Delaney Forge & Iron Co. v. Winnebago

105 N.W. 527, 142 Mich. 84, 1905 Mich. LEXIS 647
CourtMichigan Supreme Court
DecidedDecember 4, 1905
DocketDocket No. 77
StatusPublished
Cited by9 cases

This text of 105 N.W. 527 (Delaney Forge & Iron Co. v. Winnebago) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Delaney Forge & Iron Co. v. Winnebago, 105 N.W. 527, 142 Mich. 84, 1905 Mich. LEXIS 647 (Mich. 1905).

Opinion

McAlvay, J.

The Delaney Forge & Iron Company, of Buffalo, N. Y., brought this proceeding under section 10789, 3 Comp. Laws, against the steamer Winnebago, claiming a lien for materials furnished for use in and about the construction of the said steamer. George W. Edwards and others are intervening complainants, claiming a similar lien. The Iroquois Transportation Company, an Indiana corporation, is owner and claimant of the vessel.

This steamer was constructed and built by the Columbia Iron works in their shipyard at St. Clair, Mich., under a contract dated March 8, 1902. The contract price was $95,000, and the Columbia Iron Works was to furnish all material and labor necessary to completely construct said steamer, and deliver the same at Port Huron, Mich., on or before October 1, 1902. Of the contract price $31,000 was to be paid in cash from time to time. This contract was made with John J. Boland and Thomas J. Prindiville, and contained a provision that they, with other stockholders, would organize a corporation to be known as the “Iroquois Transportation Company,” which, for the balance of the purchase price, would execute its notes to the amount of $16,000, and issue bonds for $48,000, to be secured by mortgage upon its property. The corporation was duly organized, and the notes, bonds, and mortgage executed and delivered as agreed. It was understood that this corporation would ultimately be the owner of the steamer. Boland and Prindiville assigned the contract to this corporation April 5, 1902. Under the contract the Columbia Iron Works proceeded with the construction of the steamer. It was launched March 21, 1903, and after it was in the water the work under contract continued. On July 18, 1903, it was inspected, measured, enrolled, and licensed to be employed in domestic and foreign trade. [87]*87Said enrollment and license were issued to Columbia Iron Works, as owner. The same date an agreement was made, giving conditional possession to claimant corporation, the Iroquois Transportation Company:

For the purpose of completing and finishing up those things still remaining undone upon said steamer, and required to be done by said Iron Works by the terms of the contract for the construction of said steamer; * * * it being the sole intent and purpose of this agreement to enable the Iroquois Transportation Company to obtain immediate possession of this steamer, and without intending either to limit the extent of the obligation of said Columbia Iron Works under the original specifications.”

Final cash payment on the contract was made July 19, 1903, when the Columbia Iron Works had received the full contract price in cash, bonds, and mortgage, less $3,500, deducted as penalty provided in the contract for noncompletion of the boat within the time stipulated. On this last date a bill of sale of the steamer was made by the Columbia Iron Works to the Iroquois Transportation Company.

The claims for which liens are here sought by complainant to be enforced are for materials furnished to enter into and be used in the original construction and building of said steamer Winnebago. The materials furnished by complainant were steel forgings supplied, according to the specifications and drawings furnished, between November 24, 1902, arid July 16, 1903, as from time to time ordered by the Columbia Iron Works, upon the purchase price of which <a balance of $1,999.90 is claimed. The complaint was filed October 6, 1903, in the circuit court for Wayne county. The Iroquois Transportation Company filed a bond, entered, an appearance, and answered. The cause was heard, and a judgment rendered in favor of complainant for the full amount and costs against the Iroquois Transportation Company, claimant and owner of said steamer, and the United States Fidelity & Guaranty Company of Baltimore, Md., its surety upon the bond furnished [88]*88as provided by statute. Both parties against whom said judgment was rendered have appealed to this court, and by stipulation the cause is heard upon the testimony taken in the circuit court and returned to this court.

