Denning v. Shepard Co.

90 A. 805, 36 R.I. 497, 1914 R.I. LEXIS 40
CourtSupreme Court of Rhode Island
DecidedJune 25, 1914
StatusPublished
Cited by2 cases

This text of 90 A. 805 (Denning v. Shepard Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Denning v. Shepard Co., 90 A. 805, 36 R.I. 497, 1914 R.I. LEXIS 40 (R.I. 1914).

Opinion

Vincent, J.

The plaintiffs are copartners, residing in Chelsea, in the Commonwealth of Massachusetts, and are engaged in business as general contractors. On September 3, 1910, they entered into a written contract with the defendant, a Rhode Island corporation, to do certain work and furnish certain materials in and about the construction and alteration of the boiler room, in the basement of the defendant’s store, located on Westminster and Clemence Streets, in the City of Providence, including the setting of boilers, etc.

The plaintiffs commenced work on September 7, 1910, and continued until September 19, 1910. On or about the last named date the plaintiffs in making some excavations for the purpose of removing the foundations of certain of the piers which sustained the weight of the building and replacing them with deeper foundations, as required by the contract, came upon a bed of quicksand or other soft or loose material which, as they allege, continued to rise, through the opening made, as fast as it was removed.

*499 Upon making this discovery the plaintiffs stopped work .and sent the following letter to the defendant’s architect:

“Chelsea, Mass., September 20, 1910.

Mr. Fred Pope,

682 Tremont Building,

Boston, Mass.

Dear Sir:

In the progress of our work on contract at The Shepard Company Store, at Providence, R. I. (contract signed September 3, 1910), we find that in going to the required •depth as called for in our contract that the soil at that depth is what is known as quicksand, and is considered by us unsafe upon which to rest pier footings, wall footings and boiler settings. Unless we receive orders from you to the contrary we will proceed with the work but will not be responsible for any settlements, etc., that may subsequently occur.

Very truly yours,

Ford & Denning.”

This letter led to a conference between Mr. Ford, one of the plaintiffs, and Mr. John Shepard, Jr., president of the ■defendant company, and was followed by a letter from Mr. Shepard to the plaintiffs as follows:

“Providence, R. I., September 22, 1910.

Messrs. Ford & Denning,

Gentlemen:

I understand that there is a disagreement between you .and the architect, Mr. Fred Pope, as to your contract liability for certain work and material which the architect considers necessary for the proper completion of the boiler room in The Shepard Company’s building, Providence, which you have contracted to build, under contract with The Shepard Company.

*500 It seems to me a question to be settled after the work is. completed instead of having the work delayed for the adjustment of your differences with the architect at this time. The Shepard Company is willing and agrees to pay you for all work and material which you are not to furnish under your contract and which you may furnish under direction of the architect necessary for the satisfactory completion of the work you have undertaken on condition that you will immediately proceed with the work as directed by the architect. The necessity of having the work rushed to completion is my only reason for this writing.

John Shepard, Jr.,

President of The Shepard Company.”

The next feature in the correspondence is the following letter from the plaintiffs to Mr. Shepard:

“Chelsea, Mass., September 29, 1910.

Mr. John Shepard,

President Shepard Company,

Providence, R. I.

We have received the following report from Mr. Charles R. Gow — Engineer who is an expert on foundations. We have in accordance with your request examined the plan of work for The Shepard Co., store, at Providence, and have had a test boring made to determine the nature of the soil which is to carry the loads imposed by the proposed work.

The layer of material upon which the pier footings are to rest is apparently rather unstable as a foundation material, consisting of a very fine wet sand which assumes the nature of a liver when disturbed. In this condition it will flow or yield under pressure and would generally speaking, be considered an undesirable material for a foundation.

There is at a distance of 13J^ ft. below the proposed footing a stratum of coarse sand and gravel 2 ft. in thickness, forming a blanket over another deposit of fine sand which contains more clay and is therefore more stable.

*501 We would advise that concrete piles, consisting of wrought iron pipes 8 in. in diameter be driven or jacked down the 13 ft. or more to the gravel stratum, when they could be washed out and filled with concrete forming a permanent concrete pile which would distribute the loads of the piers to the gravel. We would also suggest that in excavating into this fine material, 3 in. tongued and grooved sheating should be used, driven well below the bottom of the proposed excavation, so as to properly confine the sand. It will probably be necessary to enclose the entire area of proposed boiler pit in this manner in addition to the sheating required for the individual pierspits.

In the event of this manner of procuring a safe foundation be endorsed by your architect, Mr. Fred Pope, and approved by you, we will furnish labor and material necessary to complete work as above described and in conjunction with plans already prepared, by Mr. Pope.

For the additional sum of six thousand dollars ($6,000.00), making our estimate read sixteen thousand two hundred dollars ($16,200.00).

■ Yours respectfully,

(1) By these letters the plaintiff first notified the defendant of the presence of the quicksand; its unsuitability as a foundation for pier footings, wall footings and boiler settings; and expressed their intention of proceeding with the work, under the contract, unless they received orders to the contrary, at the same time disclaiming all responsibility for any settling which might subsequently occur. Mr. Shepard, acting on behalf of the defendant and being desirous that the work should proceed with all possible speed, leaving any questions which might arise, to be settled later, assured the plaintiffs that if they would go on and complete the work in a satisfactory manner The Shepard Company would pay for all work and materials furnished by them not called for by their contract.

*502 Shortly after receiving these assurances from Mr. Shepard, the plaintiffs communicated to him the result of an examination of the premises made by an engineer expert in the matter of foundations. The report of this engineer was to the effect that the quicksand or soft material before mentioned would not furnish a stable and suitable foundation for the pier footings and contained suggestions as to the manner and method in and by which proper foundations might be secured.

There was some further correspondence between the parties through their counsel and architects to all of which it will not be necessary to particularly refer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lewis v. Anchorage Asphalt Paving Co.
535 P.2d 1188 (Alaska Supreme Court, 1975)
Angel v. Murray
322 A.2d 630 (Supreme Court of Rhode Island, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
90 A. 805, 36 R.I. 497, 1914 R.I. LEXIS 40, Counsel Stack Legal Research, https://law.counselstack.com/opinion/denning-v-shepard-co-ri-1914.