Delaware Riverkeeper Network v. Sec Pa Dept Enviromental

Court of Appeals for the Third Circuit·Decided September 20, 2018·No. 17-1456·Unpublished

Opinion

NOT PRECEDENTIAL

UNITED STATES COURT OF APPEALS FOR THE THIRD CIRCUIT

No. 17-1456

DELAWARE RIVERKEEPER NETWORK; MAYA VAN ROSSUM, Petitioners

v.

SECRETARY PENNSYLVANIA DEPARTMENT OF ENVIRONMENTAL PROTECTION; PENNSYLVANIA DEPARTMENT OF ENVIRONMENTAL PROTECTION,

Respondents

PennEast Pipeline, Co., LLC, Intervenor

On Petition for Review of an Order of the Pennsylvania Department of Environmental Protection (File Nos. WQ02-005 & CP15-558-000)

Submitted Under Third Circuit LAR 34.1(a)

October 12, 2017

Before: CHAGARES, JORDAN, and FUENTES, Circuit Judges.

(Filed: September 20, 2018)

OPINION*

*

This disposition is not an opinion of the full court and, pursuant to I.O.P. 5.7, does not constitute binding precedent.

JORDAN, Circuit Judge.

This case concerns a pipeline project (the “Project”) owned by PennEast Pipeline Company, LLC (“PennEast”). The Project involves the construction and operation of a 120-mile interstate natural gas pipeline that will move natural gas from the Marcellus Shale region in northeastern Pennsylvania to delivery points in lower Pennsylvania and New Jersey. At issue is a decision of the Pennsylvania Department of Environmental Protection (“PADEP”) to grant to PennEast a Water Quality Certification under Section 401 of the Clean Water Act. 33 U.S.C. § 1341(a)(1). The Petitioner, Delaware Riverkeeper Network (“DRN”),1 in addition to challenging PADEP’s decision on the merits, argues that the Certification issue is not ripe for review. For the reasons that follow, we conclude that we do have jurisdiction and that DRN’s challenge to the Certification fails on the merits. I. Background A. Regulatory Background The Natural Gas Act provides a comprehensive statutory scheme for regulating the transportation and sale of natural gas in interstate commerce and gives the Federal Energy Regulatory Commission (“FERC”) exclusive jurisdiction to coordinate the federal authorizations required for pipeline construction. 15 U.S.C. §§ 717(b) and 717n(b). No natural gas company may construct a pipeline until it receives “a certificate of public convenience and necessity” from FERC. Id. § 717f(c)(1)(A). FERC

1 For simplicity, we refer to the two Petitioners – the Delaware Riverkeeper Network and Maya Van Rossum, who identifies herself as the Delaware Riverkeeper – in the singular.

may grant such a certificate if it finds that a project complies with the requirements of all relevant federal laws. Id. § 717f(e). The states also have a say. Certain regulatory authority is preserved to them under the Coastal Zone Management Act of 1972, the Clean Air Act, and the Clean Water Act. Id. § 717b(d).

FERC cannot grant a certificate of public convenience and necessity unless the affected states either waive the exercise of their regulatory power or certify that the pipeline project will comply with the Clean Water Act and other state-administered water quality standards. 33 U.S.C. § 1341(a)(1). Furthermore, states can place limitations on their certifications, which “shall become a condition on any [f]ederal license or permit,” Id. § 1341(d), including the “certificate of public convenience and necessity.” Under Pennsylvania law, PADEP is responsible for Water Quality Certifications, 35 P.S. § 691.5, and any decision of PADEP can be appealed to the Commonwealth’s Environmental Hearing Board (the “EHB”) within thirty days. 25 Pa. Code § 1021.52(a)(1), (a)(2)(i).

