Delaware, Lackawanna & Western Railroad v. Mehrhof Bros. Brick Manufacturing Co.

23 A. 170, 53 N.J.L. 205, 24 Vroom 205, 1890 N.J. LEXIS 8
CourtSupreme Court of New Jersey
DecidedNovember 15, 1890
StatusPublished
Cited by1 cases

This text of 23 A. 170 (Delaware, Lackawanna & Western Railroad v. Mehrhof Bros. Brick Manufacturing Co.) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Delaware, Lackawanna & Western Railroad v. Mehrhof Bros. Brick Manufacturing Co., 23 A. 170, 53 N.J.L. 205, 24 Vroom 205, 1890 N.J. LEXIS 8 (N.J. 1890).

Opinion

The opinion of the court was delivered by

Reed, J.

This action was brought by the Mehrhof Brothers’ Brick Manufacturing Company against the Delaware, Lackawanna and Western Railroad Company and their agents, to recover damages suffered by the plaintiffs by reason of an obstruction of navigation upon the Hackensack river.

The plaintiffs have a yard upon the banks of the Hackensack where they manufacture brick. Their market for their brick is principally New York city, Brooklyn and neighboring places down the river. Between their yard and the wharves where the cargoes of brick are discharged, is a railroad bridge spanning the Hackensack.

The bridge was built by the Morris and Essex railroad in 1869 or 1870, and by a lease the Delaware, Lackawanna [206]*206and. Western railroad is now in possession and control of said bridge in operating the railroad which crosses it.

The bridge was constructed with draws for the passage of •vessels up and down the river. In 1887, the engineers of the Delaware, Lackawanna and Western Railroad Company viewing the bridge as unsafe, the company proceeded to rebuild the structure. They commenced work upon the bridge on January 7th, and began to fill up the channels of the draw on January 14th. From that time until the evening of March 2d, following, their work blocked the river for all the ■purposes of navigation.

The plaintiffs owned six schooners engaged in the business •of carrying their brick down the river to the markets. During the early part of the winter these vessels were lying at Newark, at Staten Island and elsewhere, having been frozen up outside the river. The captains were notified when the ice broke, and on February 22d the boats came up the river as far as the bridge, at which point their passage was obstructed by the work on the bridge. The boats lay below the bridge until March 2d, when they passed through the draw and pursued their way to plaintiffs’ yard.

It is for the loss resulting to the plaintiffs from this loss of time by the boats that this action was brought.

At the trial the trial justice instructed the jury that, up to March 1st, the obstruction of the channel of the stream was warranted in law, but from the beginning of March 1st it was unwarranted, and the plaintiffs were entitled to recover damages after that period.

The jury assessed the damages at $219.60.

A number of exceptions were sealed, both to the rulings in respect to the measure of damages and also in regard to the construction given by the court to the statutes which were supposed to regulate the rights and liability of the railroad company in building and maintaining of its bridge.

The company recognized its position, namely, that it must find in some legislative delegation of power a justification for its obstruction of navigable waters. The legislation touching [207]*207this particular matter is the following: In 1857 (Pamph. L., p. 111, § 2) was passed a supplement to the charter of the Morris and Essex Railroad Company. The second section ■of the act confers power upon that corporation to erect and maintain bridges or viaducts on the line of said road over the Passaic and Hackensack rivers, making and maintaining thereon, at all times, necessary and convenient draws for the accommodation of the navigation upon said rivers. The act then goes on to specify the width and method of construction of the draws, and how they shall be lighted and attended.

In 1874 was passed a supplement to an act respecting ■bridges. Rev., p. 87, § 10. It provides that, whenever it shall be necessary to repair or rebuild any bridge or viaduct in this state, over any navigable river or water, the public ■authorities, corporation or persons so repairing or rebuilding ■such bridge or viaduct shall not be liable for damages occasioned by obstructing or stopping navigation thereby; provided, the said repairs, or rebuilding, or obstructing, or ■stopping of navigation be done between the 1st day of January and the 1st day of March; and further provided, that said repairs or rebuilding be prosecuted with all practicable dispatch; and provided further, that notice of such intended repairs or rebuilding be given at least three weeks prior to commencing the same, by publishing a notice thereof in some ■newspaper circulating in the county adjacent to such bridge or viaduct.

As has been already observed, the trial judge charged that the conduct of the railroad company in rebuilding the bridge in question was to be measured by the terms of this legislation in respect of their liability for obstructing navigation.

And in construing the provisions of the act, the court held that the railroad company were obliged to conclude their work within the period granted to it by the act of 1874; and that the period terminated on the last day of February.

One exception to this ruling was taken upon the ground that the 1st day of March is within this period by a correct ■ construction of the act.

[208]*208No case, however, has been presented where it has ever held that a period defined as between two days includes the two, or either of the two, terminal days.

Between two days does not mean on one or both of the two-days.

When this word is predicable of time, it excludes both terminal days.

A policy of insurance on goods to be shipped between two-certain days does not cover goods shipped on either of these days. Atkins v. Boylston Fire and Marine Insurance Co., 5 Metc. 439.

An affidavit that a notice had been published a certain time-between two days named excludes- the days. Bunce v. Reed, 16 Barb. 347.

A stipulation to deliver chattels between two days whenever the purchaser might call for them, gave no right to demand them on either of the terminal days. Cook v. Gray, 6 Ind. 335.

Where there are to be ten days between the day of service and the first day of the next term-, there must be ten clear days.

Time between two days is that which is intermediate, without computing any part of either of those days. Robinson v. Foster, 12 Iowa 186.

The construction of the- statute in this respect was in accordance with the plain sense of untechnical language.

The second ground of exception is, that the act of 1874 does not in all cases deprive a party of the right to repair a bridge at a time other than within the period prescribed. The argument presented upon this point is substantially this,, that the grant of power Contained in the charter of 1857, to build and maintain bridges with necessary and convenient draws, carried with it, by implication, the authority to do all acts which were essential to maintain such bridges and draws.

If the reparation of such bridge and its draw became necessary, and such reparation, by the exertion of proper care, skill and dispatch, resulted in an. obstruction of navigation, [209]*209it therefore followed that all damages springing out of this condition of-affairs are damnum absque injuria.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Williams v. Chambers
154 N.E. 295 (Indiana Court of Appeals, 1926)

Cite This Page — Counsel Stack

Bluebook (online)
23 A. 170, 53 N.J.L. 205, 24 Vroom 205, 1890 N.J. LEXIS 8, Counsel Stack Legal Research, https://law.counselstack.com/opinion/delaware-lackawanna-western-railroad-v-mehrhof-bros-brick-nj-1890.