Delaware Technical & Community College

Supreme Court of Delaware·Decided July 7, 2015·No. 553, 2014·Published

Opinion

IN THE SUPREME COURT OF THE STATE OF DELAWARE

DELAWARE TECHNICAL & § COMMUNITY COLLEGE, § § No. 553, 2014

Defendant-Below, § Appellant. § Court Below:

§ Superior Court of the v. § State of Delaware, in and for § Sussex County

EMORY HILL & COMPANY § § C.A. No. S12C-08-032 THG Plaintiff-Below, § Appellee. §

Submitted: June 10, 2015

Decided: July 7, 2015

Before STRINE, Chief Justice; HOLLAND and VALIHURA, Justices.

ORDER

This 7th day of July 2015, upon consideration of the parties’ briefs and the record below, it appears to the Court that:

(1) On February 18, 2014, a jury found that both Appellant Delaware Technical & Community College (“DTCC”) and Appellee Emory Hill & Company (“Emory Hill”) had breached their contractual obligations to each other. Both parties filed motions for attorneys’ fees, interest, and costs. On May 7, 2014, the Superior Court awarded Emory Hill attorneys’ fees because it deemed Emory Hill

to be the prevailing party in the breach of contract action, and rejected DTCC’s motion (the “May Opinion”).1 The May Opinion was silent on the issue of interest. On July 15, 2014, Emory Hill filed a motion to recover pre- and post-judgment interest and additional attorneys’ fees (the “July Motion”), which the Superior Court granted on August 29, 2014 (the “August Opinion”).2 (2) DTCC raises several arguments on appeal. First, it argues that Emory Hill’s July Motion was untimely under Superior Court Rule of Civil Procedure 59(d) (“Rule 59(d)”) and under Superior Court Rule of Civil Procedure 59(e) (“Rule 59(e)”). Second, it argues that Emory Hill failed to comply with 29 Del. C. § 6516(f)(4). Third, it argues that the Trial Court erred in setting the rate at which pre- and post-judgment interest would accrue. In addition to responding to the merits of DTCC’s claims, Emory Hill argues that this Court should find that DTCC waived its arguments on the rate at which interest should accrue. For the reasons stated herein, we AFFIRM the judgment below.

(3) On June 29, 2010, DTCC and Emory Hill entered into a contract (the “Contract”), which was amended on July 1, 2014 (the “Amended Contract”), to construct a building on DTCC’s campus. The Contract provided that outstanding

1 Emory Hill & Co. v. Del. Technical & Cmty. Coll., C.A. No. S12C-08-032 DI 38 (Del. Super. May 7, 2014) [hereinafter May Opinion]. 2 Emory Hill & Co. v. Del. Technical & Cmty. Coll., C.A. No. S12C-08-032 DI 52 (Del. Super. Aug. 29, 2014) [hereinafter August Opinion].

payments would be subject to a monthly interest rate of 1%, not to exceed 12% per year (the “Contract Rate”). The parties were also bound by two other agreements, the General Conditions of the Contract for Construction (the “General Conditions”) and the General Construction Contract and Specifications (the “Contract Specifications”), which governed, among other things, claims procedures.

(4) The Contract Specifications provided that the “Contract Sum and Completion Date shall be adjusted only by a fully executed Change Order.” The Amended Contract provided that DTCC “shall not be liable for payment of any change order that has not received prior written authorization.” The agreement between the parties also required that Emory Hill submit an “Application for Payment” consistent with 29 Del. C. § 6516(f)(4)(a) when requesting payments.

(5) On February 11, 2011, Emory Hill submitted a change request for additional compensation and time due to construction delays (the “Change Request”). DTCC rejected the Change Request on July 27, 2011. Because the Change Request was denied, Emory Hill did not submit an Application for Payment.

(6) On August 22, 2012, Emory Hill filed a complaint in the Superior Court against DTCC for, among other things, breach of contract. On October 1, 2012, DTCC filed its answer and asserted a counterclaim against Emory Hill for

liquidated damages stemming from Emory Hill’s delay in completing the construction project. On February 18, 2014, the jury found that Emory Hill was entitled to $54,548.12 of the $59,996.71 it claimed as damages, and that DTCC was entitled to $2,900 of the $19,500 it claimed as liquidated damages.