B. Factual Background PennEast filed an application with FERC seeking a certificate authorizing it to start constructing its pipeline. As part of that process, PennEast also submitted an application to PADEP on February 9, 2016, seeking a Water Quality Certification pursuant to Section 401 of the Clean Water Act. PADEP issued a notice of that application in the Pennsylvania Bulletin and accepted public comments for thirty days. Pa. Dep’t. of Envtl. Prot., Bureau of Water Quality Prot., No. 362-2000-001, Permitting Policy & Procedure Manual § 400 at 6. Approximately one year later, on February 7,

2017, PADEP issued the requested Certification to PennEast, subject to the conditions that the Project obtain a discharge permit, an erosion and sediment control permit, and water obstruction and encroachment permits. A notice of the approval was promptly published in the Pennsylvania Bulletin. That notice instructed aggrieved persons to petition our Court for review of the Certification.

Almost immediately, DRN filed a petition for review, and, some six months later, also filed with the EHB an appeal of PADEP’s decision. Del. Riverkeeper Network v. Dep’t of Envtl. Prot., No. 1571 C.D. 2017, 2018 WL 3637059, at *3 (Pa. Commw. Ct. Aug. 1, 2018). II. Discussion2 Despite having filed a petition for review, DRN asserts that its claims are not ripe and that we thus lack jurisdiction in this matter. In the alternative, DRN asks us to rescind the Water Quality Certification on the merits, based on a variety of claims. We addressed many of those claims in our recent decision in Delaware Riverkeeper Network v. Secretary Pennsylvania Department of Environmental Protection, Nos. 16- 2211/2212/2218/2400, --- F.3d ---, 2018 WL 4201626 (3d Cir. Sept. 4, 2018) (Riverkeeper III).

2 Our jurisdiction is disputed. See infra Section II.A. “[W]e review for arbitrary and capricious agency action.” Del. Riverkeeper Network v. Sec’y of Pa. Dept. of Envtl. Prot., 870 F.3d 171, 179 (3d Cir. 2017) (Riverkeeper II).

A. Jurisdiction We have original and exclusive jurisdiction to hear “any civil action for the review of an order or action of a [f]ederal agency … or State administrative agency … to issue, condition, or deny any permit, license, concurrence, or approval” of a permit required by the Natural Gas Act. 15 U.S.C. § 717r(d)(1). “[W]hen such agency action is made ‘reviewable by statute’, the Administrative Procedure Act authorizes a broad scope of review, without limiting courts to considering only federal law.” Riverkeeper III, 2018 WL 4201626, at *9 (internal citation omitted). Nevertheless, DRN contends that we lack jurisdiction to review its petition. Relying on Berkshire Environmental Action Team, Inc. v. Tennessee Gas Pipeline Co., LLC, 851 F.3d 105 (1st Cir. 2017), it argues that the Natural Gas Act only permits us to hear suits involving final agency actions and that PADEP’s decision is not final until the EHB has ruled on its appeal. That argument, however, is foreclosed by our decision in Riverkeeper III, 2018 WL 4201626, at *6, a case with nearly identical facts, in which we held that a decision by PADEP is a final agency action that is fully ripe for review.3 There, we held that Berkshire Environmental is inapposite because of differences between the Massachusetts law at issue in that case and Pennsylvania’s regulatory scheme. Riverkeeper III, 2018 WL 4201626, at *5. That remains true here. Unlike the decisions of the Massachusetts Department of Environmental Protection at issue in Berkshire Environmental, which were without legal

3 Moreover, even before our decision in Riverkeeper III, this suit was likely ripe.

By waiting more than thirty days to file their petition with the EHB, DRN arguably forfeited its right to appeal PADEP’s decision to the EHB, and, if that right was forfeited, PADEP’s decision was thus final. Riverkeeper II, 870 F.3d at 178.

effect until after the period to appeal had passed and where the appeal was conducted within the same agency, PADEP’s decisions are “immediately effective” and “[t]he Department and Board are entirely independent agencies.” Riverkeeper III, 2018 WL 4201626, at *5. Thus, DRN’s petition is now ripe and we have jurisdiction to review the merits of its claim.

Free access — add to your briefcase to read the full text and ask questions with AI

Delaware Riverkeeper Network v. Sec Pa Dept Enviromental, (3d Cir. 2018).

Delaware Riverkeeper Network v. Sec Pa Dept Enviromental (Delaware Riverkeeper Network v. Sec Pa Dept Enviromental) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related