The first question to determine is whether the Michigan statute under which this proceeding was brought is in contravention of the Constitution of the United States. If the case is one within the admiralty and maritime jurisdiction, there is no question but that a Federal court would alone have jurisdiction,, notwithstanding the fact that the State statute in terms provided a remedy. By the Constitution the judicial powers of the United States extends to all causes of admiralty or maritime jurisdiction. The judiciary act of 1789 [U. S. Rev. Stat. § 563, subd. 8] saves to suitors in all such cases the right of a common-law remedy, where the common law is competent to give it, and declares that with this exception the Federal jurisdiction is exclusive. This,' then, would give the Federal courts exclusive jurisdiction as to the enforcement of all liens in respect to maritime contracts or maritime torts. If the lien sought to be enforced arises under a nonmaritime contract, and is created by a State statute, the authorities hold that the State courts have jurisdiction. Contracts for the building of ships, or for furnishing materials for their construction, are held by the Federal courts to be nonmaritime contracts, and therefore not within the jurisdiction of admiralty courts; and liens arising under State laws out of such contracts may be enforced in the State courts. Johnson v. Elevator Co., 119 U. S. 388; Knapp, Stout & Co. v. McCaffrey, 177 U. S. 638; The Robert W. Parsons, 191 U. S. 17; The John B. Ketcham, 2d, 97 Fed. 872; People’s Ferry Co. v. Beers, 20 How. (U. S.) 393, 401; Roach v. Chapman, 22 How. (U. S.) 129; Edwards v. Elliott, 21 Wall. (U. S.) 532. It will be observed that, while the authorities are uniform in holding that the jurisdiction of the Federal courts is exclusive in proceedings in rem arising under maritime contracts, the decisions of the State and Federal courts are just as uni[89]*89form in holding that such proceedings provided for by State statutes, arising under nonmaritime contracts, are within the jurisdiction of the State courts.

We find from proofs in the case at bar that the materials furnished were for the steamer Winnebago, and actually went into the original construction of the same, as contemplated by the original plans and specifications. The Michigan statute, in so far as it creates a lien for materials so furnished, and provides for the enforcement of such lien, does not contravene the Constitution of the United States. All the decisions make a clear distinction between those cases where the lien is for the materials furnished for the building and construction of a vessel, and where the same are furnished for repairs to a vessel.

The record shows that of these materials furnished by complainant all but four items were furnished before the date of the launching, March 21, 1903, and that these four items, one quadrant, three steel valve stems, three steel connecting rod caps, and one tiller, were furnished April 30 and July 16, 1903. These named items, from their description and the evidence, were necessary in the construction of the steamer. As is customary, the vessel was put into the water before its construction was entirely completed, and the work continued at least until July 18, 1903.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Conservation Department v. Brown
55 N.W.2d 859 (Michigan Supreme Court, 1952)
Stadler v. Ciprian
251 N.W. 404 (Michigan Supreme Court, 1933)
People Ex Rel. P. Koenig Coal Co. v. Davis
211 N.W. 36 (Michigan Supreme Court, 1926)
Swan v. Gregory
161 N.W. 933 (Michigan Supreme Court, 1917)
Siler Mill Co. v. Charles Nelson Co.
162 P. 590 (Washington Supreme Court, 1917)
Enterprise Bed Co. v. South American
160 N.W. 592 (Michigan Supreme Court, 1916)
McMorran v. Millinokett
157 N.W. 421 (Michigan Supreme Court, 1916)
Perkins v. Golden Girl
151 N.W. 660 (Michigan Supreme Court, 1915)
American Trust Co. v. W. & A. Fletcher Co.
173 F. 471 (First Circuit, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
105 N.W. 527, 142 Mich. 84, 1905 Mich. LEXIS 647, Counsel Stack Legal Research, https://law.counselstack.com/opinion/delaney-forge-iron-co-v-winnebago-mich-1905.