Delafield v. DeGrauw

9 Bosw. 1
CourtThe Superior Court of New York City
DecidedDecember 7, 1861
StatusPublished
Cited by2 cases

This text of 9 Bosw. 1 (Delafield v. DeGrauw) is published on Counsel Stack Legal Research, covering The Superior Court of New York City primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Delafield v. DeGrauw, 9 Bosw. 1 (N.Y. Super. Ct. 1861).

Opinion

By the Court—Woodruff, J.

In this view of the meaning and construction of the contract, if the cement did not pass inspection, by reason of any failure of the defendants to furnish the proper quantity in such packages as the contract called for, then the plaintiffs had not performed the contract on their'part.

The delivery and acceptance were conditional, and the rejection of the cement for just cause would defeat both.

[8]*8But we concur in the opinion of the Referee, that the frame of the contract is such that the stipulations of the parties were independent. The time of payment being fixed with reference to the actual delivery, the plaintiffs were entitled to sue for and recover the stipulated price on the expiration of the stipulated credit, without waiting to learn whether the cement had arrived in Pensacola, or even though it had never arrived there, and, a fortiori, without waiting to learn whether the cement was approved on inspection.

The delivery of the cement, and its acceptance by the defendant or the agents whom he employed to receive it, and the expiration of .the term of credit, made the plaintiff’s cause of action complete. The condition upon which the delivery and acceptance might fail, should it after-wards happen, would entitle the defendant to reclamation, but the possibility that the cement might be rejected, would not be any defense.

In this sense, the agreement of the defendant to pay for the cement was independent; although it did depend upon the delivery of the cement, it did not depend upon its passing inspection as a condition precedent to his obligation to make payment.

These views, in their application to the case before us, do not very materially differ from the conclusions of the Referee, and do not necessarily lead to any different result. This consequence, however, seems to us to follow; the failure of the cement to pass inspection, if that happened before suit brought, might be used as a defense to the action. We think it would avail the defendant as a failure of the consideration of his contract to pay therefor ; and that the defendant would not be confined to a counterclaim, for his protection. To treat it as a strict counterclaim, is to limit the defendant to the use of this rejection of the cement as an independent cause of action in his own favor, to be governed alone by the rules applicable to it, if he sued the plaintiffs for a breach of their contract.

[9]*9We think the defendant not so restricted. Eor example, suppose, by reason.of the failure of the plaintiffs properly to pack the cement, no part of it had been accepted, and the defendant had made a proper tender of redelivery thereof to them, as not satisfying the condition upon which it it was delivered and accepted, and the plaintiffs thereafter brought suit? The defense would have been perfect; not necessarily or solely on the ground that the defendant had sustained damages to the extent of the contract price—for if the cement was of any considerable value, that would not be true—but on the ground that the condition on which the delivery and acceptance were made had failed, and so the consideration for the defendant’s agreement to pay had failed, and he was therefore not bound to" pay anything. Indeed, in such case, he would not be bound to show that he had sustained any damage.- He was not bound to retain the cement if it did not satisfy the condition, and having returned that which was conditionally received, he was not liable at all. He, in such case, is in the position of one who, on the breach of the contract by the other party, rescinds and restores such party to the condition in which he was before the breach. This view of the rights of the parties is fully sustained we think, by Grant v, Johnson, (1 Seld., 247,) and does not conflict with Tompkins v. Elliot, (5 Wend., 496.)

In such case the party not in fault might, if he choose, set up the breach of contract by the other as a cause of action in his own behalf, and so make it the subject of counterclaim. What we mean is, that if the condition failed before action brought, he would not be confined to this, nor be bound to give proof of damages; he might, (if he had returned the goods or made a proper tender thereof,) use the failure of the condition as a defense to. the action. (Wiltsie v. Northam, 3 Bosw., 169 ; Gleason v. Moen, 2 Duer, 644.)

And, on the other hand, it is obvious that if he had in fact paid for the goods at the end of thirty days, and the cement was thereafter properly rejected on inspection, he [10]*10would necessarily have been driven to an action. But the same distinction would have been applicable to that as is above suggested. . He might return or tender the goods, and sue for and recover back the consideration money ; or he might sue for damages. In the first case he would not be bound to prove damages; and in the second he must show what loss he sustained. *

The defendant, by his answer herein, has set up the facts upon which he relies, both as a defense and also as constituting an affirmative cause of action or' counterclaim. And the inquiry before the Referee was properly whether he had established his case in either aspect.

. Fiest. The Referee finds that the cement was not packed in the manner required by the contract. But, as the delivery was made and the cement accepted, subject to inspection, that fact bécomes of no materiality, provided it passed inspection. The provisions of the contract itself enabled the plaintiff to pack in other than the stipulated barrels,, if the United States would accept it. The Referee, therefore, properly held that the defendant, by accepting the cement, waived the provision prescribing oak barrels, resting, however, upon the other condition that the cement should pass the proper inspection. The result was that all of the cement, except three hundred barrels, did pass inspection, and as to the cement so approved, there is an end of all question.

Second. Three hundred barrels did not pass inspection.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Doll v. Noble
18 Abb. N. Cas. 45 (New York Supreme Court, 1886)
Delafield v. De Grauw
1 Abb. Ct. App. 500 (New York Court of Appeals, 1867)

Cite This Page — Counsel Stack

Bluebook (online)
9 Bosw. 1, Counsel Stack Legal Research, https://law.counselstack.com/opinion/delafield-v-degrauw-nysuperctnyc-1861.