DELOACH v. Philip Morris Companies, Inc.

321 F. Supp. 2d 707, 2004 U.S. Dist. LEXIS 11060, 2004 WL 1368347
CourtDistrict Court, M.D. North Carolina
DecidedJune 4, 2004
Docket1:00 CV 01235
StatusPublished

This text of 321 F. Supp. 2d 707 (DELOACH v. Philip Morris Companies, Inc.) is published on Counsel Stack Legal Research, covering District Court, M.D. North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
DELOACH v. Philip Morris Companies, Inc., 321 F. Supp. 2d 707, 2004 U.S. Dist. LEXIS 11060, 2004 WL 1368347 (M.D.N.C. 2004).

Opinion

MEMORANDUM OPINION AND ORDER

OSTEEN, District Judge.

On April 22, 2004, this court granted preliminary approval to a settlement between Plaintiff Class and R.J. Reynolds Tobacco Co. (“Reynolds”). Prior to the approval of this settlement (the “Reynolds Settlement”), all of the other Defendants in this case reached a joint settlement with Plaintiffs. Now pending before the court is the motion of Defendant Philip Morris USA Inc. (“Philip Morris”) seeking repayment of monies recently paid to Plaintiffs, as well as notices filed by Philip Morris and Lorillard Tobacco Company (“Loril-lard”), notifying the court of the triggering of the Most Favored Nations clause of the settlement agreement they entered into with Plaintiffs.

I. FACTUAL BACKGROUND

On May 16, 2003, the Class and all Defendants except Reynolds entered into a settlement agreement (the “First Settlement Agreement”). The First Settlement Agreement contains two provisions that directly impact any later settlement between the Class and Reynolds: Section 2.1.1 and Section 7. Section 2.1.1 provides that Philip Morris was required to make a “Second Settlement Payment” of $65,000,000 “on the day before the first day of trial against [Reynolds].” (First Settlement Agreement § 2.1.1(B)(i).) The Second Settlement Payment would be modified, however, “[i]n the event that Plaintiffs and the Class reach settlements with [Reynolds] on or before the day before the first day of trial.” (Id. § 2.1.1(C).) In that event, the Second Settlement Payment would be reduced by 50 cents for each dollar received from any settlement with Reynolds (exclusive of costs and fees), and the adjusted payment would not be payable until five days after *710 the final approval of any settlement with Reynolds.

The other provision of the First Settlement Agreement relevant to any future settlements is Section 7, the Most Favored Nations clause. In pertinent part, this section provides that if a settlement is “entered into with [Reynolds] before the beginning of a trial on the merits ... this Agreement will be modified to reduce the green leaf Volume Commitment of Philip Morris USA, Lorillard and B & W.” (Id. § 7.4.)

The trial between Plaintiffs and Reynolds was scheduled to begin on April 22, 2004. On April 16, 2004, a hearing was scheduled on the parties’ pre-trial motions. The court had previously instructed the parties to be prepared to discuss settlement possibilities before being heard on their motions. The parties discussed settlement over the course of the morning of April 16 and that afternoon reported to the court that they had reached agreement on the two central terms of a settlement: a cash payment and a leaf purchase commitment. The court indicated its tentative approval of those two terms. For the first time in the entire litigation, it appeared that settlement between Plaintiffs and Reynolds was a possibility. However, the court directed that the trial would remain set as scheduled.

On April 22, at 9:00 a.m., the time scheduled to begin jury selection, court was convened and Plaintiffs’ counsel announced that a settlement had been reached and moved for its preliminary approval. The court dismissed the jury panel that had been assembled and granted its preliminary approval to the settlement. A hearing was scheduled for Friday, April 30, 2004 (later rescheduled for Monday, May 3, 2004), for the court to review the plan of notice proposed by the parties for informing the Class of the Reynolds Settlement. Prior to this hearing, Philip Morris and Lorillard filed the motion and notices that are presently under consideration. At the May 3 hearing, the parties were heard on those filings rather than the proposed notice.

