Department of Transportation v. IA Construction Corp.

588 A.2d 1327, 138 Pa. Commw. 587, 1991 Pa. Commw. LEXIS 165
CourtCommonwealth Court of Pennsylvania
DecidedMarch 28, 1991
Docket1373 C.D. 1990
StatusPublished
Cited by7 cases

This text of 588 A.2d 1327 (Department of Transportation v. IA Construction Corp.) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Department of Transportation v. IA Construction Corp., 588 A.2d 1327, 138 Pa. Commw. 587, 1991 Pa. Commw. LEXIS 165 (Pa. Ct. App. 1991).

Opinion

McGINLEY, Judge.

The Department of Transportation (DOT) petitions for review of an order of the Board of Claims (Board) awarding IA Construction Corporation (IA) $19,683.90 and Cleveland Wrecking Co. (Cleveland) $70,000.00 in a contract dispute. The issues presented for our review are whether the Board erred in ruling that a bridge reconstruction contract between DOT and IA was ambiguous with regard to the type of protection required to shield an underlying refinery owned by Gulf Oil Company (Gulf Oil) from falling debris and whether the Board erred, by ignoring substantial evidence, in ruling that DOT ratified Cleveland’s interpretation of the term “positive shielding” at a November 30, 1982 meeting between the parties. We affirm.

On September 8, 1982, IA entered into a contract with DOT for highway improvements in the City of Philadelphia which encompassed the reconstruction of the George M. Platt Bridge (Bridge) and its approaches carrying Penrose Avenue across the Schuylkill River. IA, the general contractor, subsequently negotiated with Cleveland, a subcontractor, for certain demolition, removal, and disposal work on the project.

On November 30, 1982, a meeting was held between IA, DOT, Cleveland, and Gulf Oil to discuss demolition of a *591 portion of the Bridge’s old superstructure. The general contract required that “the contractor shall provide positive shielding to protect Gulf Oil’s property from any falling concrete, steel, sparks or any other equipment, or material during any of the contractors’ or subcontractors’ operations.” (Emphasis added.) Reproduced Record (R.R.) at 31a-32a. This provision of the contract, entitled “Protection of Gulf Oil Company Facilities,” also required that protection and shielding schemes be submitted for approval by DOT and Gulf Oil. R.R. at 32a. At the meeting, Cleveland described its plan of demolition and shielding. Cleveland’s plans were accepted by DOT and Gulf Oil. As a result, Cleveland formally entered into the subcontract. Cleveland’s plan for shielding included vertical metal shields to prevent falling debris from bouncing into areas of Gulf Oil’s refinery as well as on-ground measures including snow fences erected to keep pedestrians from walking underneath the Bridge.

Following the November 30, 1982 meeting, Cleveland commenced its demolition operations in accordance with its plans. In January of 1983, during the course of Cleveland’s demolition work, several small concrete pieces fell to the ground on Gulf Oil’s property. On January 25, 1983, Gulf Oil requested that DOT require IA to place continuous solid shielding underneath the Bridge from Second Street to the river. On February 1,1983, DOT issued a written directive ordering IA to install the continuous solid shielding as requested by Gulf Oil. Cleveland objected to DOT’s directive and a meeting was subsequently held between the parties. Nonetheless, DOT refused to consider any alternative to the installation of continuous solid sheeting under the deck of the Bridge from Second Street to the river. IA employees then installed the wood sheeting under the Bridge and charged the work to Cleveland’s account.

IA and Cleveland presented claims to DOT for additional compensation as a result of the directive to install the continuous solid shielding. DOT denied the claims. IA and Cleveland subsequently filed a claim before the Board for *592 the additional compensation. Hearings were held at which IA, Cleveland, and DOT presented evidence. On June 4, 1990, the Board issued its decision awarding IA $89,683.90 for the installation of the shielding with the direction that $70,000.00 of the award was for the use and benefit of Cleveland. DOT appeals.

