Denver-Albuquerque Motor Transport, Inc. v. Galligan

358 P.2d 28, 145 Colo. 71, 1960 Colo. LEXIS 381
CourtSupreme Court of Colorado
DecidedDecember 19, 1960
Docket19234
StatusPublished
Cited by8 cases

This text of 358 P.2d 28 (Denver-Albuquerque Motor Transport, Inc. v. Galligan) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Denver-Albuquerque Motor Transport, Inc. v. Galligan, 358 P.2d 28, 145 Colo. 71, 1960 Colo. LEXIS 381 (Colo. 1960).

Opinion

Opinion by

Mr. Justice Moore.

We will refer to plaintiff in error as defendant and to defendant in error as plaintiff.

The complaint of plaintiff set forth two claims against defendant. We are concerned here only with the second claim, wherein it is alleged that as a common carrier of a shipment of beef chucks from plaintiff to consignee in Miami, Florida:

“ * * * the defendant was negligent in not delivering the perishable property (meats) within a reasonable time, and failure to deliver caused a delay of 36 hours beyond the agreed time for delivery.

“3. That due to said delay, occasioned by defendant’s failure to use reasonable dispatch, consignee refused the 'property (meats) in question, and plaintiff was forced to sell same at a loss, including telephone expense and shrinkage, of $2,841.04 in order to mitigate damages and forestall a total loss of the meats.

“4. That the negligence of the defendant in not delivering the goods in a reasonable time was the proximate cause of the damages suffered by the plaintiff in the amount of $2,841.04.”

The allegations of negligence were denied by defendant. The evidence offered by plaintiff showed the delivery of the shipment to defendant; that it was scheduled for delivery to the consignee on or before 7:00 A.M. on March 3rd, 1958; that it did not arrive until approximately thirty-six hours subsequent to the appointed time; that the delay was caused by a breakdown of the cooling system of the engine in the tractor; and that the plaintiff was forced to sell at a loss following the refusal of the consignee to accept the meat.

The evidence offered by defendant established that *73 the delay in delivery was caused by a mechanical breakdown about sixty miles east of Dallas, Texas, the equipment having operated without incident between Denver and that point; that said equipment had been recently purchased by one Buford Carter who leased it to the defendant; that prior to the trip, the tractor was test-driven for about 150 miles and appeared to be in serviceable condition; and that the equipment was checked at defendant’s terminal by the manager thereof who made a “standard check we make of all leased equipment” as prescribed by the Interstate Commerce Commission. The witness Sines, terminal manager of defendant, testified that from these inspections the equipment was in “roadworthy” condition. He was also informed by a mechanic who purported to know of the condition of the tractor because of his employment by the former owner, that it would meet all requirements of any truck line.

Defendant did not inform plaintiff concerning the breakdown and the delay occasioned thereby until the morning of March 4th. Delivery was tendered as soon as possible following the breakdown of the equipment. At the close of the evidence the trial court entered findings which included the following:

“ * * * that the equipment used for the particular trip herein at issue was second-hand equipment recently purchased, and leased to defendant a few days prior to February 28th, 1958; that the inspection given to the equipment consisted of relying on representations made by the seller of the equipment to the lessor, and a cursory inspection which consumed 10 or 15 minutes of a dispatcher’s time; that said equipment due to a loss of water broke down at Wells Point, Texas, and, as a result, the shipment could not be tendered by the carrier for delivery until approximately 48 hours after the normal time such a trip usually takes; that the shipment was refused by the consignee because of this delay; that the evidence before the Court disclosed an actual loss to the plaintiff as a result in the amount of $2,543.47; that the *74 defendant was negligent and such negligence was twofold: first, that defendant had a duty to thoroughly examine the equipment prior to using it for the first time on such a trip in transporting such merchandise; second, that it was the duty of the defendant, or its agents, to promptly notify plaintiff of such breakdown of the equipment so that plaintiff might further mitigate his damage, if possible. The defendant failed in both instances, and its negligence in so failing was the proximate cause of plaintiff’s damage.

“It is, therefore, ordered, adjudged and decreed that plaintiff have judgment against the defendant herein for the sum of $2,543.47, with interest at the legal rate from the date of filing this complaint, together with his court costs. * * * ”

We need not discuss the question of whether the trial court was correct in finding that the evidence was sufficient to show negligence on the part of defendant. An erroneous reason is not grounds for the setting aside of a correct judgment, and the question which we must determine is:

Was the trial court correct in rendering judgment against the defendant in view of all the evidence presented in the trial?

The answer is in the affirmative. Admittedly there was an unexpected delay of the shipment which was scheduled for delivery on March 3rd, 1958, at 7:00 A.M. A companion shipment of beef which left Denver at the same time was in fact delivered on schedule. True it is, that a carrier is not an insurer against delay, and ordinarily is bound to use only reasonable diligence to transport and deliver shipments. 13 C.J.S. pp. 390 and 391, section 191.

In an early case decided by this court it was held that where damage is shown to have resulted by reason of undue delay by a carrier, the burden is on the carrier to show that the delay occurred without fault on its part. Estes, et al. v. The Denver & Rio Grande Railroad Com *75 pany, 49 Colo. 378, 113 Pac. 1005. In that case we find the following language:

“(1) There was testimony to prove injury to the stock because of unnecessary delay, which resulted in an unnatural shrinkage in weight; and (2), where it appears the carrier was guilty of unnecessary delay in transporting cattle, and that they were materially damaged, the shipper makes a prima facie case. (Citing cases.)

“The burden, then, rested upon the carrier to show that the injuries for which damages were claimed resulted either from an act for which it was not responsible, or a cause from which it had legally exempted itself by special contract.” (Emphasis supplied.)

Defendant directs our attention to McKinley v. D. & R. G. W. Co., 119 Colo. 203, 201 P. (2d) 905, as authority for the proposition that where the shipper has alleged negligence as the cause of a delay in transit, the burden is upon the shipper to prove that negligence. A careful reading of that case, however, shows that there the plaintiff had pleaded specific negligence, and this court held that having alleged such negligence the burden was on the shipper to prove the same. The court there observed:

“ * * * However, when plaintiff pleads specific acts of negligence of the defendant carrier he is required to establish the negligence so specifically charged.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Branco Eastern Company v. Leffler
482 P.2d 364 (Supreme Court of Colorado, 1971)
Hellerstein v. General Rose Memorial Hospital
478 P.2d 713 (Colorado Court of Appeals, 1970)
Condakes v. Southern Pacific Co.
295 F. Supp. 121 (D. Massachusetts, 1968)
Tschudy v. Amos C. Sudler & Co.
407 P.2d 877 (Supreme Court of Colorado, 1965)
Metropolitan Industrial Bank v. Great Western Products Corp.
405 P.2d 944 (Supreme Court of Colorado, 1965)
Callaham v. Slavsky
385 P.2d 674 (Supreme Court of Colorado, 1963)
Public Employees' Retirement Ass'n v. Johnson
385 P.2d 415 (Supreme Court of Colorado, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
358 P.2d 28, 145 Colo. 71, 1960 Colo. LEXIS 381, Counsel Stack Legal Research, https://law.counselstack.com/opinion/denver-albuquerque-motor-transport-inc-v-galligan-colo-1960.