Decca Design Build, Inc. v. American Automobile Insurance

77 P.3d 1251, 206 Ariz. 301
CourtCourt of Appeals of Arizona
DecidedOctober 22, 2003
Docket1 CA-CV 02-0519
StatusPublished

This text of 77 P.3d 1251 (Decca Design Build, Inc. v. American Automobile Insurance) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Decca Design Build, Inc. v. American Automobile Insurance, 77 P.3d 1251, 206 Ariz. 301 (Ark. Ct. App. 2003).

Opinion

OPINION

LANKFORD, Judge.

¶ 1 A general contractor, Decca Design Build, Inc., appeals from the superior court’s summary judgment for American Automobile Insurance Company. The superior court barred Decca’s action against American on its performance bond, issued to assure performance by a subcontractor, as untimely. Whether the action was untimely depends on when “final payment” was “due” under the subcontract. For the following reasons, we reverse.

¶ 2 The basic facts are undisputed. Decca acted as general contractor on an apartment construction project. Decca hired Precision Mechanical, Inc. as the plumbing subcontractor. American issued a performance bond to secure Precision’s performance under the subcontract.

¶3 After completion of the project, the Owner withheld payment to Decca of about $150,000 of the contract amount, and Decca sued for payment. The Owner counterclaimed, alleging defects in the construction. Decca filed a third party complaint alleging that the defects were attributable to numerous subcontractors, including Precision. Decca also brought this action against American on May 29, 2001, alleging that Precision had defaulted on its obligations under the subcontract and sought payment under the bond. ■

¶ 4 The superior court granted American’s summary judgment motion based on the untimeliness of Decca’s action against it. It determined that the final payment under the subcontract fell due more than two years before Decca filed its action on May 29, 2001. The bond requires that the action be brought within two years of the time final payment became due under the subcontract.

¶ 5 Decca timely appeals. We have jurisdiction pursuant to Arizona Revised Statutes (“A.R.S.”) section 12-2101(B) (2003).

¶ 6 The issue on appeal is whether there was a genuine, material issue of fact or question of law as to the date on which the period of limitations under the bond began to run. In reviewing a summary judgment, we “determine de novo whether there are any genuine issues of material fact and whether the trial court erred in its application of the law.” Gonzalez v. Satrustegui, 178 Ariz. 92, 97, 870 P.2d 1188, 1193 (App.1993).

¶ 7 Summary judgment is appropriate when there are no genuine issues of material fact, Orme School v. Reeves, 166 Ariz. 301, 305, 802 P.2d 1000, 1004 (1990), and “only when one inference can be drawn from the undisputed facts, and those facts show that the moving party is entitled to judgment as a matter of law.” Mohave Elec. Co-Op. Inc. v. Byers, 189 Ariz. 292, 302, 942 P.2d 451, 461 (App.1997).

¶ 8 The time for filing an action under the performance bond is prescribed by the bond. The bond states that the action must be brought within two years of when the final payment under the subcontract comes due. 1 Such limitations clauses are enforceable. See Zuckerman v. Transamerica Ins. Co., 133 Ariz. 139, 142-43, 650 P.2d 441, 444-45 (1982) (upholding an insurance policy’s one-year limitations period, which was significantly shorter than the six-year statutory period applicable to written contracts). Thus, the dispositive question is when final payment was due under the subcontract.

¶ 9 To determine when final payment fell due under the subcontract, we first look at the subcontract. The problem is that the *303 subcontract does not define “final payment.” The performance bond was drafted on a standard AIA 2 bond form. That form apparently contemplated that an AIA subcontract form — which defines final payment — would be used. However, the subcontract was not the standard AIA form and did not define “final payment.”

¶ 10 The competing interpretations of the subcontract are as follows. Decca argues that final payment is due after it receives payment from Owner for all of the work, that is, after the entire project is complete. American contends that final payment came due after Owner paid Decca for Precision’s work, adding that the Owner’s refusal to pay the balance was due to other subcontractors’ work. We determine that the former is the only reasonable interpretation.

¶ 11 Even though the subcontract does not define “final payment,” it contains payment provisions that shed light on when final payment is due. The subcontract provides for two types of payments: progress and retention payments. We first consider paragraph 111(a), the progress payment clause, of the subcontract. Paragraph 111(a) provides:

It is expressly understood and agreed that payment is dependent upon and shall not be due to the SUBCONTRACTOR until five (5) days after the occurrence of the following items, which shall be conditions precedent to payment: (i) furnishing of all necessary documents by the SUBCONTRACTOR including hen waivers as set forth in paragraph IV and “As Built” plans (ii) receipt by CONTRACTOR of contract payments from the Owner for the SUBCONTRACTOR’S work, which shall be the sole pool of funds from which payment to the SUBCONTRACTOR shall be made.

Paragraph 111(a) establishes the amount, manner, and conditions precedent that have to be met before Precision is paid for “performance of the work.” Paragraph 111(a) states that Precision will be paid a total of $589,475 payable in monthly progress payments after Precision submits necessary documents, such as lien waivers, and after Decca receives payment from Owner for “SUBCONTRACTOR’S work.” The two conditions precedent in paragraph 111(a) have been met; Precision submitted its lien waivers, and Owner paid Decca for Precision’s work. 3 Thus, Precision was entitled to the progress payments, and those payments fell due long before Decca filed this claim.

¶ 12 Progress payments are not the only payments under the subcontract, however. Paragraph 111(b), the retention clause of the subcontract, provides: “Retention in the amount of ten percent (10%) will be withheld on all progress payments through project completion, final acceptance and payment by Owner.” The subcontract clearly contemplates that a balance due in the form of retention will remain after all progress payments have been made. Paragraph 111(b) thus states that Decca will not pay the full balance until the conditions of paragraph IH(b) are met.

¶ 13 We now consider whether, under the subcontract, this payment of the balance in the form of retention constitutes “final” payment. For the reasons that follow, we hold that the retention payment is the final payment under the subcontract.

¶ 14 First, the parties agree that final payment includes retention amounts. 4 Second, even though the subcontract does not define “final payment,” the meaning of “final” is unambiguous. “Final” means: “not to be altered or undone ... being the last in a series, process or progress ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Able Distributing Co. v. James Lampe
773 P.2d 504 (Court of Appeals of Arizona, 1989)
Gonzalez v. Satrustegui
870 P.2d 1188 (Court of Appeals of Arizona, 1994)
Orme School v. Reeves
802 P.2d 1000 (Arizona Supreme Court, 1990)
Zuckerman v. Transamerica Insurance
650 P.2d 441 (Arizona Supreme Court, 1982)
Mohave Electric Cooperative, Inc. v. Byers
942 P.2d 451 (Court of Appeals of Arizona, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
77 P.3d 1251, 206 Ariz. 301, Counsel Stack Legal Research, https://law.counselstack.com/opinion/decca-design-build-inc-v-american-automobile-insurance-arizctapp-2003.