Denman v. Aspen Drilling Co.

520 P.2d 1303, 214 Kan. 402, 47 Oil & Gas Rep. 312, 1974 Kan. LEXIS 353
CourtSupreme Court of Kansas
DecidedApril 6, 1974
Docket47,215
StatusPublished
Cited by5 cases

This text of 520 P.2d 1303 (Denman v. Aspen Drilling Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Denman v. Aspen Drilling Co., 520 P.2d 1303, 214 Kan. 402, 47 Oil & Gas Rep. 312, 1974 Kan. LEXIS 353 (kan 1974).

Opinion

The opinion of the court was delivered by

Fromme, J.:

This is an action for breach of a contractual obligation to drill the second of two exploratory oil wells in Ness County, Kansas. A claim in the second count of the petition was dismissed by plaintiff as shown in the pre-trial order. Therefore, we are not concerned with this claim of fraud against John Volosin, *403 president of the Aspen Drilling Company, a corporation. The claim for damages arising from the breach of the drilling agreement was tried to the court and judgment was entered in favor of the defendant, Aspen Drilling Company (Aspen). The trial court found that a drilling agreement was entered into by the parties, that Aspen breached the agreement by failing to drill the second exploratory well but that plaintiff s evidence failed to prove the measure of damages. Plaintiff has appealed.

A few background facts may be helpful. We will continue to refer to C. E. Denman as the plaintiff. Plaintiff put together a block of leases consisting of 1280 acres in Ness County, Kansas. The leases were four-year leases located in unproven “wildcat” territory. In July, 1969, plaintiff and Aspen signed a drilling agreement by which Aspen agreed to purchase the leases and pay plaintiff $4.00 per acre or a total of $5,120.00. In the assignment of these leases plaintiff reserved an overriding royalty whereby in event of production plaintiff was to receive on this royalty one-sixteenth (⅟1 6) of the seven-eighths (⅞) working interest. The leased acreage was divided into two blocks by the parties to the drilling agreement which blocks will be referred to as “A” and “B”. Aspen agreed to drill a test well on each block to test the Mississippi lime formation. Both test wells were to be completed on or before December 31, 1969. Under the agreement Aspen bound itself to pay for the leases and drill the two test wells.

Aspen paid the $5,120.00 for the leases and drilled a dry hole on block “A”. It thereafter turned the leases back to plaintiff and failed or refused to drill the second test well. Plaintiff then negotiated a drilling agreement with Thunderbird Drilling Company and assigned these same leases in exchange for an agreement to drill on block “B”. Thtmderbird refused to give plaintiff an overriding royalty interest. Before the present action was tried Thunderbird drilled a producing well on block “B”. The well was sis or eight miles from any proven production.

The issues for trial were delineated in a pre-trial conference at which Aspen contended that the customary practice in the oil exploration business gave it the right to tender back the leases and discontinue further drilling, and that, since plaintiff accepted the leases, this terminated any further obligation of Aspen under the drilling contract. If no such custom was allowed to be proven because of the provisions of the contract, Aspen contended in the al *404 ternative that the court should reform the drilling contract to conform to the understanding of the parties.

After hearing all evidence introduced at the trial the court made specific findings against the defendant Aspen on these issues. The court found no grounds for reformation, determined that the drilling contract as unambiguous and held that Aspen was bound by the terms of the drilling agreement.

There is evidence in the record to support these findings and no cross-appeal has been taken by Aspen. The defendant Aspen cannot now question these findings on appeal. (See Gould v. Robinson, 181 Kan. 66, 70, 71, 309 P. 2d 405; and Reinecker v. Board of Trustees, 198 Kan. 715, 722, 426 P. 2d 44.)

The plaintiff on appeal contends, as he did in the court below, that tire trial court erred in refusing to allow damages in an amount equal to the cost of drilling the well on block “B”. There was evidence introduced to establish the cost of drilling the well was between $18,000.00 and $20,000.00. To support his claim for damages in an amount equal to the cost of drilling a well plaintiff cites Gartner v. Missimer, 178 Kan. 566, 290 P. 2d 827, and In re Estate of Stannard, 179 Kan. 394, 295 P. 2d 610. In the alternative, plaintiff contends, if he is not entitled to the cost of drilling the well, the court should have allowed him the value of the lost overriding royalty.

There is considerable confusion in the law concerning proof of damages for breach of drilling contracts. The confusion arises from some of the terminology used in the Kansas cases, as well as in the cases of other states. (See cases collected in Anno: 4 A. L. R. 3d 284-313.) It should be understood that the rule as to the measure of damages for breach of contract is the same in drilling contracts as it is in other contracts. In Phillips & Easton Supply Co., Inc. v. Eleanor International, Inc., 212 Kan. 730, 512 P. 2d 379, the rule is iterated as follows:

“. . . The measure of damages recoverable for a breach of contract is limited to such [damages] as may fairly be considered as arising in the usual course of things from the breach itself, or as may reasonably be assumed to have been within the contemplation of the parties as the probable result of such a breach.' [Citations omitted.] The evidence allowed to support damages for breach of contract is the best evidence obtainable under the circumstances of the case to show the natural and ordinary consequences of the breach and which will enable the court or the jury to arrive at a reasonable estimate of the loss which resulted. [Citations omitted.]” (p. 738.)

*405 The measure of damages for a breach of contract are those damages which naturally arise from the breach itself or which are reasonably supposed to have been within the contemplation of the parties at die time die contract was made. (Cain Shoes, Inc. v. Gunn, 194 Kan. 381, 383, 399 P. 2d 831.)

The confusion in the cases comes from trying to equate the measure of damages with the various determinations of what is the best evidence obtainable under the circumstances of a particular case to show the natural and ordinary consequences of a particular breach. For instance, in Oil & Gas Co. v. Howerton, 111 Kan. 304, 206 Pac. 909, this court determined the best evidence to establish the measure of damages flowing from a breach of a drilling contract under the circumstances of that case was evidence which established that plaintiff had expended $4,000.00 in reliance on defendant completing the contract and that plaintiff in further reliance had transferred to the defendant certain other leases which had been sold by defendant for an additional $10,000.00 before the breach occurred. The measure of damages which that evidence tended to establish was the same measure of damages iterated above in Easton Supply Co., Inc., i. e., damages as may fairly be considered as arising in the usual course of things from the breach itself which would enable the court or jury to arrive at a reasonable estimate of the loss which resulted.

In Artwein v. Link, 108 Kan. 393, 195 Pac.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
520 P.2d 1303, 214 Kan. 402, 47 Oil & Gas Rep. 312, 1974 Kan. LEXIS 353, Counsel Stack Legal Research, https://law.counselstack.com/opinion/denman-v-aspen-drilling-co-kan-1974.