Deer Crest Assoc. v. Granum Partners CA6

CourtCalifornia Court of Appeal
DecidedNovember 19, 2015
DocketH039919
StatusUnpublished

This text of Deer Crest Assoc. v. Granum Partners CA6 (Deer Crest Assoc. v. Granum Partners CA6) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Deer Crest Assoc. v. Granum Partners CA6, (Cal. Ct. App. 2015).

Opinion

Filed 11/19/15 Deer Crest Assoc. v. Granum Partners CA6 NOT TO BE PUBLISHED IN OFFICIAL REPORTS California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or ordered published for purposes of rule 8.1115.

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

SIXTH APPELLATE DISTRICT

DEER CREST ASSOCIATES I, L.C., H039919 (Santa Clara County Plaintiff and Appellant, Super. Ct. No. 1-11 CV193356)

v.

GRANUM PARTNERS,

Defendant and Respondent.

In this breach of guaranty action, plaintiff Deer Crest Associates I, L.C. (Deer Crest) appeals a judgment entered in favor of defendant Granum Partners (Granum) following Granum’s successful motion for summary judgment. On appeal, Deer Crest asserts that the trial court erred in granting Granum’s summary judgment motion. We will affirm. STATEMENT OF THE FACTS AND THE CASE Deer Crest owns an expandable condominium project (the condominium project). On July 1, 2005, Deer Crest entered into a construction contract (the construction contract) with Silver Creek Development Group, L.L.C. (Silver Creek). Pursuant to the construction contract, Silver Creek agreed to perform construction work on the condominium project, including construction of a building and completion of “punch list” items, for a payment of $1,588,926.45. Silver Creek’s bid on the construction contract was based on early 2004 pricing for materials and labor. Granum executed a written guaranty (the guaranty) in connection with the construction contract. The guaranty referred to Granum as “Guarantor,” referred to Deer Crest as “Owner,” and referred to Silver Creek as “Builder.” As pertinent here, the guaranty stated that Guarantor “guarantees and promises to and for the benefit of Owner that Builder shall complete construction of the project for a price not to exceed $1,588,926.45. If the price exceeds $1,588,926.45, Builder will be responsible for payment to Builder for cost overruns.” The guaranty further provided: “Owner does not need to pursue its claim against Builder before exercising the Guaranty against Guarantor. Owner may proceed directly against Guarantor for all claims being guaranteed by Guarantor.” In October 2005, Silver Creek employees discovered a critical error in the design of the foundation. This error was the result of a mistake made by Deer Crest’s architect. The error delayed the construction project for eight months, until June 2006. Deer Crest and Silver Creek entered into a written change order for the foundation issue that added $46,000 to the price in the construction contract. During the eight-month delay, prices for materials increased due to natural disasters and demand in the construction market. From June 2006 through December 2006, it became apparent to Silver Creek’s president that holding to the 2004 bid prices would be impossible. In October 2006, Silver Creek informed Deer Crest of increased prices for stone and copper. On November 1, 2006, Silver Creek informed Deer Crest that the price of drywall had greatly increased in the past two years. Silver Creek advised Deer Crest that, given the increased prices for materials, the cost of the project would exceed the total budget. On December 4, 2006, Deer Crest sent a demand letter to Silver Creek explaining that the construction contract was a fixed-price contract. The demand letter specified that

2 “any cost overruns that are not due to change orders or caused by any conduct of [Deer Crest] are to be absorbed by the general contractor.” On December 6, 2006, Silver Creek sent an e-mail to Deer Crest in response to the demand letter. That e-mail proposed a price increase of $78,626.98, resulting in a total price of $1,667,553.43. The e-mail advised that “[t]hese monies WILL be required to complete construction.” (Capitalization in original.) Silver Creek and Deer Crest never resolved the issue of cost overruns. On February 5, 2007, Deer Crest sent Silver Creek a termination notice. Silver Creek did not complete the work described in the construction contract. Deer Crest hired another contractor to complete the construction work described in the construction contract. Deer Crest paid that contractor $1,145,222.22 to complete the work. On February 2, 2011, Deer Crest filed a complaint against Granum alleging a single cause of action for breach of guaranty. The complaint alleged that Granum was liable, under the terms of the guaranty, to pay Deer Crest $483,300.59 in cost overruns. Granum demurred to the complaint, arguing in part that it was not liable for cost overruns under the express language of the guaranty. The trial court sustained the demurrer, with leave to amend, on the ground that the complaint failed to allege sufficient facts to sustain a cause of action. Deer Crest filed a first amended complaint on October 18, 2011. The first amended complaint restated the cause of action for breach of guaranty and alleged that there was a typographical error in the guaranty. Specifically, the first amended complaint alleged that the portion of the guaranty regarding cost overruns should have stated: “If the price exceeds $1,588,926.45, Guarantor will be responsible for payment to Owner for cost overruns.”

