chapter XI proceeding was commenced, its contract with Derrico was still in the executory stage, it was still in the process of being performed was not in default and, therefore, there was no provable debt in existence on the date of the commencement of the case, therefore, its claim against Derrico cannot be affected by the arrangement proceeding and the order of confirmation would not operate as a discharge of this debt.

The facts germane and relevant to this controversy, as they appear from the record, can be summarized as follows:

On October 13, 1978, Derrico filed its petition for relief under Chapter XI of the Bankruptcy Act. At the time it filed its schedules, Derrico did not list the District as a creditor. In addition, the District never filed any proof of claim in the proceeding, nor did it participate in any manner in the plan of arrangement which was subsequently confirmed by this Court.

*555 There is no question, however, that the District did in fact receive actual notice on October 18, 1978 of the filing of the Chapi-ter XI proceeding. On that date, Derrico’s surety, The Travelers Indemnity Company, through its attorneys, sent a letter to the District advising it that Derrico had filed a Chapter XI proceeding and requested that the District not disburse any construction funds to Derrico until such time as the surety could determine the effect of the Chapter XI filing upon Derrico’s ability to perform its contract with the District.

■ It is this Court’s opinion that notice, from whatever source, is sufficient to meet the requirements of § 17(a)(3). Under § 17(a)(3), a debt is not dischargeable if it was not scheduled in time for proof and allowance, unless the creditor had “notice or actual knowledge” of the proceeding. The Court finds that the District did have actual knowledge of the pendency of the arrangement, accordingly, the order of confirmation would have released Derrico from any debt owed to the District, if the debt was a provable debt, on date of the filing of the petition. This leads to the ultimate question which is the provability, vel non, of a debt if any owed by Derrico to the District.

The factual background of the relationship of the parties as it appears from the record can be summarized as follows:

On May 13,1977, Derrico and the District entered into a construction contract. Under the terms of this contract, Derrico was to construct approximately 3.6 miles of iron forced main pipeline for the District. The pipeline was designed to carry sewage effluent from the District’s sewage and waste water treatment facility to the District’s off-site discharge pond. The contract provided for completion date of 210 days from the Notice to Proceed. The notice was issued on June 1,1977 by the District. Derri-co promptly commenced construction of the pipeline.

It is without dispute that leaks existed from the very beginning in the pipeline installed by Derrico. As of the date of the filing of the Chapter XI petition the District had not, however, called a default on the project. Nor did Derrico at the time of the filing of its petition consider the District its creditor as evidenced by the fact that it did not list the District as one of its creditors in the Schedule of Liabilities filed in this case. To the contrary, the parties to the contract continued negotiating for a substantial period of time following the filing of the petition attempting to arrive at a completion of the contract to the satisfaction of both parties. It is without doubt that the contract was not considered finished by either party until the testing and corrective work was completed. It was the District’s position throughout that it would not accept the project until the project was completed in accordance with the terms of the contract.

Under the terms of the contract, the one year warranty period was to commence from the date of the District’s final acceptance of the pipeline. Prior to such final acceptance, absent a declaration of default, under Article 19 of the contract, the contractor was required to remove and replace all materials and work not accepted by the owner on the ground that it failed to conform to the contract. In addition, under the general conditions set forth in Article 25, the fact that the owner took possession and used part of the completed or partially completed portions of the pipeline, did not constitute an acceptance of the work performed by Derrico. The fact that the physical installation of the pipeline was completed did not conclude and terminate the respective responsibilities of the parties. It is clear from the contract documents as well as from the testimony produced at the trial that the completion of the actual installation would fulfill only the initial phase of the contract and the completion of the actual work was not finished until the testing phase would be completed and the project is accepted by the District.

During the testing, the nature and extent of the leaks became obvious. Based upon this, the District refused to accept the work. While refusing to accept the work, in reliance on the continued assurances of Derri-co that steps will be taken to complete the *556 project and the corrective work, the District did not call a default, but rather gave Der-rico additional time to complete the performance by curing the defects.

These continued attempts to complete the contract continued on at least until March of 1979 when a meeting was held between Derrico and the District. The purpose of the meeting was to see if some agreement could be reached as to a manner of correcting the problems revealed by the testing of the pipeline.

It was Derrico’s position at that meeting that the mere repair of the 16 leaks would constitute “substantial performance” under the contract, therefore, Derrico was entitled to its final payment under the contract and the warranty period commenced to run if the corrective work was done. It was the District’s position at that meeting that it contracted for “new” pipeline and that the proposed method of repairing the leaks, that is, placing clamps on them, would not result in completion of the contract in accordance with its terms and the one year warranty period did not commence to run until the project was completed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Glow
111 B.R. 209 (N.D. Indiana, 1990)
Slaiby v. Rassman (In Re Slaiby)
57 B.R. 770 (D. New Hampshire, 1985)
Slaiby v. Rassman (In Re Slaiby)
50 B.R. 245 (D. New Hampshire, 1985)
In Re McCrady
23 B.R. 193 (W.D. Kentucky, 1982)
Klein v. Davis (In Re Davis)
19 B.R. 487 (S.D. Florida, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
10 B.R. 553, 1981 Bankr. LEXIS 4655, Counsel Stack Legal Research, https://law.counselstack.com/opinion/derrico-construction-corp-v-loxahatchee-river-environmental-control-flmb-1981.