Decker v. HOMES, INC./CONSTRUCTION MGMT.

654 S.E.2d 495, 187 N.C. App. 658, 2007 N.C. App. LEXIS 2524
CourtCourt of Appeals of North Carolina
DecidedDecember 18, 2007
DocketCOA06-150.
StatusPublished
Cited by9 cases

This text of 654 S.E.2d 495 (Decker v. HOMES, INC./CONSTRUCTION MGMT.) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Decker v. HOMES, INC./CONSTRUCTION MGMT., 654 S.E.2d 495, 187 N.C. App. 658, 2007 N.C. App. LEXIS 2524 (N.C. Ct. App. 2007).

Opinion

STEELMAN, Judge.

When the trial court applies the incorrect standard in deciding a motion to set aside an entry of default, we are required to remand the case to the trial court for application of the correct standard.

I. Factual Background

On 8 June 2001, Daniel and Susan Decker (plaintiffs) entered into an agreement to pay Homes, Inc./Construction Management & Financial Group (Homes, Inc.) to construct a new home. Homes, Inc. represented that plaintiffs would be able to move into their new home within nine months. Within eight weeks of entering into the agreement, there were delays in the commencement of construction of the home. Plaintiffs became concerned as to whether construction draws were being properly applied to the work *498 being performed. Subcontractors refused to finish work because they were not being paid by Homes, Inc. As late as January of 2003, some eighteen months after entering into the agreement, there was no certificate of occupancy for the home. Plaintiffs refused to pay monies to Homes, Inc. and had to pay subcontractors directly. In March of 2003, Homes, Inc. and Don Jones (Jones), a principal of Homes, Inc., filed a claim of lien on plaintiffs' property.

Plaintiffs filed suit against Homes, Inc., Jones and Don Heatherly in the Superior Court of Buncombe County on 6 January 2004. 1 This complaint asserted the following claims: (1) breach of contract; (2) breach of warranty; (3) negligence; (4) fraud; (5) unfair and deceptive trade practices; (6) slander of title; (7) punitive damages; and (8) declaratory and injunctive relief pertaining to the claim of lien. On 24 February 2004, the Clerk of Court entered an entry of default against all three defendants.

On 6 April 2004, plaintiffs filed a First Amended Verified Complaint, which added Bruce Storm (Storm) as a party defendant. The amended complaint also added allegations that Homes, Inc. was under-capitalized, was dominated and controlled by the individual defendants, and that the corporate identity of Homes, Inc. should be ignored. It also added a claim for civil conspiracy against the individual defendants. On 29 June 2004, the Clerk of Court entered default as to the Amended Complaint as to all defendants.

On 5 November 2004, plaintiffs filed a motion for entry of a default judgment. On 16 November 2004, the Honorable Ronald K. Payne entered default judgment "on the issue of liability in favor of Plaintiffs against Defendants Homes, Inc./Construction Management & Financial Group, Don Jones, and Bruce Storm," and directed that the case be set for trial on damages at the 18 January 2005 term of court.

On the morning that the trial was to commence, 18 January 2005, defendants filed a Motion to Set Aside Entry of Default and Default Judgment. This motion was denied in open court on 18 January 2005 by Judge Downs. The case proceeded to trial before a jury solely on the issue of damages. On 19 January 2005, the jury returned a verdict in favor of plaintiffs, awarding compensatory damages in the amount of $270,570.35, damages for unfair and deceptive trade practices of $107,408.71, and punitive damages in the amount of $250,000.00. Plaintiffs elected to treble the unfair trade practices damages in lieu of the punitive damages awarded by the jury. On 24 January 2005, Judge Downs entered judgment in the amount of $592,796.48 against defendants and further ordered that defendants' claim of lien be stricken. On 21 March 2005, the trial court awarded attorney's fees to plaintiffs' counsel. On 29 March 2005, the trial court denied defendants' motions for a new trial, relief from judgment, and to set aside default judgment. Defendants appeal.

II. Setting Aside Entry of Default

In their first argument, defendants contend that the trial court erred in denying their motion to set aside entry of default and default judgment. We hold that the trial court applied an incorrect legal standard in ruling on this motion and we remand this portion of the case for further proceedings.

"We have previously clarified that when one party fails to file an answer and the trial court enters a judgment determining the issue of liability but ordering a trial on the issue of damages, the judgment is only an entry of default rather than a default judgment." Moore v. Sullivan, 123 N.C.App. 647 , 649, 473 S.E.2d 659 , 660 (1996).

In the instant case, Judge Payne entered default judgment against defendants on the issue of liability and directed that the case be set for a jury trial on the issue of damages. Before the case went to trial, defendants filed a motion to set aside entry of default and default judgment. In denying defendants' motion to set aside the entry of default judgment, Judge Downs applied the standard of excusable neglect, and determined that *499 defendants' conduct did not rise to the level of excusable neglect.

In Pendley v. Ayers, 45 N.C.App. 692 , 263 S.E.2d 833 (1980), the Clerk of Court entered default against defendant. Subsequently, a trial judge entered an order granting judgment against defendant as to liability and setting the matter for trial on the issue of damages. Defendant moved to set aside the entry of default and "purported judgment." This motion was denied based upon the failure of defendant to show excusable neglect. In Pendley, we held:

Judge Howell was required to find whether defendant had shown good cause for setting aside the default. The test applied by Judge Howell related to setting aside a final judgment. For this reason, his order must be vacated, and the cause is remanded for a hearing to determine whether defendant has shown good cause sufficient enough to set aside the default.

Pendley, 45 N.C.App. at 696 , 263 S.E.2d at 835 .

The facts of the instant case are in all relevant aspects identical to those in Pendley. Our holding in that case is binding precedent which we are obliged to follow. In re Civil Penalty, 324 N.C. 373 , 384, 379 S.E.2d 30

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pee Dee Elec. Membership Corp. v. King
2018 NCBC 22 (North Carolina Business Court, 2018)
Swan Beach Corolla, L. L.C. v. Cnty. of Currituck
805 S.E.2d 743 (Court of Appeals of North Carolina, 2017)
Hatcher v. Matthews
789 S.E.2d 499 (Court of Appeals of North Carolina, 2016)
Ge Betz, Inc. v. Conrad
752 S.E.2d 634 (Court of Appeals of North Carolina, 2013)
Trantham v. Michael L. Martin, Inc.
745 S.E.2d 327 (Court of Appeals of North Carolina, 2013)
Webb v. McJas, Inc.
745 S.E.2d 21 (Court of Appeals of North Carolina, 2013)
Decker v. Homes, Inc.
680 S.E.2d 270 (Court of Appeals of North Carolina, 2009)
White v. Thompson
676 S.E.2d 104 (Court of Appeals of North Carolina, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
654 S.E.2d 495, 187 N.C. App. 658, 2007 N.C. App. LEXIS 2524, Counsel Stack Legal Research, https://law.counselstack.com/opinion/decker-v-homes-incconstruction-mgmt-ncctapp-2007.