3 On November 14, 2012, Granum moved for summary judgment on two grounds: 1) the action was barred by the statute of limitations; and 2) modification of the construction contract exonerated Granum from liability. On May 3, 2013, the trial court granted the summary judgment motion on the ground that the action was barred by the statute of limitations. On May 21, 2013, the trial court entered judgment in favor of Granum. This appeal followed. DISCUSSION Deer Crest contends that the judgment must be reversed because the trial court erred in granting summary judgment. Deer Crest makes three arguments in support of reversal: 1) the action was not barred by the statute of limitations; 2) modification of the construction contract did not exonerate Granum from liability; and 3) the trial court prejudicially erred in excluding evidence that Deer Crest offered in opposition to summary judgment. As explained below, we conclude that the trial court properly granted summary judgment on the ground that the action was barred by the statute of limitations, and we also conclude that there was no prejudicial evidentiary error. We accordingly will affirm.1 Legal Principles: Summary Judgment and the Standard of Review “Summary judgment is appropriate when all of the papers submitted show there are no triable issues of any material fact and the moving party is entitled to a judgment as a matter of law. [Citation.] ‘The purpose of the law of summary judgment is to provide courts with a mechanism to cut through the parties’ pleadings in order to determine

1 Given our conclusion that the action was barred by the statute of limitations, we need not address Deer Crest’s argument regarding exoneration. 4 whether, despite their allegations, trial is in fact necessary to resolve their dispute.’ [Citation.]” (Minish v. Hanuman Fellowship (2013) 214 Cal.App.4th 437, 444 (Minish).) “A defendant may move for summary judgment if the action has no merit. [Citation.] A defendant meets the initial burden of showing a cause of action is without merit if the defendant shows that one or more elements of the cause of action cannot be established or . . . there is a complete defense to a cause of action or the complaint. [Citation.] Once the defendant makes such a showing, the burden shifts to the plaintiff to produce evidence demonstrating the existence of a triable issue of material fact.” (Minish, supra, 214 Cal.App.4th at p.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Niederer v. Ferreira
189 Cal. App. 3d 1485 (California Court of Appeal, 1987)
Krieger v. Nick Alexander Imports, Inc.
234 Cal. App. 3d 205 (California Court of Appeal, 1991)
Claudio v. Regents of University of Cal.
35 Cal. Rptr. 3d 837 (California Court of Appeal, 2005)
Law Offices of Dixon R. Howell v. Valley
29 Cal. Rptr. 3d 499 (California Court of Appeal, 2005)
Central Building, LLC v. Cooper
26 Cal. Rptr. 3d 212 (California Court of Appeal, 2005)
Fox v. Ethicon Endo-Surgery, Inc.
110 P.3d 914 (California Supreme Court, 2005)
Ferguson v. Yaspan CA2/2
233 Cal. App. 4th 676 (California Court of Appeal, 2014)
RCA Corp. v. Hunt
133 Cal. App. 3d 903 (California Court of Appeal, 1982)
McGrory v. Applied Signal Technology, Inc.
212 Cal. App. 4th 1510 (California Court of Appeal, 2013)
Minish v. Hanuman Fellowship
214 Cal. App. 4th 437 (California Court of Appeal, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Deer Crest Assoc. v. Granum Partners CA6, Counsel Stack Legal Research, https://law.counselstack.com/opinion/deer-crest-assoc-v-granum-partners-ca6-calctapp-2015.