On appeal from a Board decision, our scope of review is limited to determining whether the necessary findings of fact were supported by substantial evidence, whether an error of law was committed or whether constitutional rights were violated. 2 Pa.C.S. § 704; Department of Transportation v. Burrell Construction and Supply Co., 111 Pa.Commonwealth Ct. 590, 534 A.2d 585 (1987).

DOT first contention is that the Board committed an error of law in ruling that the contract between IA and DOT was ambiguous. Specifically, DOT alleges that the method requested by DOT (continuous solid shielding) was within the scope of the contract; that the schemes initially utilized by IA were ineffective and thus DOT had a contractual right to require an effective method; and that the Board erred in ruling that DOT could have made the contract clearer.

In its decision, the Board noted that although under the terms of the contract, IA was to provide “positive shielding” to protect Gulf Oil’s property, the term “positive shielding” was not defined and was subject to different interpretations. Board’s Decision, June 4, 1990 at 8. Thus, the Board concluded that the term “positive shielding” was ambiguous and that an examination of the contract documents did not provide a definition of “positive shielding.” Board’s Decision at 8-9. The Board further noted that “positive shielding” could easily have been more precisely defined by DOT as “continuous solid shielding.”

To begin, we note that the function of contract interpretation and construction is a question of law peculiarly within the province of this Court’s review. Department of Transportation v. Mosites Construction Co., 90 *593 Pa.Commonwealth Ct. 33, 36, 494 A.2d 41, 43 (1985). If a contract is reasonably susceptible of different constructions, is obscure in meaning through indefiniteness of expression or has a double meaning, then it is ambiguous. Id. If the intention of the parties is unclear from the words of the contract, we may examine extrinsic evidence including consideration of the subject matter of the contract, the circumstances surrounding its execution, and the subsequent acts of the parties. Id., 90 Pa.Commonwealth Ct. at 37, 494 A.2d at 43. Furthermore, although the general rule is to resolve ambiguities against the drafter of the contract, decisional law has created an exception for government construction contracts which contain an obvious or glaring ambiguity. In such cases, the contractor is obliged to inquire and attempt to resolve the problem before entering into the contract. Id., 90 Pa.Commonwealth Ct. at 38, 494 A.2d at 44.

In the present case, the Board made the finding that the term “positive shielding” was interpreted differently by DOT, IA, Cleveland and Gulf Oil. Finding of Fact No. 27. The Board also made the finding that the vertical metal shields erected by Cleveland constituted a form of positive shielding. Finding of Fact No. 28. The Board also noted that “positive shielding” was not defined in the general contract and that various forms of positive shielding exist for bridge demolition. Finding of Fact No. 21. The Board further noted that the “continuous solid shielding,” as required by DOT, did not prevent concrete from falling to the ground. Finding of Fact No. 33. These findings are supported by substantial evidence. H. William Merz, Jr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kingsly Compression, Inc. v. MOUNTAIN v. OIL & GAS, INC.
745 F. Supp. 2d 628 (W.D. Pennsylvania, 2010)
Electroplating Technologies Ltd. v. HH Sumco Inc.
11 Pa. D. & C.5th 160 (Lehigh County Court of Common Pleas, 2009)
Penn Township v. Aetna Casualty & Surety Co.
719 A.2d 749 (Superior Court of Pennsylvania, 1998)
Ardrey Insurance Agency, Inc. v. Insurance Co. of Decatur
656 A.2d 936 (Superior Court of Pennsylvania, 1995)
Drummond v. University of Pennsylvania
651 A.2d 572 (Commonwealth Court of Pennsylvania, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
588 A.2d 1327, 138 Pa. Commw. 587, 1991 Pa. Commw. LEXIS 165, Counsel Stack Legal Research, https://law.counselstack.com/opinion/department-of-transportation-v-ia-construction-corp-pacommwct-1991.