Department of Transportation v. Hardin-Sunbelt, Joint Venture

596 S.E.2d 397, 266 Ga. App. 139, 2004 Fulton County D. Rep. 613, 2004 Ga. App. LEXIS 167
CourtCourt of Appeals of Georgia
DecidedFebruary 11, 2004
DocketA03A1876
StatusPublished
Cited by9 cases

This text of 596 S.E.2d 397 (Department of Transportation v. Hardin-Sunbelt, Joint Venture) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Department of Transportation v. Hardin-Sunbelt, Joint Venture, 596 S.E.2d 397, 266 Ga. App. 139, 2004 Fulton County D. Rep. 613, 2004 Ga. App. LEXIS 167 (Ga. Ct. App. 2004).

Opinion

ANDREWS, Presiding Judge.

Following a jury trial and verdict 1 in favor of Hardin-Sunbelt, Joint Venture (Hardin) on its breach of contract claim against the Department of Transportation (DOT), DOT appeals, contending, on numerous grounds, that the trial court improperly denied its motion for directed verdict.

“Where a jury returns a verdict and it has the approval of the trial judge, the same must be affirmed on appeal if there is any evidence to support it as the jurors are the sole and exclusive judges of the weight and credit given the evidence. *140 The appellate court must construe the evidence with every inference and presumption in favor of upholding the verdict, and after judgment, the evidence must be construed to uphold the verdict even where the evidence is in conflict. As long as there is some evidence to support the verdict, the denial of defendant’s motion for directed verdict, new trial and j.n.o.v. will not be disturbed.” (Punctuation omitted.) Southeastern Security Ins. Co. v. Hotle, 222 Ga. App. 161, 162 (1) (473 SE2d 256) (1996).

Gantt v. Bennett, 231 Ga. App. 238, 240 (1) (499 SE2d 75) (1998).

Viewed in favor of the jury’s verdict, the evidence was that, by contract of October 25,1995, DOT, as owner, contracted with Hardin as general contractor for construction of 1.283 miles of Sugarloaf Parkway in Gwinnett County, a $23 million project including construction of a portion of roadway, associated bridges, and an interchange. Incorporated into that contract was DOT’s “Standard Specification-Construction of Roads and Bridges.” Hardin then subcontracted with numerous subcontractors for portions of the project and all subcontracts also incorporated DOT’s Standard Specification. On January 6, 1996, Hardin and Dinsmore Grading (Dinsmore) entered into a $4.5 million subcontract dealing with the project’s earthwork. This earthwork included the restoration of a lake adjacent to the roadway construction. The lake, approximately two acres, was owned by Boeing Corporation (formerly Rockwell, Inc.) and was included in a temporary construction easement obtained by DOT. Although Section 166 of the Standard Specification provided that a lake such as the Boeing lake could be used as a sediment basin during the project, DOT wanted to keep the lake clear of siltation. By amendment to the specifications in October 1995, DOT provided, instead, that a sediment basin be created at the head of the lake by constructing a rock check dam to collect most sediment before it entered the lake. DOT had experience with another lake in the same area which had totally filled up while being used as a sediment basin and did not want this to happen to the Boeing lake. It was intended that most silt would be stopped by the dam and that which filtered through would be removed periodically from the lake from the top of the dam by Dinsmore. '

The bid documents and contract list the sediment basin and lake restoration items as separate items, with the lake restoration item identified as “lump sum” and bid by Dinsmore at $88,835. As stated by Section 109.01 of the Standard Specification, “[t]he term ‘Lump Sum’ when used as an item of payment will mean complete payment for the Work described in the Contract.”

*141 Section 166.03.A of the Standard Specification regarding lake restoration provides that

[a]fter the Roadway Work is completed to a point where the normal grass has produced a stand of sufficient density to prevent erosion and further pollution of the lake, the Contractor shall excavate, and clean the lake of all foreign matter to its original contour and condition or proposed contour, if different than the original. All material removed shall be disposed of in a manner satisfactory to the Engineer.

