Dept. Of Labor & Industries, V. Potelco, Inc.:jeff Lampman & Brett Mongomery

CourtCourt of Appeals of Washington
DecidedNovember 25, 2024
Docket86066-6
StatusUnpublished

This text of Dept. Of Labor & Industries, V. Potelco, Inc.:jeff Lampman & Brett Mongomery (Dept. Of Labor & Industries, V. Potelco, Inc.:jeff Lampman & Brett Mongomery) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dept. Of Labor & Industries, V. Potelco, Inc.:jeff Lampman & Brett Mongomery, (Wash. Ct. App. 2024).

Opinion

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

DEPARTMENT OF LABOR AND INDUSTRIES, No. 86066-6-I

Appellant, DIVISION ONE

v. UNPUBLISHED OPINION

POTELCO, INC.; JEFF LAMPMAN; and BRET MONTGOMERY;

Respondents.

MANN, J. — The Department of Labor and Industries (Department) issued

citations to Potelco, Inc., Jeff Lampman, and Bret Montgomery, (collectively Potelco) for

electrical work done installing Verizon 5G equipment on Seattle City Light utility poles.

Potelco appealed arguing that its work was exempt from the licensing requirements of

ch. 19.28 RCW because the “utility exemption” in RCW 19.28.010(1) applied. The

Office of Administrative Hearings (OAH) and the Electrical Board of the State of

Washington (Board) affirmed the citations. The King County Superior Court reversed

concluding that the utility exemption applied. We agree with the superior court and

conclude the utility exemption applied to Potelco’s work. We affirm the superior court,

reverse the Board’s final order, and remand to the Board to vacate the citations. No. 86066-6-I/2

I

Potelco is a licensed electrical contractor. Potelco’s electrical administrator is

Jeff Lampman whose role is to ensure that Potelco complies with all applicable laws

and regulations. Bret Montgomery is a journey-level, high-voltage lineman and has

worked for Potelco off and on since 2007.

Potelco has a multi-year contract with Seattle City Light to perform electrical

work on its utility poles. Verizon contracted with Seattle City Light to have 5G

equipment installed on Seattle City Light utility poles. Seattle City Light paid Potelco to

perform the installations. Between August and December 2020, Potelco obtained 52

permits for installing the Verizon 5G equipment on Seattle City Light utility poles.

Potelco began performing these installations in fall 2020.

Montgomery was the project foreman. The project involved installing a

disconnect switch on the utility pole. Montgomery testified that installation involved a

simple wiring process performed on a box with individual breakers, similar to a fuse box

in a residential house.

On December 4, 2020, Annette Lake, an inspector with the City of Seattle

inspected one of the installations. While investigating, she learned that Montgomery

made the installation, but he was not an 01 certified electrician. Lake reported her

concern to her supervisor, Tim Rasmussen, and to Sergey Zinakov, an electrical

inspector with the Department. Zinakov investigated and confirmed that Montgomery

did not meet the licensing requirements of ch. 19.28 RCW. Prior to the citations, 35 of

the 52 installations had been inspected and approved by the City of Seattle.

-2- No. 86066-6-I/3

Zinakov issued noncompliance citations to Potelco, Lampman, and Montgomery.

Potelco was cited for employing an individual to perform electrical work for which he

was not licensed, a violation of RCW 19.28.271. Lampman was cited for failing as an

administrator to ensure all the electrical work performed by Potelco followed the law, a

violation of RCW 19.28.061(5)(d). Montgomery was cited for performing electrical work

without the proper license, a violation of RCW 19.28.161. The Department fined

Potelco, Lampman, and Montgomery $250 for each of the 52 installations, for a total of

$13,000 each.

Potelco, Lampman, and Montgomery jointly appealed their citations to OAH. An

OAH administrative law judge affirmed the citations in an initial order. The OAH

reasoned that none of the exemptions in RCW 19.28.010(1) apply. The OAH

specifically rejected the argument that the utility exemption applied. The OAH reduced

the penalties to $12,500 because the evidence showed only 50 of the 52 installations

had been completed.

Potelco appealed the initial order to the Board. The Board adopted and

incorporated the OAH’s findings and conclusions of law. Potelco then appealed to the

King County Superior Court. The superior court reversed, finding that the Board

erroneously interpreted the law when it concluded that the utility exemption did not

apply. The court concluded that the utility exemption applied because Potelco and

Montgomery performed the work for the purpose of communication under a contract

that was under the control of an electric utility. The court reversed the citations under

RCW 34.04.574(1) and remanded to vacate the citations.

The Department appeals.

-3- No. 86066-6-I/4

II

Potelco argues that the citations should be vacated because the work was

exempt from the licensing requirements in ch. 19.28 RCW under the “utility exemption”

in RCW 19.28.010(1). We agree.

A

Under the Washington Administrative Procedure Act (APA), ch. 34.05 RCW, we

directly review the Board’s decision based on the record before the agency. Pilchuck

Contractors, Inc. v. Dep’t of Lab. & Indus., 170 Wn. App. 514, 517, 286 P.3d 383

(2012). When reviewing an agency decision under the APA, we sit in the same position

as the superior court and give no deference to the superior court’s findings.

Darkenwald v. Emp’t Sec. Dep’t, 183 Wn.2d 237, 244, 350 P.3d 647 (2015). “The

burden of demonstrating the invalidity of agency action is on the party asserting

invalidity.” RCW 34.05.570(1)(a). While the Department is the appellant before this

court, Potelco has the burden of demonstrating the invalidity of the Board’s decision.

We review the Board’s conclusions of law de novo. Whatcom County v. Hirst,

186 Wn.2d 648, 667, 381 P.3d 1 (2016). An appellant is entitled to relief if the Board

erroneously interpreted or applied the law, if the conclusions are not supported by the

findings, or if the decision is inconsistent with an agency rule. Clausing v. State, 90 Wn.

App. 863, 870, 955 P.2d 394 (1998).

We interpret statutes and regulations alike, de novo. Wash. Cedar & Supply Co.

v. Dep’t of Lab. & Indus, 137 Wn. App. 592, 598, 154 P.3d 287 (2007). When

interpreting statutes and regulations we look first to the plain language. HomeStreet,

Inc. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Garrison v. Washington State Nursing Board
550 P.2d 7 (Washington Supreme Court, 1976)
Clausing v. State
955 P.2d 394 (Court of Appeals of Washington, 1998)
HomeStreet, Inc. v. STATE, DEPT. OF REVENUE
210 P.3d 297 (Washington Supreme Court, 2009)
Washington Cedar & Supply Co. v. State
154 P.3d 287 (Court of Appeals of Washington, 2007)
HomeStreet, Inc. v. Department of Revenue
166 Wash. 2d 444 (Washington Supreme Court, 2009)
Darkenwald v. Employment Security Department
350 P.3d 647 (Washington Supreme Court, 2015)
Washington Cedar & Supply Co. v. Department of Labor & Industries
137 Wash. App. 592 (Court of Appeals of Washington, 2007)
Pilchuck Contractors, Inc. v. Department of Labor & Industries
286 P.3d 383 (Court of Appeals of Washington, 2012)
Clausing v. State
955 P.2d 394 (Court of Appeals of Washington, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
Dept. Of Labor & Industries, V. Potelco, Inc.:jeff Lampman & Brett Mongomery, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dept-of-labor-industries-v-potelco-incjeff-lampman-brett-washctapp-2024.