Delco Wire & Cable Co. v. Keystone Roofing Co.

80 F.R.D. 428, 27 Fed. R. Serv. 2d 65, 1978 U.S. Dist. LEXIS 15306
CourtDistrict Court, E.D. Pennsylvania
DecidedSeptember 27, 1978
DocketCiv. A. No. 77-627
StatusPublished
Cited by9 cases

This text of 80 F.R.D. 428 (Delco Wire & Cable Co. v. Keystone Roofing Co.) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Delco Wire & Cable Co. v. Keystone Roofing Co., 80 F.R.D. 428, 27 Fed. R. Serv. 2d 65, 1978 U.S. Dist. LEXIS 15306 (E.D. Pa. 1978).

Opinion

OPINION

POLLAK, District Judge.

In February, 1977, plaintiff, Delco Wire and Cable, Inc., a Pennsylvania corporation, instituted this diversity action against Keystone Roofing Company, a New Jersey corporation. The thrust of the complaint was that defendant had been engaged as a roofing contractor to install a roof on plaintiff’s building at Keystone Industrial Park in Bristol, Pennsylvania, and that defendant had botched the job, to plaintiff’s substantial loss. The averments of the complaint most particularly relevant to the motions now before the Court are these:

5. On March 5, 1976, the aforesaid property owned by plaintiff sustained substantial damage to its roof from the northwest corner to the southeast corner of same.
6. The occurrence referred to in paragraph 5 hereof and resulting damage to plaintiff’s property was caused by the negligence, carelessness and negligent omissions of defendant in:
a) constructing, erecting and installing a defectively designed roof when it knew or should have known that such defects subjected the property of plaintiff to an unreasonable risk of harm by reason of wind;
b) constructing, erecting and maintaining the roof of plaintiff’s premises in a defective and negligent fashion, and particularly failing to properly and adequately fasten insulation panels to the metal roof deck and negligently or improperly applying insufficient glue or mastic to insure that the insulation panels would adhere to the metal roof deck;

On April 6, 1977, defendant filed its answer. On the same day, defendant filed complaints against two third-party defendants, as defendant was entitled to do as of right under Federal Rule of Civil Procedure 14(a) within ten days after serving its answer. And some six weeks later, defendant moved, pursuant to Rule 24(a) of the Rules of this Court, to join an additional third-party defendant. Rule 24(a) provides as follows:

A motion by a defendant for leave to bring in a third-party defendant under F.R.Civ.P. 14(a) shall be made within six (6) months from the date of service of the moving defendant’s answer to the complaint.

Defendant’s motion to add an additional third-party defendant was granted.

[430]*430In August, 1978, sixteen months after filing its answer, defendant moved for leave to add a further third-party defendant, Reflecto-Barrier Sales Co., Inc. According to the proposed third-party complaint, Reflecto-Barrier is a Connecticut corporation which manufactured and delivered to defendant the adhesive utilized by it “in securing the insulation to the metal decking for the roof over the premises” of plaintiff’s building. The adhesive, so defendant alleges, “was defective and unreasonably inadequate by reason of the fact that due to defective manufacture, the adhesive . . . failed to properly secure the insulation to the metal decking over the roof of the premises above named. .

Reflecto-Barrier has asked this Court to deny defendant’s motion to add it as a third-party defendant. Also asserting that defendant’s “motion comes so late and is so lacking in substance as to be frivolous,” Reflecto-Barrier asks that counsel fees and costs in the sum of $500 be assessed against defendant.

As the foregoing scenario makes plain, defendant’s current motion to add ReflectoBarrier as a third-party defendant comes sixteen months after the filing of defendant’s answer. This is approximately ten months beyond the six-month grace period contemplated by Local Rule 24(a) as a discretionary enlargement of the ten days following the filing of an answer during which Federal Rule 14(a) permits the addition of third-party defendants as á matter of right.

