Denver v. Leopardo Cos., Inc.

2019 IL App (1st) 181079-U
CourtAppellate Court of Illinois
DecidedDecember 12, 2019
Docket1-18-1079
StatusUnpublished

This text of 2019 IL App (1st) 181079-U (Denver v. Leopardo Cos., Inc.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Denver v. Leopardo Cos., Inc., 2019 IL App (1st) 181079-U (Ill. Ct. App. 2019).

Opinion

2019 IL App (1st) 181079-U No. 1-18-1079 Order filed December 12, 2019 Fourth Division

NOTICE: This order was filed under Supreme Court Rule 23 and may not be cited as precedent by any party except in the limited circumstances allowed under Rule 23(e)(1). ______________________________________________________________________________ IN THE APPELLATE COURT OF ILLINOIS FIRST DISTRICT ______________________________________________________________________________ MICHAEL DEVER, ) Appeal from the ) Circuit Court of Plaintiff-Appellant, ) Cook County. ) v. ) No. 15 L 11791 ) LEOPARDO COMPANIES, INC., PRECISION ) CEMENT COMPANY INC., K.R. MILLER ) CONTRATORS, INC., G & V CONSTRUCTION ) COMPANY, INC., DYNASTY PLUMBING GROUP, ) LLC, and POLI CONTRACTING, INC., ) ) Defendants ) Honorable ) John H. Ehrlich, (Poli Contracting, Inc., Defendant-Appellee). ) Judge, presiding.

JUSTICE LAMPKIN delivered the judgment of the court. Justices Reyes and Burke concurred in the judgment.

ORDER

¶1 Held: The defendant subcontractor plumber was entitled to summary judgment because the plaintiff, an ironworker who was injured at a construction site when his foot slid into a pipe trench, failed to present a factual basis that would arguably entitle him to a judgment where there was no genuine issue as to the material fact that No. 1-18-1079

the defendant did not work at the site before the plaintiff was injured and thus did not create the trench or install the pipe sleeve that caused the plaintiff’s injury.

¶2 In this interlocutory appeal from his personal injury cause of action, plaintiff Michael

Dever, an ironworker who was injured while working at a construction site, challenges the trial

court’s award of summary judgment in favor of defendant Poli Contracting, Inc. (Poli).

¶3 On appeal, plaintiff argues the record shows that a genuine issue of material fact exists

regarding whether Poli created the condition that caused plaintiff’s injury because some

deposition testimony conflicted with Poli’s assertion that it did not commence work at the

construction site prior to the date of plaintiff’s injury.

¶4 For the reasons that follow, we affirm the judgment of the circuit court. 1

¶5 I. BACKGROUND

¶6 According to the pleadings, depositions and affidavits filed in this matter, plaintiff was

injured while working at a construction site at an elementary school. The construction project

was divided into two phases. During the first phase, which generally involved building the

foundation and installing a perimeter fence, grade beams and caissons, 2 Leopardo Companies,

Inc. (Leopardo) was the general contractor. During the second phase, which generally involved

the construction of a building on the foundation, K.R. Miller Contractors, Inc. (K.R. Miller) was

the general contractor, its project manager was Derek Taylor, and its general superintendent was

Paul Ingraham.

1 In adherence with the requirements of Illinois Supreme Court Rule 352(a) (eff. July 1, 2018), this appeal has been resolved without oral argument upon the entry of a separate written order. 2 A grade beam is “a sill of structural steel or reinforced concrete atop the foundation of a building and supporting a wall at or near ground level.” A caisson is “a watertight chamber used in construction work under water or as a foundation. Merriam-Webster’s Dictionary, http://www.merriam- webster.com (2019).

-2- No. 1-18-1079

¶7 Plaintiff’s injury occurred during the project’s second phase. At that time, K.R. Miller

had subcontracted with Dynasty Plumbing Group, LLC (Dynasty) to do the plumbing work at

the site. Dynasty’s vice president was Dan Humphries. Dynasty had subcontracted with Poli, a

sole proprietorship, to do plumbing-related site work that involved digging trenches for the

placement of water main pipes and then backfilling the trenches.

¶8 Plaintiff was employed as an ironworker by subcontractor M.A. Steel Erectors, Inc., to

install rebar and grade beam. According to his deposition, when his injury occurred in January

2014, the temperature was below freezing and there were mounds of snow and ice on the ground

at the work site. The ironworkers did not have a clean and level lay-down area for the rebar

because the ground was uneven and rocky and contained holes or trenches that were not

backfilled. Plaintiff described the work conditions at the site as “ugly” and “unsafe” but, “to get

the job done,” the ironworkers “had to do what [they] had to do.”

