Delta Radio, Inc. v. Federal Communications Commission

387 F.3d 897, 363 U.S. App. D.C. 312, 34 Communications Reg. (P&F) 438, 2004 U.S. App. LEXIS 23261
CourtCourt of Appeals for the D.C. Circuit
DecidedNovember 5, 2004
Docket03-1295
StatusPublished
Cited by2 cases

This text of 387 F.3d 897 (Delta Radio, Inc. v. Federal Communications Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Delta Radio, Inc. v. Federal Communications Commission, 387 F.3d 897, 363 U.S. App. D.C. 312, 34 Communications Reg. (P&F) 438, 2004 U.S. App. LEXIS 23261 (D.C. Cir. 2004).

Opinion

Opinion for the Court filed by Circuit Judge SENTELLE.

SENTELLE, Circuit Judge:

Delta Radio, Inc. (“Delta”) appeals from a Federal Communications Commission’s (“FCC” or “Commission”) order denying its request for a waiver of the payment deadline of its winning auction bid. See Memorandum Opinion and Order, In re Application of Delta Radio, Inc., 18 FCC Red 16,889, 2003 WL 21976380 (F.C.C. Aug. 20, 2003) (“Order”). In the Order, the FCC held that lack of finality and “other intervening events” did not excuse late payment, either singly or in combination. Delta Radio contends that the FCC abused its discretion by failing to give Delta’s waiver application a “hard look,” inconsistently applying a strict waiver policy, and denying the waiver when there was still an outstanding application for review and the attacks of September 11, 2001 had affected the economy. Because the FCC adequately considered Delta’s arguments and applied its waiver policy consistently, we affirm the order of the Commission.

*899 I. Background

Delta’s appeal arises from its winning bid for an FM broadcast construction permit in an FCC auction. In 1998, the Commission adopted rules governing the post-auction processing of broadcast applications. See Implementation of Section 309(j) of the Communications Act — Com petitive Bidding for Commercial Broadcast and Instructional Fixed Services, 13 FCC Red 15,920, 1998 WL 483588 (F.C.C. Aug. 18, 1998) (“Implementation”). These rules are designed to “ensure that only-serious, financially qualified applicants receive licenses and construction permits, and to expedite provision of service- to the public.” In re Application of Abundant Life, 17 FCC Red 4006, 4008, 2002 WL 257352 (F.C.C. Feb. 25, 2002).

At several stages in the auction process participants are required to make payments to ensure their continued financial capability and sincerity. Before bidders may participate, they must submit an upfront payment to be held on deposit with the FCC until the end of the auction. 47 C.F.R. § 1.2106; 47 U.S.C. § 309(j)(8)(C); Implementation at 15,951. Within ten days of being notified that it is the high bidder, the auction winner must deposit a 20% down payment to prove that it is still financially capable of building a station. 47 C.F.R. at § 1.2107(b); Implementation at 15,983. The final payment deadline is set by Public Notice once the FCC has dismissed all petitions to deny the high bidder’s application. 47 C.F.R. at §§ 1.2109(a), 73.5006(d). If the auction winner is late but makes its final payment within a ten-day grace period, it will be charged an additional 5% late fee. Id. at § 1.2109(a). After ten days, the high bidder is considered in default, subject to an additional penalty charge, and the FCC may offer the permit to the next highest bidder or hold a new auction. Id. at § 1.2109(b).

The FCC considers timely payment important for several reasons: it contributes to the overall integrity of the auction process, Abundant Life, 17 FCC Red at 4012; serves as an “objective indicator” of a winning bidder’s financial qualifications, id.; and evidences the sincerity and financial capability of the winning bidder to actually “build out” its system to ensure prompt service reaches the public. See In re Mountain Solutions, Ltd., 133 FCC Red 21,983, 21,993 (1998).

In April 1995, Delta and Mondy-Burke Broadcasting Network (“MBN”) filed mutually exclusive applications for, an FM broadcast construction permit in Greensville, Missouri. This permit was to be awarded by an auction ending October 8, 1999. Public Notice, “Closed Broadcast Auction No. 25 Closes,” 14 FCC Red 17,-186, 1999 WL 812922 (F.C.C. Oct. 12, 1999). Delta placed the winning bid of $397,000 and made its post-auction down payment of $79,400. See Letter to Mr. Larry G. Fuss and Mr. Barry D. Wood, Esq. from Peter H. Doyle, Chief, Audio Division, Office of Broadcast License Policy, Media Bureau, 17 FCC Red 19,029, 19,032, 2002 WL 31175156 (F.C.C. Oct. 2, 2002). On December 10, 1999, MBN filed a petition to' deny Delta’s application, arguing that Delta had violated FCC ownership rules, was not financially qualified, and did not intend' to build the' Greenville Station but only to block competitors from doing so.' The FCC denied the petition on May 17, 2000. MBN filed an application for review of that denial on June 15, 2000. While this application was still pending and the permit had not yet been granted, the September 11 terrorist attacks on the United States occurred, triggering a sudden downturn in the national economy.

On March 7, 2002, the Media Bureau (“Bureau”) released a Public Notice stating that Delta’s final payment, as well as *900 those of two other winning bidders, would be due on March 21, 2002. Public Notice, “FCC Announces it is Prepared to Grant Broadcast Construction Permits After Final Payment is Made,” 17 FCC Red 4278, 2002 WL 355971 (F.C.C. March 7, 2002). The other two winning bidders timely paid the balance of their bids. On April 4, at the end of the ten-day grace period, Delta submitted to the Bureau a petition for reconsideration and waiver requesting either rescission of the Public Notice triggering the deadline, or a temporary waiver of the payment deadline. It argued that several factors contributed to its inability to pay, including some created or exacerbated by the FCC itself. First, Delta claimed that it was unable to secure financing due to the uncertainty of its claim on the permit because MBN’s application for review was still pending before the Commission. It also alleged that the FCC’s delayed action on this application for review exacerbated the uncertainty surrounding the permit. Delta pointed next to the economic downturn following the attacks of September 11 as the reason its financing had fallen through and argued that this was so unique as to warrant a waiver. In the alternative Delta claimed the uniqueness of all these factors occurring simultaneously should be enough to support a waiver, even if the individual factors were not. Finally, it argued that the FCC had previously granted a “de facto” waiver to another Auction 25 participant by not setting the payment date until after the award became final, and thus it would not be fair to deny a waiver to Delta. The Bureau rejected Delta’s petition on August 27, 2002 and offered the permit to MBN as the second-highest bidder, assessing a default penalty against Delta. Letter to Mr. Larry G. Fuss, et al., from Peter H. Doyle, Chief, Audio Division, Office of Broadcast License Policy, Media Bureau, 17 FCC Red 16,324, 2002 WL 1973046 (F.C.C. Aug. 27, 2002).

On September 26, 2002, Delta applied for review of the Bureau’s decision on the grounds that it used an improper standard of review and was again denied on October 2. Letter to Mr. Larry G. Fuss, et al., 17 FCC Red 19,029, 2002 WL 31175156 (F.C.C. Oct. 2, 2002).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Ricky Olson
880 F.3d 873 (Seventh Circuit, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
387 F.3d 897, 363 U.S. App. D.C. 312, 34 Communications Reg. (P&F) 438, 2004 U.S. App. LEXIS 23261, Counsel Stack Legal Research, https://law.counselstack.com/opinion/delta-radio-inc-v-federal-communications-commission-cadc-2004.