In Goodman v. Neff, 251 F.Supp. 562, 564 (E.D.Pa.1966), the late Judge John W. Lord, Jr. explained the practice prevailing in this Court as follows:

During the six months, and following the initial ten days, the practice in this District is to grant leave to file a third-party complaint, absent a strong showing why leave should not be granted. In effect, during the six month period, the burden of persuasion is on the party who would oppose the filing of the third-party complaint.
When the six months have elapsed, Local Rule [24(a)] would seem, by its terms, to bar third-party complaints regardless of circumstances. As has been said, the cases have not construed it literally. The Rule is, however, interpreted to have the effect of placing the burden of justifying a tardy third-party complaint on the defendant who would file it.

Judge Lord’s opinion continues to be the leading discussion in this District (see Kubik v. Goldfield, 61 F.R.D. 572 [E.D.Pa.1974]) and, indeed, has given guidance elsewhere. See State Mutual Life Assur. Co. v. Arthur Andersen & Co., 65 F.R.D. 518 (S.D.N.Y.1975).

It is evident from the cases in this District that in determining the justification for motions to add third-party defendants after the six month period, the excusability of defendant’s delay in moving has not been the only factor to which attention has been addressed. There has been consideration of potential prejudice to the plaintiff and also to the proposed third-party defendant, and “whether the addition of the third-party complaint will avoid circuity of action and settle related matters in one suit,” Benetz v. Photon, 24 F.R.Serv.2d 57 (E.D.Pa.1976), or will unduly complicate the trial of the matter.

Whether the defendant bears the burden of persuasion with respect to all of these issues is not clear from the cases. But in any event, the defendant bears that burden with respect to the excusability of the defendant’s own delay — and in the present instance that is a burden which the defendant cannot sustain: Defendant seems to suggest that the question of the quality of the adhesive supplied by Reflecto-Barrier could not have been identified as an issue in the case prior to January 27, 1978 when, according to paragraph 9 of defendant’s motion, “the plaintiffs [sic] theory of liability, cold adhesive securement of insulation to metal decking was presented at depositions. . . .” But this seems hard to square with the fairly specific language of paragraph 6(b) of the complaint (“failing to properly and adequately fasten [431]*431insulation panels to the metal roof deck and negligently or improperly applying insufficient glue or mastic to insure that the insulation panels would adhere to the metal roof deck”). In any event, more than six months elapsed after the January 27, 1978 depositions before defendant moved to add Refleeto-Barrier as a third-party defendant.

Under the circumstances, I conclude that defendant has moved in unduly dilatory fashion.

Had it been otherwise — i. e., had defendant sought to introduce Refleeto-Barrier as a third-party defendant within six months after the filing of defendant’s answer — I do not think the introduction of defendant’s claim against Refleeto-Barrier would have unduly complicated the trial.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Insurance Co. of North America v. Morrison
148 F.R.D. 295 (M.D. Florida, 1993)
United States v. New Castle County
111 F.R.D. 628 (D. Delaware, 1986)
Oliner v. McBride's Industries, Inc.
106 F.R.D. 14 (S.D. New York, 1985)
Ahern v. Gaussoin
104 F.R.D. 37 (D. Oregon, 1984)
Diar v. Genesco, Inc.
102 F.R.D. 288 (N.D. Ohio, 1984)
Manglona v. Camacho
1 N. Mar. I. Commw. 820 (Northern Mariana Islands, 1983)
Afif v. RMI Co.
93 F.R.D. 429 (E.D. Pennsylvania, 1982)
Jagielski v. Package Machine Co.
93 F.R.D. 431 (E.D. Pennsylvania, 1981)
Zielinski v. Zappala
470 F. Supp. 351 (E.D. Pennsylvania, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
80 F.R.D. 428, 27 Fed. R. Serv. 2d 65, 1978 U.S. Dist. LEXIS 15306, Counsel Stack Legal Research, https://law.counselstack.com/opinion/delco-wire-cable-co-v-keystone-roofing-co-paed-1978.