Debola George and Gifted Kids Child Care and Learning Center, Inc. v. Colony Builders, Inc.

CourtCourt of Appeals of Texas
DecidedJanuary 28, 2014
Docket01-13-00010-CV
StatusPublished

This text of Debola George and Gifted Kids Child Care and Learning Center, Inc. v. Colony Builders, Inc. (Debola George and Gifted Kids Child Care and Learning Center, Inc. v. Colony Builders, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Debola George and Gifted Kids Child Care and Learning Center, Inc. v. Colony Builders, Inc., (Tex. Ct. App. 2014).

Opinion

Opinion issued January 28, 2014

In The

Court of Appeals For The

First District of Texas ———————————— NO. 01-13-00010-CV ——————————— DEBOLA GEORGE AND GIFTED KIDS CHILD CARE AND LEARNING CENTER, INC., Appellants V. COLONY BUILDERS, INC., Appellee

On Appeal from the County Civil Court at Law No. 2 Fort Bend County, Texas Trial Court Case No. 12-CCV-047454

MEMORANDUM OPINION

Appellee, Colony Builders, Inc. (“Colony Builders”), sued appellants,

Debola George and Gifted Kids Child Care and Learning Center, Inc. (collectively,

“George”), for breach of contract arising out a construction agreement. At trial, Colony Builders sought to enter deemed admissions into evidence. George

objected but did not file a written objection or motion to withdraw the deemed

admissions. The trial court overruled George’s objection, allowed the trial to

proceed, and then entered judgment in favor of Colony Builders, awarding it

$27,204 on its breach of contract claim and $10,000 in attorney’s fees. In her sole

issue on appeal, George argues that the trial court erred in considering the deemed

admissions over her objection because she presented evidence at trial contradicting

the deemed admissions to which Colony Builders did not object. George also

argues that Colony Builders waived the ability to rely on the deemed admissions.

We affirm.

Background

On September 12, 2011, George entered into a construction agreement with

Colony Builders to build out a property that she intended to use to operate a

daycare business (“Construction Agreement”). The Construction Agreement

provided the specifications for the daycare build-out project (“the Project”). It

provided that George would pay $30,000 up front, “6 payments of $3,850

including [a] $1,100 Finance Charge,” and $20,000 “upon Rough In Inspection.”

George paid the $30,000 down payment, and Colony Builders began work

on the Project and completed many of the specified tasks, including procuring

drawings and permits, completing the “rough in” for plumbing and electrical

2 fixtures, and roughing in classrooms, the kitchen, and an office. When Colony

Builders sought further payment under the terms of the contract, George refused to

pay, stating that the building was taking too long. 1 She eventually locked Colony

Builders out of the Project and hired another contractor to finish the build-out for

the daycare.

On March 5, 2012, Colony Builders sued George for suit on an open account

and breach of contract, alleging that it provided goods and services under the

Construction Agreement, that George accepted the goods and services and became

bound to pay, and that she defaulted on that obligation and breached the agreement

by failing to pay. Colony Builders also sought attorney’s fees. With its original

petition, Colony Builders served several requests for admissions on George.

George answered with a general denial. She did not file responses to the

requests for admission.

Colony Builders moved for summary judgment on its claims. It argued that

the affidavit of Ali Zare, Colony Builders’ representative, and its accompanying

1 George testified at trial that she told Colony Builders that time was of the essence in the project and that she wanted the daycare to be ready to open by a certain date. Ali Zare, Colony Builders’ representative, testified that he was not aware of these facts, and the Construction Agreement is silent both on the question of whether time was of the essence and on any specific deadline for completion of the Project. 3 exhibits, 2 along with the admissions deemed against George, established that

Colony Builders “provided labor and materials pursuant to its agreement with

[George], and that [George] [has] failed and refused to pay for those services per

their agreement.” It further argued that Zare’s affidavit and the deemed admissions

“establish that value of those services provided for which [Colony Builders] has

not been paid is $27,204.00.”

George responded to the motion for summary judgment in writing, arguing

in part that the deemed admissions had “since been answered.” George filed her

own affidavit contradicting some of the facts raised in Colony Builders’ motion.

However, the record does not include the answers to the requests for admissions.

Nor did George file a written motion to withdraw the deemed admissions. The

trial court denied Colony Builders’ motion for summary judgment, and the case

proceeded to trial. The record does not contain a transcript of the hearing on the

motion for summary judgment.

At the bench trial, Colony Builders offered, as its first exhibit, a copy of its

requests for admissions and argued that the trial court should consider the

admissions deemed against George. Colony Builders argued that the requests for

admissions had been properly served on George on March 5, 2012, and that she did

2 The exhibits included receipts and other records demonstrating Colony Builders’ expenses for the Project, including materials used and expenses for subcontractors and other workmen. 4 not respond. Colony Builders offered into evidence the following relevant deemed

admissions: that Colony Builders sold George “goods, wares, merchandise or

services” as described in the Construction Agreement; that George “accepted

goods, wares, merchandise or services” under the Construction Agreement; that the

prices Colony Builders charged for the goods and services it provided to George

were the prices agreed to by George and were the usual and customary prices for

those services at the time they were delivered in the county where they were

delivered; that the principal amount due to Colony Builders from George for the

goods or services provided under the Construction Agreement was $27,204 after

applying any credits to which George was entitled; that Colony Builders had

presented a request for payment according to the terms of the Construction

Agreement but George had refused to pay; that the “goods, wares, merchandise or

services received by [George] from [Colony Builders] conformed to all

representations and warranties made”; and that George “never rejected, disputed or

returned” the goods or services provided by Colony Builders.

George objected to admission of her deemed admissions, arguing that she

had responded to the deemed admissions prior to trial on July 5, 2012. However,

those responses are not included in the record on appeal. George also

acknowledged that she never moved for the deemed admissions to be withdrawn,

but she asked the court for leave “to make an oral motion to strike based on the fact

5 if you look at the totality of the cases [George] has a reasonable defense to [Colony

Builders’] claims. . . .”

The trial court overruled George’s objection and allowed Colony Builders to

present evidence of the admissions deemed to have been made by George. 3

Both parties presented testimony regarding the extent and nature of the work

performed on the Project. Ali Zare, Colony Builders’ representative, testified that

Colony Builders performed work on the Project in accordance with the

Construction Agreement until George locked the contractors out of the property

and terminated the Construction Agreement. Zare provided specific testimony

regarding the exact work completed by Colony Builders, its expenses related to the

Project, its overhead expenses, and its usual profit margin.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wheeler v. Green
157 S.W.3d 439 (Texas Supreme Court, 2005)
Boulet v. State
189 S.W.3d 833 (Court of Appeals of Texas, 2006)
Wal-Mart Stores, Inc. v. Deggs
968 S.W.2d 354 (Texas Supreme Court, 1998)
USAA County Mutual Insurance Co. v. Cook
241 S.W.3d 93 (Court of Appeals of Texas, 2007)
Maswoswe v. Nelson
327 S.W.3d 889 (Court of Appeals of Texas, 2010)
Webb v. Ray
944 S.W.2d 458 (Court of Appeals of Texas, 1997)
Marshall v. Vise
767 S.W.2d 699 (Texas Supreme Court, 1989)
Carpenter v. Cimarron Hydrocarbons Corp.
98 S.W.3d 682 (Texas Supreme Court, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
Debola George and Gifted Kids Child Care and Learning Center, Inc. v. Colony Builders, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/debola-george-and-gifted-kids-child-care-and-learn-texapp-2014.