¶9 Plaintiff observed only one pipe trench in his work area at the site. The pipe trench was

about two feet deep and was not backfilled or “sectioned off” with “barriers.” The work area also

had a grade beam trench, which was about four feet below street grade level and did not have

any ladders. As an ironworker, plaintiff would jump in and crawl out of the grade beam trench

several times a day.

¶ 10 On January 9, 2014, plaintiff and two other ironworkers went to the staging area and

picked up a 40-foot piece of rebar, which weighed about 160 pounds and had “hooks,” i.e., bent

“L” shapes, on each end. As they carried the rebar on their shoulders, they walked by the pipe

trench and toward the rebar installation location. They had walked only about eight feet when the

hook at the front end of the rebar either hit or snagged something, causing plaintiff, who was at

-3- No. 1-18-1079

the rear, to lose his balance. He stepped to his left to regain his balance and his left foot slid

down into the pipe trench and contacted a black pipe sleeve that was in the trench. Then his left

foot slid off the pipe sleeve and became wedged in a crevice between the pipe sleeve and the

ground. Plaintiff was still carrying his end of the rebar as he pulled himself out of the trench.

Despite the pain he felt in his leg, hip and buttock area, he continued working that day and the

next day to finish the job. Thereafter, his condition worsened, and he sought medical treatment.

He did not know who had excavated the pipe trench that caused his injury or who installed the

pipe sleeve in that trench. Plaintiff had no knowledge or information regarding whether anyone

from Poli was present at the work site either on or before the date of his injury.

¶ 11 Subsequently, plaintiff sued Poli and other defendants, alleging causes of action under

theories of construction negligence, premises liability and direct negligence. Specifically,

plaintiff alleged defendants failed to reasonably inspect and properly operate, manage, maintain

and control the premises; failed to provide plaintiff with a safe workplace; failed to warn him of

the dangerous conditions; failed to provide adequate safeguards; failed to supervise the work;

placed the pipe sleeve in an unsafe location; failed to properly bury the pipe sleeve and backfill

the trench in which it was located; failed to properly protect the pipe sleeve; improperly

sequenced and coordinated the work; and failed to provide a safe work support.

¶ 12 In its answer, Poli denied plaintiff’s allegations of negligence and alleged as affirmative

defenses that plaintiff’s negligence caused his injuries; something other than Poli’s acts or

omissions caused plaintiff’s injuries; the alleged unsafe condition was open, obvious and well

known to plaintiff; any liability assessed to Poli must be reduced by plaintiff’s contributory or

comparative negligence; Poli had no duty to warn plaintiff because it had no notice of the alleged

-4- No. 1-18-1079

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chmielewski v. Kahlfeldt
606 N.E.2d 641 (Appellate Court of Illinois, 1992)
Sanchez v. Firestone Tire & Rubber Co.
604 N.E.2d 948 (Appellate Court of Illinois, 1992)
Siegel v. Village of Wilmette
756 N.E.2d 316 (Appellate Court of Illinois, 2001)
Gilbert v. Sycamore Municipal Hospital
622 N.E.2d 788 (Illinois Supreme Court, 1993)
Home Insurance v. Cincinnati Insurance
821 N.E.2d 269 (Illinois Supreme Court, 2004)
Robidoux v. Oliphant
775 N.E.2d 987 (Illinois Supreme Court, 2002)
Kalata v. Anheuser-Busch Companies, Inc.
581 N.E.2d 656 (Illinois Supreme Court, 1991)
Gyllin v. College Craft Enterprises, Ltd.
633 N.E.2d 111 (Appellate Court of Illinois, 1994)
Wojdyla v. City of Park Ridge
592 N.E.2d 1098 (Illinois Supreme Court, 1992)
Wilson v. Bell Fuels, Inc.
574 N.E.2d 200 (Appellate Court of Illinois, 1991)
American Nat. Bank & Trust Co. of Chicago v. NAT. ADVERTISING CO.
594 N.E.2d 313 (Illinois Supreme Court, 1992)
Loyola Academy v. S & S Roof Maintenance, Inc.
586 N.E.2d 1211 (Illinois Supreme Court, 1992)
Guterman Partners Energy, LLC v. Bridgeview Bank Group
2018 IL App (1st) 172196 (Appellate Court of Illinois, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
2019 IL App (1st) 181079-U, Counsel Stack Legal Research, https://law.counselstack.com/opinion/denver-v-leopardo-cos-inc-illappct-2019.