(7) On March 4, 2014, Emory Hill filed a timely motion under Superior Court Rule of Civil Procedure 54(f)3 to collect attorneys’ fees, costs, and interest at the Contract Rate as the prevailing party. DTCC responded on March 12, 2014, and contended that “a more accurate and reasonable characterization of this litigation is that it was a ‘draw’ in which neither party ‘prevailed’ nor ‘lost’ as a result of the verdicts entered by the jury.” In its response, DTCC did not object to the application of the Contract Rate to calculate the interest award.

(8) On March 6, 2014, DTCC filed its own motion under Rule 54(d) for attorneys’ fees, costs and interest. DTCC contended that “[p]ursuant to Section 8.2 of the contract for construction, payments due and unpaid bear interest at an annual

3 Emory Hill’s reference to Super. Ct. R. Civ. P. 54(f) was incorrect. The motion should have been made pursuant to Super. Ct. R. Civ. P. 54(d). Compare Super. Ct. R. Civ. P. 54(d) (“Costs. Except when express provision therefor is made either in a statute or in these Rules or in the Rules of the Supreme Court, costs shall be allowed as of course to the prevailing party upon application to the Court within ten (10) days of the entry of final judgment unless the Court otherwise directs.”), with Super. Ct. Civ. P. 54(f) (“Court reporter fees. The fees paid court reporters for the Court's copy of transcripts of depositions shall not be taxable costs unless introduced into evidence. Fees for other copies of such transcripts shall not be taxable costs. The production and playback costs associated with any videotape deposition may also be taxable as costs if the video deposition is introduced into evidence.”).

rate of 12% or 1% per month. In the alternative, pursuant to 6 Del. C. § 2301, the lawful rate of interest is 5% over the Federal Reserve discount rate. . . .” Emory Hill responded on March 20, 2014, and argued, among other things, that DTCC’s motion was untimely pursuant to Rule 54(d) because the motion was filed more than ten days after the final judgment. It contended that for DTCC’s motion to be timely, the motion should have been filed on or before March 4, 2014, two days before DTCC actually filed its motion.

(9) On May 7, 2014, the Trial Court found that Emory Hill was the sole prevailing party and was entitled to reasonable attorneys’ fees and costs. Despite both parties having sought pre- and post-judgment interest, the May Opinion was silent on the issue of interest.

(10) On June 11, 2014, DTCC sent Emory Hill a letter and two checks “in payment of the judgment, interest and attorneys’ fees.” DTCC calculated “post- judgment interest at the legal rate of 5.07% ($7.174 per day) from February 18, 2014 through June 6, 2014.” The letter enclosed an additional check for $50.22 representing “additional post-judgment interest through June 13th.” The letter did not address pre-judgment interest.

(11) On July 15, 2014, Emory Hill filed a motion to modify the judgment to seek unpaid pre- and post-judgment interest, and an award for additional

attorneys’ fees.4 In its July Motion, Emory Hill argued, among other things, that the interest DTCC was required to pay must be computed at the Contract Rate as opposed to the legal rate.5 After DTCC filed a response on August 8, 2014, the Superior Court held a hearing on August 26, 2014 (the “August Hearing”).6 On August 29, 2014, the Superior Court awarded Emory Hill interest calculated using the Contract Rate, and additional attorneys’ fees.

Free access — add to your briefcase to read the full text and ask questions with AI

Delaware Technical & Community College, (Del. 2015).

Delaware Technical & Community College (Delaware Technical & Community College) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Dambro v. Meyer
974 A.2d 121 (Supreme Court of Delaware, 2009)
Moffitt v. Carroll
640 A.2d 169 (Supreme Court of Delaware, 1994)
Levitt v. Bouvier
287 A.2d 671 (Supreme Court of Delaware, 1972)
Moskowitz v. Mayor & Council of Wilmington
391 A.2d 209 (Supreme Court of Delaware, 1978)
Estate of Osborn Ex Rel. Osborn v. Kemp
991 A.2d 1153 (Supreme Court of Delaware, 2010)
Brandywine Smyrna, Inc. v. Millennium Builders, LLC
34 A.3d 482 (Supreme Court of Pennsylvania, 2011)