DeCurtis LLC v. Carnival Corporation

District Court, S.D. Florida·Decided August 18, 2021·No. 1:20-cv-22945·Unknown

Opinion

UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF FLORIDA Case No. 20-22945-Civ-SCOLA/TORRES DECURTIS LLC,

Plaintiff, v. CARNIVAL CORPORATION,

Defendant. ___________________________________________ CARNIVAL CORPORATION,

Plaintiff, v. DECURTIS CORPORATION and DECURTIS LLC,

Defendants. ___________________________________________/ ORDER ON PENDING MOTIONS TO MODIFY THE COURT’S SCHEDULING ORDER

This matter is before the Court on DeCurtis, LLC’s and DeCurtis Corporation’s (collectively, “DeCurtis”) and Carnival Corporation’s cross-motions to modify the Court’s Scheduling Order. [D.E. 166-167]. Each party filed their respective responses and replies, and therefore the motions are now ripe for disposition. After careful consideration of the motions, responses, replies, relevant authorities, and for the reasons discussed below, the motions are GRANTED in part and DENIED in part.1 I. ANALYSIS

On June 17, 2021, the Court issued an order on the pending motions to compel and directed the parties to confer and present a joint motion to modify the operative Scheduling Order. [D.E. 163 at 25]. The Court stated that, if the parties failed to reach an agreement, either party could file a motion with the hope that most, if not all, the disputes could be resolved without the expenditure of more judicial resources. The parties completed that process and have now agreed, in many respects, on a

proposed schedule. Some disputes remain and we consider each parties’ arguments in turn. Carnival says that there is no dispute that a new Scheduling Order is needed and that the parties have reached an agreement on several deadlines. That agreement ends, however, with the close of fact discovery all the way through trial. Carnival proposes a two-week trial commencing on June 20, 2022 and DeCurtis asks that the date be extended to November 15, 2022. Carnival says that good cause exists

for a modest extension, but it opposes adding unnecessary months to the schedule when there is no need to do so. Carnival points out that the parties have had significantly more time than the typical patent case and that a short extension to all deadlines should be adequate to complete any outstanding tasks. Thus, Carnival

1 On November 20, 2020, the Honorable Robert N. Scola referred all pretrial matters to the undersigned Magistrate Judge for disposition, including full authority to amend the Court’s Scheduling Order. [D.E. 102]. asks that the Court adopt its proposed deadlines in all respects and modify the Scheduling Order with dates that are commensurate with the work that needs to be performed.

DeCurtis opposes Carnival’s proposed dates because it seeks to expedite post- claim construction deadlines. DeCurtis says that this case is much more complex than the typical patent dispute and that Carnival includes unrealistic deadlines for the Court to rule on claim construction, dispositive motions, and Daubert disputes. DeCurtis mentions, for example, that Carnival wants to shorten the time between the filing of dispositive and pretrial motions with no good cause presented for that

relief. DeCurtis also accuses Carnival of failing to consider the referral of all pretrial matters to the undersigned and the time needed for either party to present objections to Judge Scola. DeCurtis says that these pretrial matters are critical and that an orderly case schedule should add at least eight weeks to the patent case track for final disposition of any objections that might arise. To demonstrate the unrealistic characteristics of Carnival’s position, DeCurtis takes aim at the proposal where it

includes one month between the filing of dispositive motions due March 18, 2022 and motions in limine due April 20, 2022. DeCurtis argues that, even if the undersigned immediately issues a Report and Recommendation (“R&R”) on the pending motions (which DeCurtis suggests is unrealistic), there is no possibility that any objections would be resolved until well after the expiration of future deadlines. Furthermore, DeCurtis proposes extending the deadline for opening expert reports to four months after the deadline for responsive claim construction briefs because otherwise the parties might conduct discovery based on two competing sets

of claim constructions. DeCurtis claims that the only way Carnival’s proposal would work is if the undersigned issues immediate rulings on claim construction and neither party objects. If, however, either party objects, Carnival’s timetable leaves no time for Judge Scola to adequately review these rulings and for the parties to comply with the remaining dates in the Scheduling Order. DeCurtis suggests that, if the Court adopts Carnival’s proposal, the Scheduling Order may have to be revisited at a later

date. For these reasons, DeCurtis asks that the Court adopt its proposed deadlines and issue a Scheduling Order that will require no additional extensions. A district court’s scheduling order may be modified only “upon a showing of good cause,” which “precludes modification unless the schedule cannot be met despite the diligence of the party seeking the extension.” Sosa v. Airprint Sys., Inc., 133 F.3d 1417, 1418 (11th Cir. 1998) (citing Fed. R. Civ. P. 16 advisory committee’s note; Johnson v. Mammoth Recreations, Inc., 975 F.2d 604, 609 (9th Cir.

1992) (“If [a] party was not diligent, the [good cause] inquiry should end.”)). “In other words, good cause exists when evidence supporting the proposed amendment would not have been discovered in the exercise of reasonable diligence until after the amendment deadline had passed.” Donahay v. Palm Beach Tours & Transp., Inc., 243 F.R.D. 697, 699 (S.D. Fla. 2007) (citing Forstmann v. Culp, 114 F.R.D. 83, 85-86 (M.D. N.C. 1987)). Further, “good cause is not shown if the amendment could have been timely made,” even if the opposing party would not be prejudiced. Id.; see also Kernal Records Oy v. Mosley, 794 F. Supp. 2d 1355, 1369 (S.D. Fla. 2011), aff’d sub nom. Kernel Records Oy v. Mosley, 694 F.3d 1294 (11th Cir. 2012) (“Diligence is

evaluated by considering the following factors: (1) whether the plaintiff failed to ascertain facts prior to filing the complaint and to acquire information during the discovery period; (2) whether the information supporting the proposed amendment was available to the plaintiff; and (3) whether even after acquiring the information the plaintiff delayed in seeking the amendment.”). Here, the parties have presented good cause for an amended Scheduling Order.

The only issue is what those revised deadlines should be. The best place to start is where the parties have reached an agreement: 1. Exchange Proposed Terms for Construction: July 12, 2021 2. Exchange Preliminary Claim Construction and Extrinsic Evidence: August 13, 2021 3. File Joint Claim Construction and Prehearing Statement: October 1, 2021 4. Complete Claim Construction Discovery: October 22, 2021 5. File Opening Claim Construction Brief and File Opening Brief Asserting Claims for Invalidity and Unenforceability: November 5, 2021 6. File Responsive Claim Construction Briefs: November 23, 2021

Free access — add to your briefcase to read the full text and ask questions with AI

DeCurtis LLC v. Carnival Corporation, (S.D. Fla. 2021).

DeCurtis LLC v. Carnival Corporation (DeCurtis LLC v. Carnival Corporation) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Kernel Records Oy v. Timothy Z. Mosley
694 F.3d 1294 (Eleventh Circuit, 2012)
Kernal Records Oy v. Mosley
794 F. Supp. 2d 1355 (S.D. Florida, 2011)
Donahay v. Palm Beach Tours & Transportation, Inc.
243 F.R.D. 697 (S.D. Florida, 2007)
Forstmann v. Culp
114 F.R.D. 83 (M.D. North Carolina, 1987)