(Emphasis supplied.)

In order to determine the original contour of the lake, DOT conducted a survey of the lake by measuring its depth and contours before construction began. Following completion of the project, a second survey was conducted and it indicated that the lake contained more water after construction than before, indicating that material had been removed from the lake.

Kenneth Dinsmore, general superintendent for Dinsmore Grading on the Sugarloaf project, was on the job site daily and discussed the condition of the lake with Hawkins, his project foreman. He told Hawkins to keep the lake as clean as possible and wanted any silt to be removed by using the access they had, which was the rock check dam. Hawkins removed silt from the lake by using a backhoe on the rock check dam, removing 50 to 60 buckets per hour on at least several occasions. Hawkins cleaned silt from the lake and deposited the material into the sediment basin. Periodically, the sediment basin was emptied by loading the material into dump trucks and taking it to another area where it was spread and dried, to be dealt with later. The material was soupy and the trucks could not be fully loaded because it was like hauling water and when the trucks exited the lake area, it would run out the back of the truck.

Dinsmore had to build a dam around the area used to dry the silt and the drying frequently took weeks. Removing the silt from the sediment basin, including that which had previously been removed from the lake, trucking it out of the area, and drying it took as many as five pieces of heavy equipment and a half-dozen employees.

Although the contract provided that, upon completion of the project, the rock check dam and sediment basin would be removed, Boeing decided that it wanted the rock check dam left in place. As acknowledged by Graham, who was the State Construction Engineer for DOT during the Sugarloaf project, the contract provided that payment for the sediment basin item was made 75 percent upfront, with the remaining 25 percent due when the DOT advised Hardin that the sediment basin was no longer required and was to remain in *142 place or when the dam and sediment basin were removed, “whichever is applicable.” It was not disputed that full payment was made by DOT for the sediment basin item.

Boeing required a lien waiver from Dinsmore and a release from Hardin of any obligation to pay for any work done on the sediment basin or lake restoration. The lien waiver was provided to Boeing May 13, 1999, and the release, signed by Hardin and Dinsmore, was provided in August. Boeing, in September 1999, also provided a release, which stated that Boeing released DOT, Hardin, and Dins-more “from all liability of any nature, either present or consequential in connection with the restoration of Lake, Station 1050 + 00 Left, 1-85.” When Dinsmore began pursuing payment of the lump sum item for lake restoration, DOT made obtaining this release one of the items on its punch list. DOT received the release signed by Boeing on January 6, 2000.

By letter of January 25, 2000, DOT advised Hardin that

[t]he Department has received the original signature release from Rockwell International/Boeing North American, Inc. However, we cannot remit payment for the Restoration of Lake line item. Rockwell/Boeing has apparently accepted the lake in its current state.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Capital Health Management Group Inc. v. Hartley
689 S.E.2d 107 (Court of Appeals of Georgia, 2009)
Clements v. Weaver
687 S.E.2d 602 (Court of Appeals of Georgia, 2009)
Asgharneya v. Hadavi
680 S.E.2d 866 (Court of Appeals of Georgia, 2009)
City of Lilburn v. Astra Group, Inc.
649 S.E.2d 813 (Court of Appeals of Georgia, 2007)
The Cupboard, LLC v. Sunshine Travel Center
640 S.E.2d 584 (Court of Appeals of Georgia, 2006)
Anderson v. Cayes
630 S.E.2d 441 (Court of Appeals of Georgia, 2006)
Morrison Homes of Florida, Inc. v. Wade
598 S.E.2d 358 (Court of Appeals of Georgia, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
596 S.E.2d 397, 266 Ga. App. 139, 2004 Fulton County D. Rep. 613, 2004 Ga. App. LEXIS 167, Counsel Stack Legal Research, https://law.counselstack.com/opinion/department-of-transportation-v-hardin-sunbelt-joint-venture-gactapp-2004.