Dennis Electric, Inc. v. United States Fidelity & Guaranty Co.

219 Cal. App. 3d 1228, 269 Cal. Rptr. 26, 1990 Cal. App. LEXIS 397
CourtCalifornia Court of Appeal
DecidedApril 26, 1990
DocketB044935
StatusPublished
Cited by2 cases

This text of 219 Cal. App. 3d 1228 (Dennis Electric, Inc. v. United States Fidelity & Guaranty Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dennis Electric, Inc. v. United States Fidelity & Guaranty Co., 219 Cal. App. 3d 1228, 269 Cal. Rptr. 26, 1990 Cal. App. LEXIS 397 (Cal. Ct. App. 1990).

Opinion

Opinion

GEORGE, Acting P. J.

In Hutnick v. United States Fidelity & Guaranty Co. (1988) 47 Cal.3d 456 [253 Cal.Rptr. 236, 763 P.2d 1326], the Supreme Court held that the statute of limitations governing an action on a mechanic’s lien release bond does not apply where the surety is made a party defendant to a pending lien foreclosure action that was timely filed before the bond was recorded. In the present case, we hold that the statute of limitations also does not apply where, instead of naming the surety as a party defendant in a pending action, the lien claimant first obtains a final judgment in a lien foreclosure action that was filed before the bond was recorded and, thereafter, files a separate action against the surety to recover on the release bond. Accordingly, we reverse the trial court’s orders sustaining the surety’s demurrer to the lien claimant’s second amended complaint without leave to amend and dismissing the action.

*1231 Facts

Plaintiff Dennis Electric, Inc., the lien claimant on a mechanic’s lien (Civ. Code, § 3109 et seq.), 1 filed an action against defendant United States Fidelity & Guaranty Company to recover on a release bond. (§ 3143.) Plaintiff’s second amended complaint alleges the following.

Plaintiff, a licensed contractor, performed electrical work pursuant to written contracts and oral agreements with E&W Builders, Inc., for a total agreed price of $345,640.07. Plaintiff was paid $276,996.97, leaving an unpaid balance of $68,643.10.

On January 15, 1980, plaintiff filed a mechanic’s lien on the property where the work had been performed and, the following day, commenced an action to foreclose that lien. On April 9, 1980, and June 17, 1981, defendant issued and recorded surety bonds to release the property subject to the mechanic’s lien. 2 Plaintiff was not given notice that these bonds had been recorded, however, and remained unaware of their existence for several years.

On September 29, 1983, plaintiff obtained a judgment in its foreclosure action. On January 18, 1988, plaintiff learned of the existence of the release bonds and, on March 24, 1988, filed the present action to recover against those bonds.

Defendant filed a demurrer to plaintiff’s second amended complaint on the ground the cause of action for recovery against the release bond was barred by the four-year statute of limitations set forth in Code of Civil Procedure section 337, subdivision 1. On July 12, 1989, the superior court sustained the demurrer without leave to amend and entered an order of dismissal. 3

Discussion

Pursuant to section 3144.5, which became effective January 1, 1984, the statute of limitations governing an action for recovery against a release *1232 bond is six months. The person who records a release bond is required to notify the lienholder of the bond, and the running of the statute of limitations is tolled until such notice is given. (§ 3144.5.) 4 The plaintiffs in Hutnick v. United States Fidelity & Guaranty Co., supra, 47 Cal.3d 456, recorded a mechanic’s lien and filed an action to foreclose that lien. During the pendency of the foreclosure action, the owner of the subject property recorded a release bond and served notice on the plaintiffs as required by section 3144.5. More than six months later, plaintiffs filed an amended complaint in the foreclosure action naming the surety as a defendant and adding a cause of action on the lien release bond.

The surety demurred and obtained a judgment in its favor on the ground that suit on the release bond had not been brought within six months of the bond’s recording as required by section 3144.5. The Supreme Court reversed, holding that because the lien foreclosure action had been timely filed before the release bond was recorded, the statute of limitations contained in section 3144.5 was inapplicable where the surety was made a party to that pending suit.

The decision in Hutnick did not address the situation involved in the present case, where an action to foreclose a mechanic’s lien was timely filed before the release bond was recorded, a final judgment was obtained in that foreclosure action, and thereafter a separate action was filed to recover against the release bond. Although “an opinion is not authority for a proposition not therein considered [citation]” (Ginns v. Savage (1964) 61 Cal.2d 520, 524, fn. 2 [39 Cal.Rptr. 377, 393 P.2d 689]), in order to resolve the issues involved in the present case we seek guidance from the reasoning employed in Hutnick.

As noted in Hutnick, the mechanic’s lien law derives from our state Constitution, which directs that “the Legislature shall provide, by law, for the speedy and efficient enforcement of such liens.” (Cal. Const., art. XIV, §3.) Legislation adopted pursuant to this constitutional provision is remedial in nature and is “ ‘to be liberally construed for the protection of laborers and materialmen.’ [Citation.]” (Hutnick v. United States Fidelity & Guaranty Co., supra, 47 Cal.3d 456, 462.)

The court in Hutnick stated that “[t]he purpose of the release bond procedure is to provide a means by which, before a final *1233 determination of the lien claimant’s rights and without prejudice to those rights, the property may be freed of the lien, so that it may be sold, developed, or used as security for a loan. [Fn. omitted.]” (47 Cal.3d at p. 462.) 5 The procedure thus benefits the owner of the subject property while protecting “the lien claimant by providing an alternate source of recovery on the claim of lien. . . . The recording of the release bond does not extinguish the lien; rather, the bond is substituted for the land as the object to which the lien attaches. [Citation.]” (Id., at p. 463.) The high court was careful to note, however, that “ ‘it was not within the legislative purpose in permitting the substitution [of the bond for the subject property] to deteriorate the lienor’s rights.’ [Citations.]” (Ibid.)

The foregoing principles are fully applicable to the present case. Our decision, therefore, must give effect to the release bond procedure without deteriorating the lien claimant’s rights.

The court in Hutnick considered the facts before it and noted that the plaintiffs had “pursued a single cause of action” in “seeking to enforce their mechanic’s lien first against the liened property and subsequently against the release bond . . . .” (47 Cal.3d at p.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Torres v. Superior Court CA2/5
California Court of Appeal, 2021
Mountain Ranch Corp. v. Amalgam Enterprises, Inc.
143 P.3d 1065 (Colorado Court of Appeals, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
219 Cal. App. 3d 1228, 269 Cal. Rptr. 26, 1990 Cal. App. LEXIS 397, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dennis-electric-inc-v-united-states-fidelity-guaranty-co-calctapp-1990.