Delta Saloon v. AmeriGas Propane, L.P.

CourtDistrict Court, D. Nevada
DecidedMarch 3, 2023
Docket3:19-cv-00748
StatusUnknown

This text of Delta Saloon v. AmeriGas Propane, L.P. (Delta Saloon v. AmeriGas Propane, L.P.) is published on Counsel Stack Legal Research, covering District Court, D. Nevada primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Delta Saloon v. AmeriGas Propane, L.P., (D. Nev. 2023).

Opinion

1 UNITED STATES DISTRICT COURT 2 DISTRICT OF NEVADA 3 Case No.: 3:19-cv-000748-RCJ-CSD DELTA SALOON, INC., 4 Order Plaintiff 5 Re: ECF No. 84 v. 6 AMERIGAS PROPANE, INC., et al. 7 Defendants 8

9 Before the court is defendant AmeriGas’ motion regarding discovery dispute over Rule 10 26 disclosures and incomplete court-ordered production. (ECF No. 84.) Plaintiff Delta Saloon 11 filed a response. (ECF Nos. 86, 87.) The court then ordered the parties to further meet and confer 12 and provided a joint status update, which the parties did. (ECF Nos. 88, 89.) 13 I. BACKGROUND 14 The Delta Saloon is located in Virginia City, Nevada. Delta Saloon alleges that on March 15 11, 2019, AmeriGas refilled its propane tank in a reckless and negligent manner, which resulted 16 in an explosion on March 12, 2019, causing substantial destruction to the Delta Saloon. Delta 17 Saloon claims its damages exceed $3,000,000 in restoration, repair costs, charges, fees and 18 expenses. (ECF No. 17.) 19 In this discovery motion, AmeriGas asserts that Plaintiff: (1) failed to sufficiently update 20 its Rule 26 disclosures; and (2) failed to timely produce documents consistent with the court’s 21 December 15, 2022 order. 22 23 1 2 II. DISCUSSION 3 A. Production in Response to the Court’s December 15, 2022 Order 4 The court issued an order on December 15, 2022, requiring Delta Saloon and third parties

5 Mr. Malfitano, Bonanza, Virginia City Gaming, and Skyline Crest to produce various 6 documents. (ECF No. 81.) 7 It appears that the issues related to production in response to the court’s December 15, 8 2022, order have been resolved. Nevertheless, AmeriGas seeks an order imposing sanctions, in 9 the form of the fees associated with filing the motion and meeting and conferring to ensure 10 Plaintiff’s compliance. 11 The court declines to impose sanctions in connection with this production. Plaintiff 12 produced some 1,500 pages of documents in response to the court’s order. Some of the required 13 documents were missing, but when this was discovered by AmeriGas’ counsel, the parties 14 engaged in a productive meet and confer, and additional documents were produced. Plaintiff

15 states that as of the time the joint status update was filed, all documents have been produced, 16 except for two years of tax returns, which were identified as missing by AmeriGas. Plaintiff’s 17 counsel believes they may not exist, but he is checking with his client. 18 B. Rule 26 Disclosures 19 The parties appear to dispute whether Plaintiff’s disclosure/supplemental disclosures of 20 its damages computation and supporting documentation for Plaintiff’s “building restoration and 21 repair costs” is deficient.1 22 23 1 The second supplemental disclosure included a line item for lost profit damages in the amount of $1.8 million, even though counsel had previously represented to AmeriGas and the court that 1 1. Plaintiff’s Disclosures 2 On May 6, 2021, Plaintiff served AmeriGas with documents Bates labeled DSI1218- 3 1469, with a file named “Damages Calculations with supporting docs,” which broke down the 4 components of Plaintiff’s damages and attached supporting documents for each item. The first

5 page of the document was a spreadsheet titled “Summary of Damages,” and attached were 6 building contract, construction invoices, etc. (Jahrmarkt Decl., ECF No. 87 at 3-4 ¶ 7; ECF No. 7 87 at 10.) 8 On August 11, 2022, Plaintiff provided AmeriGas with a document titled “Delta v 9 AmeriGas – Building Restoration and Repair Costs,” with documents Bates labeled DSI4054- 10 4102, which contained 74 line items comprising the claimed $3,783,148 in restoration and repair 11 costs. According to Plaintiff’s counsel, that document included approximately 50 pages of 12 attached documents for each of the 74-line items. (Jahrmarkt Decl., ECF No. 87 at 4 § 8; ECF 13 No. 87 at 12-16.) This production was apparently made in connection with settlement 14 conversations, and this was not served as a formal supplemental disclosure. (ECF No. 89 at 4:13-