II. DISCUSSION

A. The Section 2 Dispute

As noted above, Section 2.1.1 of the First Settlement Agreement allows Philip Morris to reduce the amount of its Second Settlement Payment “[i]n the event that Plaintiffs and the Class reach settlements with [Reynolds] on or before the day before the first day of trial against [Reynolds].” (First Settlement Agreement § 2.1.1(C).) Philip Morris argues that the settlement between Plaintiffs and Reynolds was reached on April 16, or at least by April 21 (the day before the first scheduled trial day) and as such Section 2.1.1(C) has been triggered. Besides seeking a reduction in the amount of the Second Settlement Payment, Philip Morris also asks the court to order that its payment (made April 21) be returned to it until five days after the Reynolds Settlement is finally approved. (See id. § 2.1.1(B)(ii).) In the alternative, Philip Morris asks the court to permit discovery on the issue of when a settlement was actually reached.

Philip Morris points to Smith v. Columbia Gas Transmission Corp., in which the Fourth Circuit affirmed a district court’s decision to enforce a settlement agreement that had been orally agreed to, but which the plaintiff ultimately refused to sign. No. 97-2786,1999 WL 198799, at *1-4 (4th Cir. Apr.9, 1999). Citing this precedent, Philip Morris argues that the Reynolds Settlement was “reached” and enforceable by at least April 21 even without the formal signing of the agreement that occurred on April 22.

Philip Morris is correct when it asserts that the essential terms of the settlement *711 were agreed to on April 16. By that afternoon, counsel for Reynolds and the Class had informed the court that an agreement had been reached whereby Reynolds would pay $33 million in cash and purchase 35 million pounds of domestic leaf for each of the next ten years. At that time, counsel indicated, however, that some details remained to be worked out and that in any event, no final agreement would be entered into before April 22.

Despite the Fourth Circuit’s holding in Smith, there is no reason to conclude that a binding settlement was reached in this case before April 22. In determining the binding nature of a settlement agreement, a court should consider “whether the agreement at issue is the type of contract that is usually put in writing.” Ciaramella v. Reader’s Digest Ass’n, Inc., 131 F.3d 320, 326 (2d Cir.1997). The magnitude of this settlement is such that the sophisticated parties involved would never have reached final agreement without a signed writing. See, e.g., Peterson v. Atlantic Funding Corp., No. 97-1680, 1998 WL 390842, at *2 (4th Cir. June 29, 1998) (noting that in an agreement of sufficient size and complexity, the parties clearly contemplate reducing the agreement to a final writing); Peterson v. Cooley, 142 F.3d 181, 186 (4th Cir.1998) (noting that “a transaction of this size and complexity [over $4 million] is normally embodied in a written contract”); Davidson Pipe Co. v. Laventhol & Horwath, No. 84 Civ. 5192, 1986 WL 2201, at **4, 8 (S.D.N.Y. Feb.11, 1986) (holding that, where an agreement included “numerous complex terms,” “the parties did not intend to be contractually bound by anything other than a final written agreement”).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Twin City Pipe Line Co. v. Harding Glass Co.
283 U.S. 353 (Supreme Court, 1931)
United States v. Jorn
400 U.S. 470 (Supreme Court, 1971)
Serfass v. United States
420 U.S. 377 (Supreme Court, 1975)
United States v. William Montoya
827 F.2d 143 (Seventh Circuit, 1987)
United States v. John Charles Richard Mentz
840 F.2d 315 (Sixth Circuit, 1988)
Pfleeger v. SWANSON
367 P.2d 406 (Oregon Supreme Court, 1961)
Walton v. City of Raleigh
467 S.E.2d 410 (Supreme Court of North Carolina, 1996)
State Ex Rel. Utilities Commission & Duke Power Co. v. Eddleman
358 S.E.2d 339 (Supreme Court of North Carolina, 1987)
Adder v. Holman & Moody, Inc.
219 S.E.2d 190 (Supreme Court of North Carolina, 1975)
Rowe v. Rowe
287 S.E.2d 840 (Supreme Court of North Carolina, 1982)
Zinn v. Walker
361 S.E.2d 314 (Court of Appeals of North Carolina, 1987)
Pratt v. Bishop
126 S.E.2d 597 (Supreme Court of North Carolina, 1962)
Peaseley v. VIRGINIA IRON, COAL AND COKE COMPANY
194 S.E.2d 133 (Supreme Court of North Carolina, 1973)
Wilkins v. Gagliardi
556 N.W.2d 171 (Michigan Court of Appeals, 1996)
Harris v. Latta
259 S.E.2d 239 (Supreme Court of North Carolina, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
321 F. Supp. 2d 707, 2004 U.S. Dist. LEXIS 11060, 2004 WL 1368347, Counsel Stack Legal Research, https://law.counselstack.com/opinion/deloach-v-philip-morris-companies-inc-ncmd-2004.