Delzar Construction Co. v. New Marian Homes Corp.

117 N.W.2d 851, 1962 N.D. LEXIS 98
CourtNorth Dakota Supreme Court
DecidedNovember 5, 1962
Docket7999
StatusPublished
Cited by19 cases

This text of 117 N.W.2d 851 (Delzar Construction Co. v. New Marian Homes Corp.) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Delzar Construction Co. v. New Marian Homes Corp., 117 N.W.2d 851, 1962 N.D. LEXIS 98 (N.D. 1962).

Opinion

*853 TEIGEN, Judge.

This is an appeal by the plaintiff, Delzer Construction Company, from a judgment dismissing plaintiff’s complaint and the defendant’s counterclaim. The case was tried to the court without a jury and a trial de novo is demanded. The appeal is from the whole judgment and the entire judgment is open for review.

The plaintiff, a contractor, brought this action against the defendant, a subdivision developer, for money damages alleged to have arisen out of contract. The defendant admits contract, pleads payment in full, and counterclaims for damages for delay.

The district court dismissed plaintiff’s complaint and defendant’s counterclaim and judgment was entered accordingly. This dispute arises over the interpretation of the contract.

There were two contracts entered into, one for the construction and installation of water mains and the other for the construction and installation of a sanitary sewer within the defendant’s subdivision known as Marian Park Second Addition to the City of Bismarck, North Dakota. This was a new development for residential housing. The defendant had secured S3 purchase orders for homes and had entered into building agreements relative thereto. It petitioned the City of Bismarck to extend its water and sanitary sewer mains into the addition. The plaintiff was the successful bidder and it entered into contracts with the defendant and the City for the work. The contracts provide for a division of the costs between the City and the defendant, the defendant assuming and agreeing to pay the costs for the water main and the sanitary sewer necessary to serve its addition and the City assuming the cost for the oversize of the systems needed for trunk line purposes. The preface of the contracts describes this. It states:

“WHEREAS, NEW MARIAN HOMES CORPORATION, a corporation, has petitioned and requested the City to extend its water and sanitary sewer mains to Marian Park Second Addition, which is now undeveloped, but which petitioner intends to develop, and
“WHEREAS, petitioner has agreed to pay for said extensions as necessary for its particular areaj and the City will pay for such extra size of said main extensions as are needed for trunk line purposes, and
“WHEREAS, a bid for .such extension of the sanitary sewer and water mains in Marian Park Second Addition has been made by . the Contractor, which is acceptable to the City and the Owner, and they desire to -provide for such work and the payment of their shares therefor, along with other work of the City alone 'contained in said bid.”

The defendant and the City, in one instrument, each contracted separately with the plaintiff for its proportion of the work and the consideration to be paid. The entire work was constructed as one unit. There were two contracts similar in format, one for the construction of the water main and the other for the construction of the sanitary sewer. .

The plaintiff construes the contracts to be on a unit price basis and claims the contract sum can be determined only after the work is completed. The defendant construes the contracts as fixed sum contracts. The issue turns upon the construction of the contracts in question.

Article Three of the contracts, provides for the contract sum. The first section of Article Three provides for work in which the defendant corporation has no interest and is to be paid for in full by the City. The second section in each of the contracts provides for the work, the cost of which is to be divided between the City and the defendant. Because each contract is identical as to form, we copy only from the water contract. It states, in part, as follows :

*854 “The Owner, New Marian Homes Corporation shall pay the Contractor according to the following schedule of approximate quantities for the performance of the following work in its addition:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

U.S. Bank Ass'n v. Koenig
2002 ND 137 (North Dakota Supreme Court, 2002)
US BANK, NATIONAL ASS'N v. Koenig
2002 ND 137 (North Dakota Supreme Court, 2002)
Production Credit Ass'n of Fargo v. Ista
451 N.W.2d 118 (North Dakota Supreme Court, 1990)
Protection & Advocacy Project of State v. Jawaski
446 N.W.2d 258 (North Dakota Supreme Court, 1989)
Bridston Ex Rel. Bridston v. Dover Corp.
352 N.W.2d 194 (North Dakota Supreme Court, 1984)
Perschke v. Burlington Northern, Inc.
311 N.W.2d 564 (North Dakota Supreme Court, 1981)
Gift v. Ehrichs
284 N.W.2d 435 (North Dakota Supreme Court, 1979)
Hamilton v. Winter
281 N.W.2d 54 (North Dakota Supreme Court, 1979)
Tallackson Potato Co., Inc. v. MTK Potato Co.
278 N.W.2d 417 (North Dakota Supreme Court, 1979)
Sugarlines Company v. American Crystal Sugar Company
594 F.2d 687 (Eighth Circuit, 1979)
St. Paul Fire & Marine Insurance Co. v. Amerada Hess Corp.
275 N.W.2d 304 (North Dakota Supreme Court, 1979)
Halverson v. Pet, Inc.
261 N.W.2d 887 (North Dakota Supreme Court, 1978)
Metcalf v. Security International Insurance Co.
261 N.W.2d 795 (North Dakota Supreme Court, 1978)
Stuart v. Secrest
170 N.W.2d 878 (North Dakota Supreme Court, 1969)
Oliver-Mercer Electric Cooperative, Inc. v. Fisher
146 N.W.2d 346 (North Dakota Supreme Court, 1966)
Prince v. Universal Underwriters Insurance Co.
143 N.W.2d 708 (North Dakota Supreme Court, 1966)
Great Lakes Pipe Line Co. v. City of Grand Forks
142 N.W.2d 126 (North Dakota Supreme Court, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
117 N.W.2d 851, 1962 N.D. LEXIS 98, Counsel Stack Legal Research, https://law.counselstack.com/opinion/delzar-construction-co-v-new-marian-homes-corp-nd-1962.