15 15.) For most of the line items, the last column identifies dates, checks, wires, and payments, but 16 they do not identify any corresponding documents by Bates label. For line items 63-74, the last 17 column states “Budgeted for Completion.” The “Budgeted for Completion” line items include: 18 structural fixtures ($185,000), electrical ($65,000), plumbing ($35,000), flooring/hard surface 19 ($35,000), fire systems ($20,000), surveillance ($35,000), painting ($20,000), debris 20 removal/cleaning ($15,000), carpet ($40,000), doors/windows ($40,000), “end of project Misc.” 21 ($ 25,000) and “Legal (Blut – mechanic’s lien suit) ($22,672). (ECF No. 87 at 14.) 22

23 Delta Saloon was not seeking lost profit damages. Delta Saloon’s counsel subsequently agreed to remove that line item; therefore, this issue is no longer in dispute. 1 In January and early February, Plaintiff served additional supplemental disclosures. 2 (Ferguson Decl., ECF No. 84-1 ¶¶ 5, 8, 12, 13.) 3 On February 22, 2023, Plaintiff served its Sixth Supplemental Disclosures. These 4 disclosures contain, among other things, a revised amount of $3,530,761 for rebuilding and

5 refurbishment costs with 73 line items. (ECF No. 89-1 at 17-18.) Again, the first 62-line items 6 reference dates, checks, and wires, but they do not identify any corresponding documents by 7 Bates label. (Id. at 18-21.) Line items 63-73 are the items described as “Budgeted for 8 Completion.” (Id. at 21.) Those line items include: structural fixtures ($140,000)2, electrical 9 ($65,000), plumbing ($30,000)3, flooring/hard surface ($22,000)4, fire systems ($25,000)5, 10 surveillance ($25,000)6, painting ($18,500)7, debris removal/cleaning ($15,000), carpet 11 ($22,500)8, doors/windows ($30,000)9, and end of project miscellaneous ($25,000). 12 From the joint status report, AmeriGas’ issues with the supplemental disclosures seem to 13 be: (1) the delay in providing them; (2) that they do not identify the supporting documents by 14 Bates label; and (3) the items identified as “budgeted for completion” and no supporting

15 documentation. 16 17 18

2 Reduced from $185,000 identified in the prior production. 19 3 Reduced from $35,000 identified in the prior production. 20 4 Reduced from $35,000 identified in the prior production. 21 5 Increased from $20,000 identified in the prior production. 6 Reduced from $35,000 in the prior production 22 7 Reduced from $20,000 in the prior production. 23 8 Reduced from $40,000 in the prior production. 9 Reduced from $40,000 in the prior production. 1 2. Rules 26 and 37 2 Pursuant to Federal Rule of Civil Procedure 26(a)(1)(A), a party must, without waiting 3 for a discovery request, provide the other parties with several things, including: “a computation 4 of each category of damages claimed by the disclosing party—who must also make available for

5 inspection and copying as under Rule 34 the documents or other evidentiary material, unless 6 privileged or protected from disclosure, on which each computation is based[.] 7 Fed. R. Civ. P. 26(a)(1)(A)(iii). “The advisory committee note to Rule 26 describes this last 8 requirement as ‘the functional equivalent of a standing Request for Production under Rule 34.’” 9 R&R Sails, Inc. v. Insurance Company of Pennsylvania, 673 F.3d 1240 (9th Cir. 2012) (citing 10 Fed. R. Civ. P. 26 advisory committee’s note to 1993 Amendments).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fonten Corp. v. Ocean Spray Cranberries, Inc.
469 F.3d 18 (First Circuit, 2006)
R & R Sails, Inc. v. Insurance Co. of Pennsylvania
673 F.3d 1240 (Ninth Circuit, 2012)
Torres v. City of Los Angeles
548 F.3d 1197 (Ninth Circuit, 2008)
Yeti by Molly Ltd. v. Deckers Outdoor Corp.
259 F.3d 1101 (Ninth Circuit, 2001)
Jackson v. United Artists Theatre Circuit, Inc.
278 F.R.D. 586 (D. Nevada, 2011)
Silvagni v. Wal-Mart Stores, Inc.
320 F.R.D. 237 (D. Nevada, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
Delta Saloon v. AmeriGas Propane, L.P., Counsel Stack Legal Research, https://law.counselstack.com/opinion/delta-saloon-v-amerigas-propane-lp-nvd-2023.