Denver & Rio Grande Western Railroad v. United States

312 F. Supp. 329, 1970 U.S. Dist. LEXIS 11761
CourtDistrict Court, D. Colorado
DecidedMay 11, 1970
DocketCiv. A. No. C-1699
StatusPublished
Cited by4 cases

This text of 312 F. Supp. 329 (Denver & Rio Grande Western Railroad v. United States) is published on Counsel Stack Legal Research, covering District Court, D. Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Denver & Rio Grande Western Railroad v. United States, 312 F. Supp. 329, 1970 U.S. Dist. LEXIS 11761 (D. Colo. 1970).

Opinion

MEMORANDUM OPINION AND ORDER

WILLIAM E. DOYLE, District Judge.

This action was commenced by plaintiffs, Denver and Rio Grande Western Railroad Company (DRGW) and Southern Pacific Company (SP) against the United States, seeking review pursuant to 28 U.S.C. § 1336 of an order of the Interstate Commerce Commission. A three-judge court was convened as required by 28 U.S.C. §§ 2284 and 2325. The Oregon Short Line Railroad Company (OSL) and the Union Pacific Railroad Company (UP), applicants in the proceedings before the Commission, were permitted to intervene as parties defendant.

In June 1967, OSL and UP applied to the Interstate Commerce Commission for a certificate of public convenience and necessity for the construction and operation of a 12.39 mile extension of trackage from their main line to a developing industrial area near the Great Salt Lake, Utah. SP and DRGW were permitted to intervene as protestants before the Commission. The bases of their opposition were that: (1) SP claimed to be a carrier already in the area; (2) there was no necessity for an additional carrier; and (3) competition resulting from the granting of the OSL-UP application would have substantial detrimental effect on both DRGW and SP.

Evidence was presented before a Commission hearing examiner who recommended that the application be denied because SP was already adequately serving the area and, therefore, the services of an additional carrier were unnecessary. The Commission did not accept the recommendation of the hearing examiner, but rather determined that applicants were entitled to a certificate. The Commission held that the present and future public convenience and necessity required that the OSL-UP application be granted. 334 I.C.C. 267 (1969). It is this order which the plaintiffs now challenge.

At this juncture there is little factual dispute. The area to be served by the proposed extension of the UP line is known as Little Mountain, located near the Great Salt Lake. It is the anticipated freight from this source which has [331]*331generated this controversy. Although presently Little Mountain is substantially undeveloped, construction has begun on facilities for the extraction and processing of minerals, such as magnesium chloride, potassium sulphate and sodium sulphate from the Great Salt Lake. By 1974 over 1,000,000 tons per year of such materials will be shipped from Little Mountain to markets throughout the country.

At the present time the UP main line runs in a north-south direction, through Ogden and Hot Springs, Utah. This line is some 13 miles east of Little Mountain development area (see map, Appendix I). UP maintains and operates an industrial spur which extends 4,650 feet west of the main line at a point just north of Hot Springs. The proposed extension would add to this spur an additional 12.39 miles of track, terminating at Little Mountain.

The SP main line runs in an east-west direction and passes directly south of Little Mountain. The eastern terminus of this line is at Ogden, some 15 miles east of Little Mountain, and its western terminus is at San Francisco. Subsequent to the filing of the UP-OSL application here in question, SP constructed a 1.7 mile spur from its main line into the industrial development area. At the present time this spur is not in use and future additions to the spur will be necessary to connect it with the various plant facilities under construction in the area.

The crucial issue according to SP is that it is, contrary to the finding of the Commission, a carrier serving the area and hence the action of the Commission in granting the UP certificate was arbitrary. This SP contention is based on its geographic contiguity — the fact that it acquired a large tract of land there in 1965 and has now built a spur to the edge of Little Mountain. According to SP this gives it a preemptive right to exclude UP, whereby the Commission had no discretion but to deny the UP application. However, SP is not now actually serving the area and the Commission treated it as new territory not being served by any railroad; that even if it were within the SP service area it was not exclusively so. At the same time the Commission and the parties proceeded on the assumption that SP was, due to its location, exempt from the requirement of a certificate and could serve the area once operations commenced. We do not see the question as one of pure law as SP contends. Rather, we regard it as a factual matter properly determinable by the Commission (and not the examiner).

The Commission found that UP could provide more efficient and economic service in transporting minerals from the Little Mountain area to virtually all points of destination. UP would be able to provide single-line service north to the Pacific Northwest, south to Southern California and east through Ogden to the Midwest. Although SP could provide single-line service to Central California, freight bound for other points would have to be transferred to other carriers at the Ogden interchange. Thus, southbound and northbound freight would be transferred to UP at Ogden, while eastbound freight would be interchanged with either UP or DRGW. Even if the UP-OSL application were denied, some 65 to 75 percent of traffic from Little Mountain would ultimately be handled by UP in interchange.

As a result of SP’s joint-line service, using the interchange at Ogden, SP transit time from Little Mountain to Portland, Oregon would be approximately 20 hours more than that of UP; SP transit time to Los Angeles would be some 15 hours more than that of UP. Transit time for both UP and SP to Council Bluffs, Iowa would be approximately the same.

Construction cost of the proposed UP extension is estimated at $1,250,000.00. The Commission found that UP would have the opportunity to net approximately $850,000.00 per year and thus recoup its investment within two years. [332]*332Furthermore, the Commission determined that SP would not be substantially harmed by the proposed UP extension because SP’s present traffic would not be diminished and the business generated by the Little Mountain facilities would be sufficient to sustain both roads.

Based upon the above evidence, the Commission arrived at the following conclusions in granting the OSL-UP certificate of convenience and necessity:

(1) Little Mountain will be more efficiently served under the UP proposal, and certain needs of the area cannot be met under SP’s joint-line arrangement;
(2) SP is not already a carrier in the Little Mountain area;
(3) SP will not be harmed by the proposed UP extension;
(4) UP will not be weakened by the expenditures for the extension because the cost is de minimus relative to UP’s total assets. The added cost is justified by the resulting public benefit;
(5) The evidence indicates that single-line service, avoiding the Ogden interchange, would be inherently faster and more efficient;
(6) Rate and service competition between UP and SP with respect to Little Mountain will provide greater assurance of dependable service and economical rates;

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Trans-American Van Service, Inc. v. United States
421 F. Supp. 308 (N.D. Texas, 1976)
Union Mechling v. United States
390 F. Supp. 391 (W.D. Pennsylvania, 1974)
Curtis, Inc. v. United States
327 F. Supp. 291 (D. Colorado, 1971)
Leesona Corporation v. Duplan Corporation
317 F. Supp. 290 (D. Rhode Island, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
312 F. Supp. 329, 1970 U.S. Dist. LEXIS 11761, Counsel Stack Legal Research, https://law.counselstack.com/opinion/denver-rio-grande-western-railroad-v-united-states-cod-1970.